# US 2015/0191888 A1 · Method and apparatus for stabilising a dike

> Agents: this data is available as JSON from the patentgrep API and MCP server — see https://patentgrep.com/llms.txt

- Number: US 2015/0191888 A1
- Document ID: US20150191888A1
- Status: Published application
- Kind: A1
- Application number: 14/410,639
- Filed: 2013-06-28
- Published: 2015-07-09
- Earliest claimed: 2012-06-28
- Assignees: J.F. Karsten Beheer B.V.
- Applicants: J.F. Karsten Beheer B.V.
- Inventors: Johannes Franciscus Karsten
- Web page: https://patentgrep.com/patent/US20150191888A1

## CPC

- E02D 27/50: Anchored foundations
- E02B 3/10: Dams; Dykes; Sluice ways or other structures for dykes, dams, or the like (making embankments or dams in general E02D17/18)
- E02B 3/12: Revetment of banks, dams, watercourses, or the like, {e.g. the sea-floor}(of slopes in general E02D17/20)
- E02D 5/803: {with pivotable anchoring members}
- E02D 17/18: Making embankments, {e.g. dikes, dams}(E02D17/20 takes precedence; {foundations for dams E02D27/40})
- E02D 17/20: Securing of slopes or inclines {(by soil E02D3/12; protection against snowslides or avalanches E01F7/04, E01F15/00; securing banks or like surfaces facing on bodies of water E02B3/12)}
- E02D 17/207: {with means incorporating sheet piles or piles}
- E02D 27/40: Foundations for dams across valleys or for dam constructions {(dams per se E02B3/10, E02B7/04)}
- E02D 29/0233: {the retention means being anchors (details of anchors E02D5/80)}
- E02D: FOUNDATIONS; EXCAVATIONS; EMBANKMENTS (specially adapted for hydraulic engineering E02B); UNDERGROUND OR UNDERWATER STRUCTURES {(tunnels, tunnelling, mining E21)}
- E02B: HYDRAULIC ENGINEERING (ship-lifting E02C; dredging E02F)

## Abstract

A method of stabilizing a dike using a ground anchor assembly, includes: connecting a ground anchor to a first end of a tensile member; introducing the ground anchor through the earth body and into a stable layer beneath the dike; providing a pressure distributing member on or around the tensile member at a position within the dike where stabilisation against lateral earth movement is required; and connecting a second end of the tensile member to a counter member at an outer surface of the dike.

## Claims

### Claim at position 1

1-34. (canceled)

### Claim 35

Ground anchor assembly (1) for stabilizing a dike, comprising a ground anchor (4), a counter member (5) and an elongate tensile member (3), connecting the ground anchor (4) and the counter member (5), wherein said tensile member is provided between the ground anchor and the counter member (5) with a pressure distributing member (2), arranged to prevent earth flow in a direction (a) perpendicular to a length direction of the tensile member (3).

### Claim 36 (depends on 35)

The assembly according to claim 35, wherein the pressure distributing member is elongated and extends along the tensile member, preferably over at least 10% of its length, more preferably over at least 30% of its length.

### Claim 37 (depends on 35)

The assembly according to claim 35, wherein the pressure distributing member comprise a bladed structure, having preferably a cross or a star in cross-section.

### Claim 38 (depends on 35)

The assembly according to claim 35, wherein the pressure distributing member is slideably mounted around the tensile member.

### Claim 39 (depends on 35)

The assembly according to claim 35, wherein the pressure distributing member is integral with the tensile member.

### Claim 40 (depends on 35)

The assembly according to claim 35, wherein the pressure distributing member comprises a composite material, preferably basalt epoxy composite.

### Claim 41 (depends on 35)

The assembly according to claim 35, wherein the pressure distributing member is a plastic or a metal strip.

### Claim 42 (depends on 35)

The assembly according to claim 35, wherein the ground anchor is a pivotable ground anchor that can be inserted into the dike by an insertion rod and pivoted into position by applying tension to the tensile member.

### Claim 43 (depends on 35)

The assembly according to claim 35, wherein the tensile member is a flexible composite rod, preferably a basalt fibre composite, secured to the ground anchor and to the counter member.

### Claim 44 (depends on 35)

The assembly according to claim 35, wherein the counter member is a perforated plate, preferably of basalt composite.

### Claim 45 (depends on 35)

The assembly according to claim 35, wherein the counter member comprises a net.

### Claim 46 (depends on 35)

Dike (9) comprising a number of adjacently arranged ground anchor assemblies according to claim 35, arranged to prevent earth flow in a direction (a) perpendicular to the length direction of the tensile member.

### Claim 47 (depends on 46)

The dike according to claim 46, wherein the counter member is provided near an outer surface of the dike.

