# US 2012/0254819 A1 · Circuit diagram creation support method and apparatus

> Agents: this data is available as JSON from the patentgrep API and MCP server — see https://patentgrep.com/llms.txt

- Number: US 2012/0254819 A1
- Document ID: US20120254819A1
- Status: Published application
- Kind: A1
- Application number: 13/426,658
- Filed: 2012-03-22
- Published: 2012-10-04
- Earliest claimed: 2011-03-28
- Assignees: Fujitsu Limited
- Inventors: Miki TAKAGI
- Web page: https://patentgrep.com/patent/US20120254819A1

## CPC

- G06F 30/394: Routing (G06F30/396 takes precedence)
- G06F 30/30: Circuit design
- G06F: ELECTRIC DIGITAL DATA PROCESSING (computer systems based on specific computational models G06N)

## Abstract

The disclosed method includes: generating data of a first circuit diagram by disposing a block that represents a connection relationship between first branch lines included in a first bus line in a second circuit diagram and second branch lines included in a second bus line to be connected to the first bus line in the second circuit diagram so as to connect the first bus line with the second bus line through the block, wherein the block represents that the connection relationship identified by connection relationship data is depicted in detail in a lower-layer than a layer of the block; and generating display data including the connection relationship data and the first circuit diagram to output the generated display data.

## Claims

### Claim 1

A computer-readable, non-transitory storage medium storing a program for causing a computer to execute a procedure comprising:
generating data of a first circuit diagram by disposing a block that represents a connection relationship between first branch lines included in a first bus line in a second circuit diagram and second branch lines included in a second bus line to be connected to the first bus line in the second circuit diagram so as to connect the first bus line with the second bus line through the block, wherein the block represents that the connection relationship identified by connection relationship data is depicted in detail in a lower-layer than a layer of the block; and
generating display data including the connection relationship data and the first circuit diagram to output the generated display data.

### Claim 2 (depends on 1)

The computer-readable, non-transitory storage medium as set forth in claim 1, wherein the procedure comprises:
outputting the connection relationship data in a mode that a user is capable of editing the connection relationship data; and
in response to receipt of edited connection relationship data, updating the connection relationship data by the edited connection relationship data.

### Claim 3 (depends on 1)

The computer-readable, non-transitory storage medium as set forth in claim 1, wherein the procedure comprises:
first ordering the first branch lines according to names of the first branch lines or a temporal sequence that the first branch lines were disposed, by using first data including, for each bus line, names of branch lines included in the bus line or data of a temporal sequence that the branch lines included in the bus line were disposed;
second ordering the second branch lines according to names of the second branch lines or a temporal sequence that the second branch lines were disposed, by using the first data; and
identifying connection relationship between the first branch lines and the second branch lines by associating the first branch lines with the second branch lines based on results of the first ordering and the second ordering.

### Claim 4 (depends on 3)

The computer-readable, non-transitory storage medium as set forth in claim 3, wherein the procedure comprises:
identifying, for each bus line included in the second circuit diagram, the number of branch lines included in the bus line by using the first data; and
splitting bus lines to be connected to the first bus line and to the second bus line so as to make the number of branch lines in an input side and the number of branch lines in an output side coincide.

### Claim 5 (depends on 1)

The computer-readable, non-transitory storage medium as set forth in claim 1, wherein the procedure comprises:
generating data of a third circuit diagram that is a circuit diagram within the block by using the connection relationship data; and
outputting the data of the third circuit diagram in response to detecting that the block in the first circuit diagram is selected.

### Claim 6 (depends on 5)

The computer-readable, non-transitory storage medium as set forth in claim 5, wherein at least one bus line of bus lines included in the third circuit diagram is split to a plurality of sub-bus lines and the plurality of sub-bus lines are disposed in the third circuit diagram, and an identifier representing a portion to be connected to another sub-bus line among the plurality of sub-bus lines is assigned to each of the plurality of sub-bus lines.

### Claim 7

A circuit diagram creation support method comprising:
generating, by using a computer, data of a first circuit diagram by disposing a block that represents a connection relationship between first branch lines included in a first bus line in a second circuit diagram and second branch lines included in a second bus line to be connected to the first bus line in the second circuit diagram so as to connect the first bus line with the second bus line through the block, wherein the block represents that the connection relationship identified by connection relationship data is depicted in detail in a lower-layer than a layer of the block; and
generating, by using the computer, display data including the connection relationship data and the first circuit diagram to output the generated display data.

