# US 2014/0236660 A1 · Gui support for diagnosing and remediating problems that threaten on-time delivery of software and systems

> Agents: this data is available as JSON from the patentgrep API and MCP server — see https://patentgrep.com/llms.txt

- Number: US 2014/0236660 A1
- Document ID: US20140236660A1
- Status: Published application
- Kind: A1
- Application number: 14/184,187
- Filed: 2014-02-19
- Published: 2014-08-21
- Earliest claimed: 2012-06-01
- Assignees: International Business Machines Corporation
- Applicants: International Business Machines Corporation
- Inventors: Murray R. Cantor; Evelyn Duesterwald; Tamir Klinger; Peter K. Malkin; Paul M. Matchen; Stanley M. Sutton; Peri L. Tarr; Mark N. Wegman
- Web page: https://patentgrep.com/patent/US20140236660A1

## CPC

- G06Q 10/063114: {Status monitoring or status determination for a person or group}
- G06Q 10/06: Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
- G06Q 10/06312: {Adjustment or analysis of established resource schedule, e.g. resource or task levelling, or dynamic rescheduling}
- G06Q 10/06313: {Resource planning in a project environment}
- G06Q 10/0633: Workflow analysis
- G06Q 10/06334: {using forecasting or predicting}
- G06Q 10/0635: Risk analysis of enterprise or organisation activities
- G06Q: INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR

## Abstract

A graphical interface module may provide a set of graphical presentations comprising at least: a Likelihood of Delivery chart showing a probability distribution of predicted delivery dates; a Delivery Date Risk Trend chart showing how the completion time for the project predicted according to the Likelihood of Delivery chart has changed over time; and a Burndown chart that shows at least work-items of planned work for the project. Each of the Likelihood of Delivery chart, the Delivery Date Risk Trend chart, and the Burndown chart has a timeline axis.

## Claims

### Claim 1

A system for providing a graphical user interface support for diagnosing and remediating problems that threaten on-time delivery of a project, comprising:
a processor; and
a graphical interface module operable to execute on the processor and further operable to display a set of graphical presentations associated with a probability distribution for completion time for the project,
the set of graphical presentations comprising at least:
a Likelihood of Delivery chart showing a probability distribution of predicted delivery dates;
a Delivery Date Risk Trend chart showing how the completion time for the project predicted according to the Likelihood of Delivery chart has changed over time; and
a Burndown chart that shows at least work-items of planned work for the project, a graphical position on the Burndown chart of a work-item of said work-items representing a date on which the work-item is completed or to be completed, and how much more work remains to be done on the project after the work-item is completed,
each of the Likelihood of Delivery chart, the Delivery Date Risk Trend chart, and the Burndown chart having a timeline axis.

### Claim 2 (depends on 1)

The system of claim 1, wherein the graphical interface module displays the Likelihood of Delivery chart, the Delivery Date Risk Trend chart, and the Burndown chart with their timeline axes aligned.

### Claim 3 (depends on 1)

The system of claim 1, wherein the Likelihood of Delivery chart maps a plurality of project completion probabilities over the Likelihood of Delivery chart's timeline axis and an axis that represents the probability of delivery, wherein the probability associated with a particular position on the Likelihood of Delivery chart's timeline axis represents the particular probability of delivery on or during the time, date, or interval represented by that position on the timeline axis.

### Claim 4 (depends on 1)

The system of claim 1, wherein the Likelihood of Delivery chart further shows a line representing planned delivery date,
wherein a first portion of a curve of the probability distribution, or a first area under the curve of the probability distribution, or both, that fall on or before the planned delivery date are shown with one visual indication, and
a second portion of the curve of the probability distribution, or a second area under the curve of the probability distribution, or both, that fall after the planned delivery date are shown with another visual indication.

### Claim 5 (depends on 1)

The system of claim 1, wherein responsive to detecting an interactive input over the Likelihood of Delivery chart, the graphical user interface is further operable to show a visual representation of a cumulative probability of delivery on or before a date selected by current position on the Likelihood of Delivery chart of the interactive input.