### Claim 48

Method for stabilizing a dike using a ground anchor assembly, the method comprising:
connecting a ground anchor to a first end of a tensile member;
introducing the ground anchor through the dike and into a stable layer beneath the dike;
providing a pressure distributing member on or around the tensile member at a position within the dike where stabilisation against lateral earth movement is required; and
connecting a second end of the tensile member to a counter member at an outer surface of the dike.

### Claim 49 (depends on 48)

The method according to claim 48, wherein the pressure distributing member is introduced together with the ground anchor and tensile member.

### Claim 50 (depends on 48)

The method according to claim 48, wherein introducing the ground anchor comprises pivoting the ground anchor relative to the tensile member to engage with the stable layer.

### Claim 51 (depends on 48)

The method according to claim 48, wherein the counter member is connected to the tensile member with a pretension.

### Claim 52 (depends on 48)

The method according to claim 48, further comprising performing a geotechnical survey of the dike and positioning the pressure distributing member at a position corresponding to a slip zone within the dike.

### Claim 53

Method for stabilizing an earth body (1), like a dike, embankment, dam etc., comprising the steps;
providing a plurality of mechanical ground anchor assemblies (3), each assembly comprising a ground anchor (6) and a flexible tension member (5) for coupling the ground anchor to an object to be anchored, as well as a coupling member (11) which fixedly couples the anchor to the tension member,
installing a mechanical ground anchor of the plurality of assemblies through the earth body in a respective anchor location at least 0.5 meter below the earth body surface for stabilizing the earth body,
applying a geonet (3), like geotextile, to the earth body (1) for ground stabilization,
coupling the flexible tension member (5), associated with the mechanical ground anchor of the plurality of assemblies, with the geonet for maintaining the earth body.

### Claim 54 (depends on 53)

The method according to claim 53, comprising repeating the steps;
installing a mechanical ground anchor of the plurality of assemblies through the earth body in a respective anchor location at least 0.5 meter below the earth body surface for stabilizing the earth body,
coupling the flexible tension member (3), associated with the mechanical ground anchor of the plurality of assemblies, with the geonet for maintaining the earth body,
for each respective ground anchor of the plurality of ground anchors.

### Claim 55 (depends on 53)

The method according to claim 53, wherein the mechanical ground anchor is a pivoting ground anchor and the method comprises the step;
setting the pivoting ground anchor in its anchor position upon taking in of the flexible tension member.

### Claim 56 (depends on 54)

The method according to claim 54, wherein adjacent tension members are coupled with the geonet at a mutual tension member spacing in the range of 0.1 meter to 10 meter.

### Claim 57 (depends on 54)

The method according to claim 54, wherein the tension member spacing is about 1 meter.

### Claim 58 (depends on 56)

The method according to claim 56, wherein the tension members are coupled with the geonet along a pattern like a line-, check- or any other suitable pattern.

### Claim 59 (depends on 53)

The method according to claim 53, wherein the tension member is a flexible strip made of woven or non-woven fabric suitable for coupling with the geonet.

### Claim 60 (depends on 53)

The method according to claim 53, wherein the tension member is a plastic or a metal strip.

### Claim 61 (depends on 53)

The method according to claim 53, wherein the coupling of the tension member (3) with the geonet comprises weaving of the tension member with the geonet, clamping of the tension member with the geonet, and/or hooking of the tension member into the geonet.

### Claim 62 (depends on 53)

The method according to claim 53, comprising the step;
installing mechanical ground anchors of the plurality of assemblies through the earth body from opposite sides of the earth body for stabilizing the earth body.

### Claim 63 (depends on 53)

The method according to claim 53, wherein installing the ground anchor comprises driving of the ground anchor with a driving rod coupled with the ground anchor by a driving rod coupling member for temporary coupling the anchor with the driving rod to drive the anchor to the anchor location, wherein the method comprises the step filling of the space left by the driving rod with a filler like grout, bentonite or any other suitable filling material, upon retracting the driving rod after the ground anchor has been installed in its respective anchor location.

### Claim 64 (depends on 63)

The method according to claim 63, wherein the driving rod comprises a conduit which extends in the longitudinal direction of the driving rod, and wherein the conduit is provided with a discharge at is leading end, and the filling of the space left by the driving rod comprises supplying of the filler through the conduit.

### Claim 65 (depends on 53)

The method according to claim 53, wherein the length (l) of the tension member exceeds 0.5 meter, preferably exceeds 3 meter.

### Claim 66 (depends on 53)

The method according to claim 53, wherein the length (l) of the tension member is such that the anchor location below the earth body surface is at a separate earth layer distinct from the earth body.

### Claim 67 (depends on 53)

The method according to claim 53, wherein the tension member is of one piece.

### Claim 68 (depends on 53)

The method according to claim 53, wherein the tension member is continuous.