# US 2014/0207512 A1 · Timeline-Based Visual Dashboard For Construction

> Agents: this data is available as JSON from the patentgrep API and MCP server — see https://patentgrep.com/llms.txt

- Number: US 2014/0207512 A1
- Document ID: US20140207512A1
- Status: Published application
- Kind: A1
- Application number: 13/749,563
- Filed: 2013-01-24
- Published: 2014-07-24
- Earliest claimed: 2013-01-24
- Assignees: DPR Construction
- Applicants: Dpr Construction
- Inventors: Atul Khanzode; John Vardman; Howard Steve Spence; Daniel Gonzales
- Web page: https://patentgrep.com/patent/US20140207512A1

## CPC

- G06Q 10/06312: {Adjustment or analysis of established resource schedule, e.g. resource or task levelling, or dynamic rescheduling}
- G06Q: INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR

## Abstract

An embodiment of the invention includes a computer implemented method for monitoring construction. The method may include receiving information about a construction project. The received information may include information about construction milestones and schedule information about the construction milestones. The information may include graphical data related to the construction milestones and the schedule information. Information about the location of a computing device may be received. Based on the location information and the information about the construction project, a graphical display user-interface may be prepared. In an embodiment of the invention, the display may include a visual representation of expected progress of the project. The display may include information about expected activity related to the project for a period of time. Embodiments include receiving an indication from a user that the representation of the expected progress differs from actual progress of the project and determining revised information about the construction project.

## Claims

### Claim 1

A computer implemented method for monitoring construction, the method comprising:
providing a processor;
receiving information about a construction project, the information comprising:
information about construction milestones;
schedule information about the construction milestones; and
graphical data related to the construction milestones and the schedule information;
receiving location information for a computing device;
based on the location information and the information about the construction project, preparing, using the processor, a display comprising:
a visual representation of expected progress of the project; and
information about expected activity related to the project for a period of time;
receiving an indication from a user that the representation of the expected progress differs from actual progress of the project; and
determining revised information about the construction project.

### Claim 2 (depends on 1)

The method of claim 1 wherein schedule information comprises information about expected construction activity including at least one of: equipment in use at a particular time; and materials used at a particular time.

### Claim 3 (depends on 1)

The method of claim 1 wherein schedule information comprises one or more of: number of persons present at a particular time; money spent by a particular time; and man hours worked by a particular time.

### Claim 4 (depends on 1)

The method of claim 1 wherein location information for a computing device comprises GPS coordinates of the computing device.

### Claim 5 (depends on 1)

The method of claim 1 wherein location information for a computing device comprises an indication from a user on a touch screen.

### Claim 6 (depends on 1)

The method of claim 1 wherein the visual representation of the expected progress of the project comprises a Gantt chart.

### Claim 7 (depends on 1)

The method of claim 1 wherein the visual representation of the expected progress of the project comprises:
a three-dimensional graphical representation of the expected appearance of the construction site; and
indicators showing differences between the actual progress of the construction site and the expected progress of the construction site.

### Claim 8 (depends on 1)

The method of claim 1 further comprising receiving additional information about the actual progress of the project by receiving one or more of the following:
financial projections;
data from an access card system;
data from a vehicle tracking device;
logistical tracking data; and
imaging data.

### Claim 9

A non-transitory computer-readable storage medium comprising a plurality of computer-readable instructions tangibly embodied on the computer-readable storage medium, which when executed by a data processor, provide a timeline-based visual dashboard for construction, the plurality of instructions comprising:
instructions that cause the data processor to receive information about a construction project comprising: information about construction milestones; schedule information about the construction milestones; and graphical data related to the construction milestones and the schedule information;
instructions that cause the data processor to receive location information for a computing device;
instructions that cause the data processor to, based on the location information and the information about the construction project, prepare a display comprising: a visual representation of expected progress of the project; and information about expected activity related to the project for a period of time;
instructions that cause the data processor to receive an indication from a user that the representation of the expected progress differs from actual progress of the project; and
instructions that cause the data processor to determine revised information about the construction project.

### Claim 10 (depends on 9)

The non-transitory computer-readable storage medium of claim 9 wherein schedule information comprises information about expected construction activity including at least one of: equipment in use at a particular time; and materials used at a particular time.

### Claim 11 (depends on 9)

The non-transitory computer-readable storage medium of claim 9 wherein schedule information comprises one or more of: number of persons present at a particular time; money spent by a particular time; and man hours worked by a particular time.

### Claim 12 (depends on 9)

The non-transitory computer-readable storage medium of claim 9 wherein the visual representation of the expected progress of the project comprises a Gantt chart.

### Claim 13 (depends on 9)

The non-transitory computer-readable storage medium of claim 9 wherein the visual representation of the expected progress of the project comprises:
a three-dimensional graphical representation of the expected appearance of the construction site;
indicators showing differences between the actual progress of the construction site; and the expected progress of the construction site.

### Claim 14 (depends on 9)

The non-transitory computer-readable storage medium of claim 9 further comprising:
instructions that cause the data processor to receive additional information about the actual progress of the project by receiving one or more of the following:
financial projections;
data from an access card system;
data from a vehicle tracking device;
logistical tracking data; and
imaging data.

### Claim 15

A system for monitoring and tracking the progress of a construction project, comprising:
a processor;
a memory disposed in communication with the processor and storing processor executable instructions, the instructions comprising instructions for:
receiving information about a construction project comprising:
information about construction milestones;
schedule information about the construction milestones; and
graphical data related to the construction milestones and the schedule information;
receiving location information for a computing device;
based on the location information and the information about the construction project, preparing, using the processor, a display comprising:
a visual representation of expected progress of the project; and
information about expected activity related to the project for a period of time;
receiving an indication from a user that the representation of the expected progress differs from actual progress of the project; and
determining revised information about the construction project.

### Claim 16 (depends on 15)

The system of claim 15 wherein schedule information comprises information about expected construction activity including at least one of: equipment in use at a particular time; and materials used at a particular time.

### Claim 17 (depends on 15)

The system of claim 15 wherein schedule information comprises one or more of: number of persons present at a particular time; money spent by a particular time; and man hours worked by a particular time.

### Claim 18 (depends on 15)

The system of claim 15 wherein the visual representation of the expected progress of the project comprises a Gantt chart.

### Claim 19 (depends on 15)

The system of claim 15 wherein the visual representation of the expected progress of the project comprises:
a three-dimensional graphical representation of the expected appearance of the construction site;
indicators showing differences between the actual progress of the construction site; and the expected progress of the construction site.

### Claim 20 (depends on 15)

The system of claim 15 wherein the instructions further comprise instructions for receiving additional information about the actual progress of the project by receiving one or more of the following:
financial projections;
data from an access card system;
data from a vehicle tracking device;
logistical tracking data; and
imaging data.