# US 2013/0158695 A1 · Method, system and program for constructing a controller

> Agents: this data is available as JSON from the patentgrep API and MCP server — see https://patentgrep.com/llms.txt

- Number: US 2013/0158695 A1
- Document ID: US20130158695A1
- Status: Published application
- Kind: A1
- Application number: 13/327,700
- Filed: 2011-12-15
- Published: 2013-06-20
- Earliest claimed: 2011-12-15
- Assignees: International Business Machines Corporation
- Inventors: Junya Shimizu
- Web page: https://patentgrep.com/patent/US20130158695A1

## CPC

- G05B 13/042: {in which a parameter or coefficient is automatically adjusted to optimise the performance}
- G05B: CONTROL OR REGULATING SYSTEMS IN GENERAL; FUNCTIONAL ELEMENTS OF SUCH SYSTEMS; MONITORING OR TESTING ARRANGEMENTS FOR SUCH SYSTEMS OR ELEMENTS (systems for controlling or regulating non-electric variables G05D; systems for regulating electric or magnetic variables G05F; control devices or systems insofar as characterised by mechanical features only G05G)

## Abstract

A system, program and related computer implemented method for selecting a controller and constructing it to automate one or more processes is provided. The method comprises the steps of: constructing a controller from a plant described by an LPV model to which a scheduling parameter is given by: a) calculating one or more v gaps and a mean value of each candidate of a plant parameter vector of said LPV model based on a requirement of preselected constraints; b) choosing a candidate via information gathered by proof based on the magnitude of differences between the v gaps; c) converting the LPV model into LMI and finding controllers, according to an H∞ criterion, at all combination end points of a maximum value and a minimum value of the plant parameter vector thus chosen; and d) choosing and constructing said chosen controller for said plant.

## Claims

### Claim 1

A computer implemented method for selecting a controller from a plurality of controllers and constructing so that it can automate one or more processes used in a plant, comprising the steps of:
constructing a controller from a plant described by an LPV model to which a scheduling parameter is given by:
a) calculating via a processor one or more v gaps respectively for Min, Max, and a mean value of each candidate of a plant parameter vector of said LPV model based on a requirement of preselected constraints;
b) said processor choosing a candidate via information gathered by proof said plant parameter vector based on the magnitude of differences between said v gaps;
c) said processor converting the LPV model into LMI and finding controllers, according to an H∞ criterion, at all combination end points of a maximum value and a minimum value of the plant parameter vector thus chosen; and
d) said processor choosing and constructing said chosen controller for said plant by using bilinear interpolation weighted by said v gaps specifically calculated for said plant parameter vector thus chosen.

### Claim 2 (depends on 1)

The method according to claim 1, wherein said processor calculates said v gaps, using a transfer function into which a maximum value of an i-th element of the scheduling parameter is substituted is assumed Timax, a transfer function into which a minimum value thereof is substituted is assumed Timin, a transfer function into which a mean value thereof is substituted is assumed Timid, and δv( ) is assumed as a function and said values are calculated by said processor using the formula:
vi—mid_max=δv(Timid, Timax)
vi—min_mid=δv(Timin, Timid)
vi—min_max=δv(Timin, Timax)

### Claim 3 (depends on 2)

The method according to claim 2, wherein said processor chooses a candidate based on said plant parameter vector and based on a value of (|vi—min_mid−vi—mid_max|+vi—min_max).

### Claim 4 (depends on 3)

The method according to claim 3, wherein in step of selecting candidates only one candidate having a largest value of (|vi—min_mid−vi—mid_max|+vi—min_max) is chosen, such that bilinear interpolation is performed at two points to which min and max of the parameter thus chosen are fixed, respectively.

### Claim 5 (depends on 2)

The method according to claim 2, wherein said step of choosing a candidate includes choosing a plurality of candidates such that at least one candidate with a largest value of (|vi—min_mid−vi—mid_max|+vi—min_max) and another candidate with a second largest value of (|vi—min_mid−vi—mid_max|+vi—min_max), are chosen, such that bilinear interpolation is performed at four points to which p1_min and p2_min, p1_min and p2_max, p1_max and p2_min, and p1_max and p2_max are fixed, respectively, where p1 indicates said candidate with said largest value and p2 indicates the candidate with said second largest value.