### Claim 8 (depends on 7)

The circuit diagram creation support method as set forth in claim 7, further comprising:
outputting the connection relationship data in a mode that a user is capable of editing the connection relationship data; and
in response to receipt of edited connection relationship data, updating the connection relationship data by the edited connection relationship data.

### Claim 9 (depends on 7)

The circuit diagram creation support method as set forth in claim 7, further comprising:
first ordering the first branch lines according to names of the first branch lines or a temporal sequence that the first branch lines were disposed, by using first data including, for each bus line, names of branch lines included in the bus line or data of a temporal sequence that the branch lines included in the bus line were disposed;
second ordering the second branch lines according to names of the second branch lines or a temporal sequence that the second branch lines were disposed, by using the first data; and
identifying connection relationship between the first branch lines and the second branch lines by associating the first branch lines with the second branch lines based on results of the first ordering and the second ordering.

### Claim 10 (depends on 9)

The circuit diagram creation support method as set forth in claim 9, wherein the procedure comprises:
identifying, for each bus line included in the second circuit diagram, the number of branch lines included in the bus line by using the first data; and
splitting bus lines to be connected to the first bus line and to the second bus line so as to make the number of branch lines in an input side and the number of branch lines in an output side coincide.

### Claim 11 (depends on 7)

The circuit diagram creation support method as set forth in claim 7, further comprising:
generating data of a third circuit diagram that is a circuit diagram within the block by using the connection relationship data; and
outputting the data of the third circuit diagram in response to detecting that the block in the first circuit diagram is selected.

### Claim 12 (depends on 11)

The circuit diagram creation support method as set forth in claim 11, wherein at least one bus line of bus lines included in the third circuit diagram is split to a plurality of sub-bus lines and the plurality of sub-bus lines are disposed in the third circuit diagram, and an identifier representing a portion to be connected to another sub-bus line among the plurality of sub-bus lines is assigned to each of the plurality of sub-bus lines.

### Claim 13

A circuit diagram creation support apparatus comprising:
a memory; and
a processor configured to execute a procedure comprising:
generating data of a first circuit diagram by disposing a block that represents a connection relationship between first branch lines included in a first bus line in a second circuit diagram and second branch lines included in a second bus line to be connected to the first bus line in the second circuit diagram so as to connect the first bus line with the second bus line through the block, wherein the block represents that the connection relationship identified by connection relationship data stored in the memory is depicted in detail in a lower-layer than a layer of the block; and
generating display data including the connection relationship data and the first circuit diagram to output the generated display data.

### Claim 14 (depends on 13)

The circuit diagram creation support apparatus as set forth in claim 13, wherein the procedure comprises:
outputting the connection relationship data in a mode that a user is capable of editing the connection relationship data; and
in response to receipt of edited connection relationship data, updating the connection relationship data by the edited connection relationship data.

### Claim 15 (depends on 13)

The circuit diagram creation support apparatus as set forth in claim 13, wherein the procedure comprises:
first ordering the first branch lines according to names of the first branch lines or a temporal sequence that the first branch lines were disposed, by using first data including, for each bus line, names of branch lines included in the bus line or data of a temporal sequence that the branch lines included in the bus line were disposed;
second ordering the second branch lines according to names of the second branch lines or a temporal sequence that the second branch lines were disposed, by using the first data; and
identifying connection relationship between the first branch lines and the second branch lines by associating the first branch lines with the second branch lines based on results of the first ordering and the second ordering.

### Claim 16 (depends on 15)

The circuit diagram creation support method as set forth in claim 15, wherein the procedure comprises:
identifying, for each bus line included in the second circuit diagram, the number of branch lines included in the bus line by using the first data; and
splitting bus lines to be connected to the first bus line and to the second bus line so as to make the number of branch lines in an input side and the number of branch lines in an output side coincide.

### Claim 17 (depends on 13)

The circuit diagram creation support method as set forth in claim 13, wherein the procedure comprises:
generating data of a third circuit diagram that is a circuit diagram within the block by using the connection relationship data; and
outputting the data of the third circuit diagram in response to detecting that the block in the first circuit diagram is selected.

### Claim 18 (depends on 17)

The circuit diagram creation support method as set forth in claim 17, wherein at least one bus line of bus lines included in the third circuit diagram is split to a plurality of sub-bus lines and the plurality of sub-bus lines are disposed in the third circuit diagram, and an identifier representing a portion to be connected to another sub-bus line among the plurality of sub-bus lines is assigned to each of the plurality of sub-bus lines.