# US 2015/0178647 A1 · Method and system for project risk identification and assessment

> Agents: this data is available as JSON from the patentgrep API and MCP server — see https://patentgrep.com/llms.txt

- Number: US 2015/0178647 A1
- Document ID: US20150178647A1
- Status: Published application
- Kind: A1
- Application number: 14/630,328
- Filed: 2015-02-24
- Published: 2015-06-25
- Earliest claimed: 2012-07-09
- Assignees: Sysenex, Inc.
- Applicants: Sysenex, Inc.
- Inventors: Laurie WIGGINS; David HALL
- Web page: https://patentgrep.com/patent/US20150178647A1

## CPC

- G06Q 10/0635: Risk analysis of enterprise or organisation activities
- G06Q: INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR

## Abstract

Disclosed herein is a system and method for project risk assessment. The system and method include collecting project identification information, receiving responses to a single comprehensive query about the project, using the responses to find specific characteristics of a coupled module for performing tasks related to the project, and determining a risk level of the module performing the tasks based on the specific characteristics of the coupled module.

## Claims

### Claim 1

A method for project risk assessment comprising:
collecting project identification information,
receiving responses to a single comprehensive query about the project,
using the responses to find specific characteristics of a coupled module for performing tasks related to the project, and
determining a risk level of the module performing the tasks based on the specific characteristics of the coupled module.

### Claim 2 (depends on 1)

The method as recited in claim 1 wherein the single comprehensive survey is based on a set of known factors and is applicable to mutually exclusive projects.

### Claim 3 (depends on 2)

The method as recited in claim 2 wherein the set of known factors comprise two hundred and eighteen mutually exclusive factors.

### Claim 4 (depends on 1)

The method as recited in claim 1 wherein the tasks are at least one risk area selected from the group of risk areas consisting of technical, organizational, operational, external managerial and enterprise.

### Claim 5 (depends on 4)

The method as recited in claim 4 further comprising producing a generic risk determination based on all of the areas.

### Claim 6 (depends on 4)

The method as recited in claim 4 wherein all of the risk areas collectively comprise thirty-one risk categories and wherein all of the risk categories collectively comprise two hundred and eighteen individual risks.

### Claim 7 (depends on 1)

The method as recited in claim 1 wherein less than all of the individual risks are considered when determining the risk level.

### Claim 8 (depends on 4)

The method as recited in claim 4 further comprising producing a risk level for each of the risk areas.

### Claim 9 (depends on 8)

The method as recited in claim 8 further comprising revising the risk level in response to a user request.

### Claim 10 (depends on 1)

The method as recited in claim 1 wherein the specific characteristics of the coupled module are selected from the group consisting of a history of the coupled module, a bandwidth of the coupled module, available bandwidth of the coupled module, special resources of the coupled module, logistics, quality of resources, reuse of previously used resources, environment, regulatory considerations, geographic concerns and testing results.

### Claim 11 (depends on 1)

The method as recited in claim 1 wherein the determining step is performed before the project is completed.

### Claim 12 (depends on 11)

The method as recited in claim 11 wherein the determining step is performed before the project is begun.

### Claim 13 (depends on 1)

The method as recited in claim 1 further comprising plotting a risk trend over time during project execution.

### Claim 14 (depends on 13)

The method as recited in claim 13 further comprising modifying the determined risk based on the risk trend as the risk trend is plotted.