### Claim 6

A computer processor enabled to execute a program for constructing a controller from a plant described by an LPV model to which a scheduling parameter is given, comprising the steps of:
said processor calculating v gaps respectively for Min, Max, and a mean value of each candidate of a plant parameter vector of the LPV model based on a requirement of constraints;
said processor choosing a candidate of the plant parameter vector based on the magnitude of differences between the v gaps;
said processor converting the LPV model into LMI and finding controllers, according to an H∞ criterion, at all combination end points of a maximum value and a minimum value of the plant parameter vector thus chosen; and
said processor constructing a controller for the plant by bilinear interpolation weighted by the v gaps calculated for the plant parameter vector thus chosen.

### Claim 7 (depends on 6)

The computer processor of claim 6, wherein said processor calculates v gaps, via a transfer function into which a maximum value of an i-th element of said scheduling parameter is substituted is assumed Timax, a transfer function into which a minimum value thereof is substituted is assumed Timin, a transfer function into which a mean value thereof is substituted is assumed Timid, and δv( ) is assumed using formula:
vi—mid_max=δv(Timid, Timax)
vi—min_mid=δv(Timin, Timid)
vi—min_max=δv(Timin, Timax)

### Claim 8 (depends on 7)

The computer processor of claim 7, wherein said candidate is chosen by using said plant parameter vector is chosen based on a value of (|vi—min_mid−vi—mid_max|+vi—min_max).

### Claim 9 (depends on 7)

The program according to claim 7, wherein said step of choosing a candidate includes choosing a plurality of candidates such that at least one candidate with a largest value of (|vi—min_mid−vi—mid_max|+vi—min_max) and another candidate with a second largest value of (|vi—min_mid−vi—mid_max|+vi—min_max), are chosen, such that bilinear interpolation is performed at four points to which p1_min and p2_min, p1_min and p2_max, p1_max and p2_min, and p1_max and p2_max are fixed, respectively, where p1 indicates said candidate with said largest value and p2 indicates the candidate with said second largest value.

### Claim 10

A computer implemented system for constructing a controller from a plant described by an LPV model to which a scheduling parameter is given, the system comprising:
a memory means;
an LPV model and its scheduling parameter which are stored in the memory means;
one or more processors enabled to calculating v gaps respectively for Min, Max, and a mean value of each candidate of a plant parameter vector of the LPV model based on a requirement of constraints;
said processor having means for choosing a candidate of the plant parameter vector based on the magnitude of differences between the v gaps and for converting the LPV model into LMI and finding controllers, according to an H∞ criterion, at all combination end points of a maximum value and a minimum value of the plant parameter vector thus chosen; and
said processor having means for constructing a controller for the plant by bilinear interpolation weighted by the v gaps calculated for the plant parameter vector thus chosen.

### Claim 11 (depends on 10)

The system according to claim 10, wherein said processor calculates v gaps, via a transfer function into which a maximum value of an i-th element of said scheduling parameter is substituted is assumed Timax, a transfer function into which a minimum value thereof is substituted is assumed Timin, a transfer function into which a mean value thereof is substituted is assumed Timid, and δv( ) is assumed using formula:
vi—mid_max=δv(Timid, Timax)
vi—min_mid=δv(Timin, Timid)
vi—min_max=δv(Timin, Timax)

### Claim 12 (depends on 10)

The system according to claim 10 wherein said candidate is chosen by using said plant parameter vector is chosen based on a value of (|vi—min_mid−vi—mid_max|+vi—min_max).

### Claim 13 (depends on 10)

The system according to claim 10, wherein said step of choosing a candidate includes choosing a plurality of candidates such that at least one candidate with a largest value of (|vi—min_mid−vi—mid_max|+vi—min_max) and another candidate with a second largest value of (|vi—min_mid−vi—mid_max|+vi—min_max), are chosen, such that bilinear interpolation is performed at four points to which p1_min and p2_min, p1_min and p2_max, p1_max and p2_min, and p1_max and p2_max are fixed, respectively, where p1 indicates said candidate with said largest value and p2 indicates the candidate with said second largest value.