System and method for golf course cart path construction
OwnerGerald Lynn Lemons, William Robert Fullerinventors
Life of this patent
Estimating the term…
Abstract
A system and method for building and renovating golf course paths to provide an alternate golf cart path with a drainage system and durable natural path for golf. A drainage system and a layer of gravel is installed over the entire sub grade of the path. A layer of crumb rubber is placed over the gravel. A pre-polymer is sprayed onto the layer of crumb rubber and gravel to secure it in place. The polymer sprayed is permitted to cure for approximately 24-48 hours.
Claims11
A system for golf course cart path construction, said system comprising:
- a pre-polymer container;
- a pre-polymer container heater connected to said pre-polymer container in such a manner that allows for the pre-polymer container heater to heat contents of said pre-polymer container;
- a power source connected to said pre-polymer container heater such that said power source can provide power to said pre-polymer container heater;
- a diaphragm pump;
- a suction hose, wherein said suction hose connects the pre-polymer container to the diaphragm pump such that contents of the pre-polymer container can be passed through the suction hose and into the diaphragm pump;
- a spray wand;
- and
- a dispenser hose, wherein said dispenser hose connects the diaphragm pump to said spray wand such that said contents of the pre-polymer container can be passed through the diaphragm pump and into the spray wand,
- wherein the spray wand is configured to allow the even dispersing of said contents of said pre-polymer container onto a golf course cart path.
6 more elements
A method for creating a pathway, said method comprising the steps of:
- preparing a sub grade;
- excavating one or more drainage trenches in said sub grade;
- installing one or more perforated drain pipes in said one or more drainage trenches;
- surrounding at least a portion of each of said one or more perforated drain pipes by pea gravel;
- layering said sub grade, said one or more drainage trenches and said one or more perforated drain pipes with a layer of gravel;
- compacting said layer of gravel;
- layering, over said layer of gravel, a thin layer of crumb rubber;
- raking said thin layer of crumb rubber;
- smoothing said thin layer of crumb rubber;
- rolling said thin layer of crumb rubber;
- and
- spraying said thin layer of crumb rubber with the pre-polymer.
9 more elements