# US 2012/0253677 A1 · Lag Calculation with Caving Correction in Open Hole

> Agents: this data is available as JSON from the patentgrep API and MCP server — see https://patentgrep.com/llms.txt

- Number: US 2012/0253677 A1
- Document ID: US20120253677A1
- Status: Published application
- Kind: A1
- Application number: 13/076,014
- Filed: 2011-03-30
- Published: 2012-10-04
- Earliest claimed: 2011-03-30
- Assignees: Weatherford/Lamb, Inc.
- Inventors: Gabriel Frunza
- Web page: https://patentgrep.com/patent/US20120253677A1

## CPC

- G01N 33/2823: {Raw oil, drilling fluid or polyphasic mixtures}
- E21B 47/003: Determining well or borehole volumes
- E21B 47/11: using tracers; using radioactivity
- E21B 49/005: {Testing the nature of borehole walls or the formation by using drilling mud or cutting data}
- G01N: INVESTIGATING OR ANALYSING MATERIALS BY DETERMINING THEIR CHEMICAL OR PHYSICAL PROPERTIES (measuring or testing apparatus or processes other than immunoassay, involving enzymes or microorganisms C12M, C12Q)
- E21B: EARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS

## Abstract

A gas analyzer system that can detect atmospheric air gasses in drilling mud is used to calculate an actual lag time in a well. The calculated lag time and a theoretical lag time may be compared to estimate a caving percentage in an open hole section of the well.

## Claims

### Claim 1

A method of estimating an amount of caving in an open hole drilling well, comprising:
calculating an actual lag for a well by detecting a predetermined component of atmospheric air in a drilling fluid;
calculating a theoretical lag for the well; and
calculating a caving amount by comparing the actual lag and the theoretical lag.

### Claim 2 (depends on 1)

The method of claim 1, wherein the component of atmospheric air is nitrogen gas.

### Claim 3 (depends on 1)

The method of claim 1, repeating the acts of calculating an actual lag, calculating a theoretical lag, and calculating a caving amount for a plurality of connection events.

### Claim 4 (depends on 3)

The method of claim 3, further comprising:
calculating a trend in a borehole caving over time.

### Claim 5 (depends on 3)

The method of claim 3, further comprising:
calculating a trend in a borehole caving corresponding to location.

### Claim 6 (depends on 3)

The method of claim 3, further comprising:
correlating the actual lag, theoretical lag, and caving amount for a plurality of connection events with data from other sources to indicate a state of a borehole.

### Claim 7 (depends on 3)

The method of claim 3, wherein the plurality of connection events is every connection event for the well.

### Claim 8 (depends on 3)

The method of claim 3, further comprising:
identifying specific downhole locations where deviations from a nominal borehole occurred.

### Claim 9 (depends on 3)

The method of claim 3, further comprising:
storing the actual lag in a database.

### Claim 10 (depends on 3)

The method of claim 3, further comprising:
storing the caving amount in a database.

### Claim 11 (depends on 1)

The method of claim 1, wherein the act of calculating an actual lag comprises:
detecting a connection event;
detecting a change in an amount of the predetermined component of atmospheric air in the drilling fluid corresponding to the connection event;
determining a first quantity of mud pump strokes at an end of the connection event;
determining a second quantity of mud pump strokes at a beginning of the change in the amount of the predetermined component of atmospheric air in the drilling fluid corresponding to the connection event;
determining a third quantity of down strokes of the mud pump; and
calculating the actual lag by subtracting the second quantity and the third quantity from the first quantity.

### Claim 12

A gas analyzer system, comprising:
a gas analyzer probe, configured to detect and measure a predetermined component of atmospheric air in a drilling fluid; and
a gas analyzer system unit, coupled to the gas analyzer probe, comprising:
software for execution by the gas analyzer system unit, comprising instructions that when executed:
calculating an actual lag for a well by detecting the predetermined component of atmospheric air in the drilling fluid;
calculating a theoretical lag for the well; and
calculating a caving amount by comparing the actual lag and the theoretical lag.

### Claim 13 (depends on 12)

The gas analyzer system of claim 12, wherein the predetermined component of atmospheric air is nitrogen gas.

### Claim 14 (depends on 12)

The gas analyzer system of claim 12, wherein the gas analyzer system unit repeats the acts of calculating an actual lag, calculating a theoretical lag, and calculating a caving amount for a plurality of connection events.

### Claim 15 (depends on 14)

The gas analyzer system of claim 14, wherein the plurality of connection events is every connection event for the well.

### Claim 16 (depends on 14)

The gas analyzer system of claim 14, further comprising:
a database, coupled to the gas analyzer system unit,
wherein the software comprises instructions that when executed by the gas analyzer system unit cause the gas analyzer system unit to perform actions further comprising:
storing the actual lag in the database.

### Claim 17 (depends on 14)

The gas analyzer system of claim 14, further comprising:
a database, coupled to the gas analyzer system unit,
wherein the software comprises instructions that when executed by the gas analyzer system unit cause the gas analyzer system unit to perform actions further comprising:
storing the caving amount in a database.

### Claim 18 (depends on 12)

The gas analyzer system of claim 12, wherein the act of calculating an actual lag comprises:
detecting a connection event;
detecting a change in an amount of the predetermined component of atmospheric air in the drilling fluid corresponding to the connection event;
determining a first quantity of mud pump strokes at an end of the connection event;
determining a second quantity of mud pump strokes at a beginning of the change in the amount of the predetermined component of atmospheric air in the drilling fluid corresponding to the connection event;
determining a third quantity of down strokes of the mud pump; and
calculating the actual lag by subtracting the second quantity and the third quantity from the first quantity.

### Claim 19

A non-volatile machine-readable storage media, containing instructions that when executed by a gas analyzer system unit cause the gas analyzer system unit to perform actions comprising:
calculating an actual lag for a well by detecting a predetermined component of atmospheric air in a drilling fluid;
calculating a theoretical lag for the well; and
calculating a caving amount by comparing the actual lag and the theoretical lag.

### Claim 20 (depends on 19)

The non-volatile machine-readable storage media of claim 19, wherein the act of calculating an actual lag comprises:
detecting a connection event;
detecting a change in an amount of the predetermined component of atmospheric air in the drilling fluid corresponding to the connection event;
determining a first quantity of mud pump strokes at an end of the connection event;
determining a second quantity of mud pump strokes at a beginning of the change in the amount of the predetermined component of atmospheric air in the drilling fluid corresponding to the connection event;
determining a third quantity of down strokes of the mud pump; and
calculating the actual lag by subtracting the second quantity and the third quantity from the first quantity.