### Claim 6 (depends on 1)

The system of claim 1, wherein the Delivery Date Risk Trend chart maps a plurality of project completion times over the Delivery Date Risk Trend chart's timeline axis and an expected delivery date axis,
each of the plurality of project completion times predicted at different dates according to information available at the different dates of prediction and the dates of prediction being represented on the Delivery Date Risk Trend chart's timeline axis,
wherein for each of the plurality of project completion times that is predicted, the Delivery Date Risk Trend chart graphs earliest predicted delivery date, most likely predicted delivery date, and latest predicted delivery date, and
wherein the Delivery Date Risk Trend chart further shows one or more of:
a line that represents a planned delivery date for the project provided by a user; or an area between the earliest delivery date and the latest delivery dates that is visually coded to represent a status of the predicted delivery dates with respect to the planned delivery date; or
a textual display of dates that represent the earliest delivery date, the most likely delivery date, and the latest delivery date associated with current prediction.

### Claim 7 (depends on 1)

The system of claim 1, wherein the Burndown chart shows amount of work remaining on the project over the Burndown chart's timeline axis and another axis that represents percentage of work remaining on the project, and further shows the work-items of the planned work to be completed according to the work-items' positions on the timeline axis.

### Claim 8 (depends on 7)

The system of claim 7, wherein said amount of work remaining is represented in the Burndown chart according to the work-item's position on said another axis that represents percentage of work remaining on the project.

### Claim 9 (depends on 7)

The system of claim 7, wherein the Burndown chart further shows current predictions for completion dates to a given percentage of work remaining on the project,
wherein the current predictions comprise earliest predicted date to the given percentage of work remaining on the project and latest predicted delivery date to the given percentage of work remaining on the project,
wherein the earliest predicted delivery date to the given percentage of work remaining on the project corresponds to Likelihood of Delivery chart's earliest predicted date shown by the Likelihood of Delivery chart's probability distribution of predicted delivery dates, and
wherein the latest predicted delivery date to the given percentage of work remaining on the project corresponds to Likelihood of Delivery chart's latest predicted delivery date shown by the Likelihood of Delivery chart's probability distribution of predicted delivery dates.

### Claim 10 (depends on 9)

The system of claim 9, wherein the Burndown chart shows a cone of uncertainty going forward from the current date representing most likely outcomes possible, best outcomes possible, and worst outcomes possible for delivery, which provides a predictive range of dates for delivery.

### Claim 11 (depends on 7)

The system of claim 7, wherein the Burndown chart further shows higher-level items that comprise one or more of said work-items in the project and represent a collection of said work-items, the higher-level items positioned on the Burndown chart's timeline axis and said another axis that represents percentage of work remaining on the project, the Burndown chart further showing a stack of said higher-level items aligned according to their positions on said another axis, wherein a line is graphically shown to extend from most recently completed higher-level items of the higher-level items to the stack of said higher-level items wherein the higher-level items are placed above the line as the higher-level items are completed.

### Claim 12 (depends on 7)

The system of claim 7, wherein selecting the work-item on the Burndown chart triggers one or more of: displaying detailed information on the work-item, or hyperlinking to a representation of the work item in its native environment, or combinations thereof.

### Claim 13 (depends on 1)

The system of claim 1, wherein the set of graphical presentations further comprises a slider bar which allows a user to select one or more dates and allows the user to play back a history of delivery date predictions made for the project using data that was known at the one or more selected dates, wherein using the slider bar the user is allowed to go back in time and play forward a development history to a current date and visualize how a changing likelihood on-time delivery evolved in time.

### Claim 14

A method of providing graphical user interface support for diagnosing and remediating problems that threaten on-time delivery of a project, comprising:
displaying by a processor on a display device a set of graphical presentations associated with a probability distribution for completion time for the project,
the set of graphical presentations comprising at least:
a Likelihood of Delivery chart showing a probability distribution of predicted delivery dates;
a Delivery Date Risk Trend chart showing how the completion time for the project predicted according to the Likelihood of Delivery chart has changed over time; and
a Burndown chart that shows at least work-items of planned work for the project, a graphical position on the Burndown chart of a work-item of said work-items representing date on which the work-item is completed or to be completed, and how much more work remains to be done on the project after the work-item is completed,
each of the Likelihood of Delivery chart, the Delivery Date Risk Trend chart, and the Burndown chart having a timeline axis

### Claim 15 (depends on 14)

The method of claim 14, wherein the Likelihood of Delivery chart, the Delivery Date Risk Trend chart, and the Burndown chart are displayed with their timeline axes aligned.

