# US 2015/0197895 A1 · Stepwise repeated destabilization and stabilization of highly collapsible soil mass by 'soil nailing technique' used for construction of railway/road underpass

> Agents: this data is available as JSON from the patentgrep API and MCP server — see https://patentgrep.com/llms.txt

- Number: US 2015/0197895 A1
- Document ID: US20150197895A1
- Status: Published application
- Kind: A1
- Application number: 14/415,553
- Filed: 2013-07-17
- Published: 2015-07-16
- Earliest claimed: 2012-07-17
- Assignees: Council of Scientific and Industrial Research
- Applicants: Council of Scientific & Industrial Research
- Inventors: Kanwar Singh; Pulikanti Subramanya Prasad; Sudhir Mathur; Farhat Azad; Subhamay Gangopadhyay
- Web page: https://patentgrep.com/patent/US20150197895A1

## CPC

- E01C 1/04: Road crossings on different levels; Interconnections between roads on different levels
- E02D 3/12: Consolidating by placing solidifying or pore-filling substances in the soil (making piles E02D5/46; soil-conditioning or soil-stabilising materials C09K17/00; consolidation of ground around boreholes or wells E21B43/025)
- E02D 7/06: Power-driven drivers {(tampers E02D3/061)}
- E02D 17/20: Securing of slopes or inclines {(by soil E02D3/12; protection against snowslides or avalanches E01F7/04, E01F15/00; securing banks or like surfaces facing on bodies of water E02B3/12)}
- E02D 31/08: against transmission of vibrations or movements in the foundation soil {(E02D27/34 takes precedence; foundations for machines, engines or ordnance E02D27/44; for road foundations E01C3/06)}
- E21D 21/0026: {characterised by constructional features of the bolts}
- E21D 23/03: having protective means, e.g. shields, for preventing or impeding entry of loose material into the working space or support
- E21D 23/24: the advancing mechanisms being separate from the supporting construction
- E01C: CONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR (forming roads or like surfaces by compacting or grading snow or ice E01H)
- E02D: FOUNDATIONS; EXCAVATIONS; EMBANKMENTS (specially adapted for hydraulic engineering E02B); UNDERGROUND OR UNDERWATER STRUCTURES {(tunnels, tunnelling, mining E21)}
- E21D: SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS (soil-conditioning or soil-stabilising materials C09K17/00; drilling or cutting machines for mining or quarrying E21C; safety devices, transport, rescue, ventilation or drainage E21F)

## Abstract

The excavations of side vertical walls for building and underpasses must be shored so that the excavations adjacent to the neighboring properties do not cave in during the constructions. A Soil Nailing system has been used for stabilization of excavations and natural slopes for the last few decades in India and Abroad. Soil Nailing Technique used steel anchor rods inserted directly into the soil mass as a driven nails and when Nails are placed in pre-drilled holes to form grouted nails. In both the cases, it restrained load and the side deformations. In the present study, an innovative technique of ‘Soil Nailing’ has been developed for stepwise vertical de-stabilization and stabilization of compacted collapsible sandy soil for the construction of railway underpasses in live railway loading conditions. This technique is successfully implemented first time in the world for controlled destabilization of vertical cut slope and again stabilization for creating a space for pushing of box for railway underpasses for the length of 22 m and 50 m at two sites, namely Yamuna Bazzar and Apsara border, respectively, in Delhi, India. This Soil Nailing Technique of controlled destabilization of soil and again stabilization in steps has proved a superficial method of stabilization with the other methods for such kind of dynamic loading situations.

## Claims

### Claim 1

A process for making an underpass through a railway track or road without service interruption by stepwise destabilization and stabilization of a highly collapsible soil mass by a soil nailing technique, the process comprising the steps of:
marking a position of a box on a vertical face of a first retaining wall or an embankment;
dismantling the retaining wall above the marked position of the box and providing temporary support by shuttering plates having holes for pre-decided positions of nails to be driven in the vertical face;
nailing the soil mass by using grouted nails and optionally driven nails above the marked position of the box;
again dismantling the first retaining wall, placing the shuttering plates with pre-drilled positions of nails and inserting only the driven nails from the top to the bottom of a box pushing area;
leaving a complete nail system for a period in the range of 8 to 12 hrs to mobilize the friction of the nails;
bringing the box close to the soil-nailed, wall face;
loosening one top row of shuttering plates, and excavating the soil to a 30 to 40 cm depth;
repeating step (vii) until the entire rows of the nails are covered for a 30 to 40 cm depth followed by pushing the box into the excavated area of 30 to 40 cm depth;
pushing the nails into the soil mass and again tightening of the shuttering plates;
repeating step (vii) to (ix) until 50% of the box pushing length;
cutting the nails in the range of 25 to 35 cm to create a space for box pushing wherein first/pointed ends of the nails will touch a second retaining wall, followed by placing vertical nails in order to increase the stability of the cut slope; and
again repeating step (vii) to (ix) until till complete insertion of the box for making an underpass.

### Claim 2 (depends on 1)

The process as claimed in claim 1, wherein a thickness of the shuttering plate used is in the range of 3 to 5 mm.

### Claim 3 (depends on 1)

The process as claimed in claim 1, wherein a length of the grouted nail and driven nails in step (iii) is equal to the length of the underpass.

### Claim 4 (depends on 1)

The process as claimed in claim 1, wherein a diameter of the grouted nail used is in the range of 90 to 110 mm.

### Claim 5 (depends on 1)

The process as claimed in claim 1, wherein a diameter of the driven nail used is in the range of 25 to 32 mm.

### Claim 6 (depends on 1)

The process as claimed in claim 1, wherein a length of the driven nail used in step (iv to xii) is optimized with height of the vertical cut height in 0.7H wherein H is the height of vertical cut slope.

### Claim 7 (depends on 1)

The process as claimed in claim 1, wherein it is ensured that all the driven nails have an extra length of at least 40 cm outside the shuttering plate.