# US 2016/0145815 A1 · Method for pre-stressing a steel structure, and steel structure pre-stressed using said method

> Agents: this data is available as JSON from the patentgrep API and MCP server — see https://patentgrep.com/llms.txt

- Number: US 2016/0145815 A1
- Document ID: US20160145815A1
- Status: Published application
- Kind: A1
- Application number: 14/898,452
- Filed: 2014-04-16
- Published: 2016-05-26
- Earliest claimed: 2013-05-14
- Assignees: S&P Clever Reinforcement Company AG
- Applicants: S&P Clever Reinforcement Company AG
- Inventors: Masoud Motavalli; Elyas Ghafoori
- Web page: https://patentgrep.com/patent/US20160145815A1

## CPC

- E01D 22/00: Methods or apparatus for repairing or strengthening existing bridges {(electrochemical desalination or re-alkalisation C04B41/00); Methods or apparatus for dismantling bridges}
- E01D 6/00: Truss-type bridges
- E04B 1/24: the supporting parts consisting of metal
- E04C 3/10: prestressed
- E04C 5/085: {Tensile members made of fiber reinforced plastics}
- E04G 23/0218: {Increasing or restoring the load-bearing capacity of building construction elements (E04G23/0203 and E04G23/0266 take precedence)}
- E01D 2101/32: prestressed
- E01D: CONSTRUCTION OF BRIDGES, {ELEVATED ROADWAYS} OR VIADUCTS; ASSEMBLY OF BRIDGES (bridges extending between terminal buildings and aircraft for embarking or disembarking passengers B64F1/305; {tracks for special kinds of railways E01B25/00; culverts E01F5/005})
- E04B: GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS (border constructions of opening in walls, floors or ceilings E06B1/00; {electromagnetic shielding H05K9/0001})
- E04C: STRUCTURAL ELEMENTS; BUILDING MATERIALS (for bridges E01D; specially designed for insulation or other protection E04B; elements used as building aids E04G; for mining E21; for tunnels E21D; structural elements with broader range of application than for building engineering F16, particularly F16S)
- E04G: SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS

## Abstract

According to the method, at least one carbon fibre-reinforced polymer band is joined to the steel structure at the end regions thereof, capable of transferring tensile forces. Subsequently, at least one lifting element (7) disposed between the carbon fibre-reinforced polymer band (4) and the steel girder (3) to be reinforced in a region between these end anchorages (5), is extended substantially perpendicular to the carbon fibre-reinforced polymer band (4). So, a tensile force stress is generated between the end regions of the carbon fibre-reinforced polymer band (4). Then, a steel girder treated in such a manner includes at least one carbon fibre-reinforced polymer band, which is each joined to the steel structure (1) at the end regions thereof, capable of transferring tensile forces. In the region between these end regions, a lifting element (7) is disposed between the carbon fibre-reinforced polymer band (4) and the steel girder (3) to be reinforced, by means of which the carbon fibre-reinforced polymer band (4) is subjected to tensile stress by lifting away from the steel girder (3). The tensile force is transferred to the steel girder (3) via the anchoring elements (5).

## Claims

### Claim 1

Method for pre-stressing a steel structure, in which at least one carbon fiber-reinforced polymer band (4) each is loosely joined to a steel girder of the steel structure (1) to be reinforced at the end regions thereof with end anchorages (5) in the form of clamping shoes purely based on friction forces and without gluing, capable of transferring tensile forces, and subsequently, in a region between these end anchorages (5), at least one hydraulically, pneumatically, electrically or mechanically operated lifting element (7) disposed between the respectively carbon fibre-reinforced polymer band (4) and the steel girder to be reinforced (3,8), is extended substantially perpendicular to the carbon fibre-reinforced polymer band (4) above the tensile stress to be finally achieved for generating several 10 kN lifting force and the lifting of the polymer band (4) by means of a mechanical latch is secured, then supports are placed between the polymer band (4) and the steel structure and subsequently the lifting element (7) is relieved again, so that the target stress is achieved and the supporting force is absorbed by the supports for providing a permanent tensile force stress between the end regions of the respective carbon fibre-reinforced polymer band (4).

### Claim 2 (depends on 1)

Method for pre-stressing a steel structure according to claim 1, characterized in that several carbon fibre-reinforced polymer bands (4) are laid on the same over the length of the steel girders (3,8) to be reinforced.

### Claim 3 (depends on 1)

Method for pre-stressing a steel structure according to claim 1, characterized in that several carbon fibre-reinforced polymer bands (4) are aligned parallel to each other over the length of the steel girder (3,8) to be reinforced and each is laid on the same over the entire length of the steel beam (3,8).

### Claim 4 (depends on 1)

Method for pre-stressing a steel structure according to claim 1, characterized in that several carbon fibre-reinforced polymer bands (4) are laid over partial sections of the lengths of the steel girders (3,8) aligned parallel to each other, over the length of the steel girders (3,8) to be reinforced.

### Claim 5 (depends on 1)

Method for pre-stressing a steel structure according to claim 1, characterized in that several carbon fibre-reinforced polymer bands (4) are laid over partial sections of the lengths of the steel girder (3,8) aligned parallel to each other, over the length of the steel girder (3,8) to be reinforced, so that these are adjacent to each other and overlap in partial sections with reference to the lengths thereof.

### Claim 6 (depends on 1)

Method for pre-stressing a steel structure according to claim 1, characterized in that several carbon fibre-reinforced polymer bands (4) are mislaid over the lengths of the steel beam (3,8) to be reinforced, which are disposed extending in a direction deviating from the longitudinal direction of the steel girder (3,8) and are intersected.

### Claim 7

Steel structure, characterized in that at least one carbon fibre-reinforced polymer strip (4) each is joined to a steel girder of the steel structure (1) to be reinforced at the end regions thereof, capable of transferring tensile forces, wherein at least one lifting element (7) disposed between the respective carbon fibre-reinforced polymer band (4) and the steel girder (3,8) to be reinforced in the region between these end regions, by means of which the respective carbon fibre-reinforced polymer band (4) is subjected to tensile stress from the steel girder (3,8) by substantially perpendicular lifting of the carbon fibre-reinforced polymer band (4) and supports are inserted between the polymer band (4) and the steel structure on both the sides of the lifting element (7).

### Claim 8 (depends on 7)

Steel structure according to claim 7, characterized in that the lifting elements (7) are the hydraulically, pneumatically, electrically or mechanically operated lifting elements (7) with such a translation that only fractions thereof are generated by their paths as the reaction paths of the lifting element.

### Claim 9 (depends on 7)

Steel structure according to claim 7, characterized in that in addition to the lifting elements (7), mechanical supports are installed between the band (4) and the steel girder (3,8) to be reinforced, for relieving the lifting elements (7) after completion of the working stroke of the same.

### Claim 10 (depends on 8)

Steel structure according to claim 8, characterized in that in addition to the lifting elements (7), mechanical supports are installed between the band (4) and the steel girder (3,8) to be reinforced, for relieving the lifting elements (7) after completion of the working stroke of the same.