### Claim 16 (depends on 14)

The method of claim 14, further comprising:
displaying on the Likelihood of Delivery chart a line representing a planned delivery date, wherein a first portion of a curve of the probability distribution, or a first area under the first portion of the curve of the probability distribution, that fall on or before the planned delivery date are shown with one visual indication and a second portion of the curve of the probability distribution, or a second area of that the second portion of the curve of the probability distribution, that fall after the planned delivery date are shown with another visual indication;
detecting an interactive input over the Likelihood of Delivery chart; and
displaying a visual representation of a cumulative probability of delivery on or before a date selected by a current position on the Likelihood of Delivery chart of the detected interactive input.

### Claim 17 (depends on 14)

The method of claim 14, wherein the Delivery Date Risk Trend chart maps a plurality of project completion times over its timeline axis and an expected delivery date axis,
each of the plurality of project completion times predicted at different dates according to information available at the different dates,
wherein for each of the plurality of project completion times, Delivery Date Risk Trend chart graphs earliest predicted delivery date, most likely predicted delivery date, and latest predicted delivery date, and
wherein the Delivery Date Risk Trend chart further shows one or more of:
a line that represents a planned delivery date for the project provided by a user; or
an area between the earliest delivery date and the latest delivery date visually coded to represent status of the predicted delivery dates with respect to the planned delivery date; or
the dates textually that represent the earliest delivery date, the most likely delivery date, and the latest delivery date associated with current prediction.

### Claim 18 (depends on 14)

The method of claim 14, wherein the Burndown chart shows one or more of:
amount of work remaining on the project over its timeline axis and another axis that represents percentage of work remaining on the project, and further shows work-items of the planned work to be completed according to their positions on the timeline axis,
wherein said amount of work remaining to be done is represented in the Burndown chart according to the work-item's position on said another axis that represents percentage of work remaining on the project; or
current predictions for completion dates to a given percentage of work remaining on the project,
wherein the current predictions comprise earliest predicted date to the given percentage of work remaining on the project and latest predicted delivery date to the given percentage of work remaining on the project,
wherein the earliest predicted date to the given percentage of work remaining on the project corresponds to a first tail at an earlier end of the Likelihood of Delivery chart's probability distribution of predicted delivery dates, and
the latest predicted delivery date to the given percentage of work remaining on the project corresponds to a second tail at a later end of the Likelihood of Delivery chart's probability distribution of predicted delivery dates.

### Claim 19 (depends on 14)

The method of claim 14, wherein the set of graphical presentations further comprises a slider bar which allows a user to select one or more dates and allow the user to play back a history of delivery date predictions made for the project using data that was known at the one or more selected dates, wherein using the slider bar the user is allowed to go back in time and play forward a development history to a current date and visualize how a changing likelihood on-time delivery evolved in time.

### Claim 20

A computer readable storage medium storing a program of instructions executable by a machine to perform a method of providing graphical user interface support for diagnosing and remediating problems that threaten on-time delivery of a project, comprising:
displaying by a processor on a display device a set of graphical presentations associated with a probability distribution for completion time for the project,
the set of graphical presentations comprising at least:
a Likelihood of Delivery chart showing a probability distribution of predicted delivery dates;
a Delivery Date Risk Trend chart showing how the completion time for the project predicted according to the Likelihood of Delivery chart has changed over time; and
a Burndown chart that shows at least work-items of planned work for the project, graphical position on the Burndown chart of a work-item of said work-items representing date on which the work-item is completed or to be completed, and how much more work remains to be done on the project after the work-item is completed,
each of the Likelihood of Delivery chart, the Delivery Date Risk Trend chart, and the Burndown chart having a timeline axis,
wherein the Likelihood of Delivery chart, the Delivery Date Risk Trend chart, and the Burndown chart displayed with their timeline axes aligned,
wherein the Burndown chart further shows current predictions for completion dates to a given percentage of work remaining on the project,
wherein the current predictions comprise earliest predicted date to the given percentage of work remaining on the project and latest predicted delivery date to the given percentage of work remaining on the project,
wherein the earliest predicted date to the given percentage of work remaining on the project corresponds to left tail of the Likelihood of Delivery chart's probability distribution of predicted delivery dates, and
the latest predicted delivery date to the given percentage of work remaining on the project corresponds to right tail of the Likelihood of Delivery chart's probability distribution of predicted delivery dates.