# US 2012/0200139 A1 · Underground mining

> Agents: this data is available as JSON from the patentgrep API and MCP server — see https://patentgrep.com/llms.txt

- Number: US 2012/0200139 A1
- Document ID: US20120200139A1
- Status: Published application
- Kind: A1
- Application number: 13/381,470
- Filed: 2010-06-30
- Published: 2012-08-09
- Earliest claimed: 2009-06-30
- Assignees: Technological Resources Pty. Limited
- Inventors: Fredric Christopher Delabbio; Max Edward Oddie
- Web page: https://patentgrep.com/patent/US20120200139A1

## CPC

- E21D 1/08: while moving the lining downwards {(lowering the lining into a ready shaft E21D5/01; sheet piles E02D5/02)}
- E21D 1/06: with shaft-boring cutters (drilling machines E21B, E21C)
- E21D 5/04: with brick, concrete, stone, or similar building materials (E21D5/01, E21D5/012, E21D5/016 take precedence)
- E21D 7/02: Arrangement of guides for cages in shafts; Connection of guides for cages to shaft walls (guideways or guides for elevators B66B7/02)
- E21D 9/00: Tunnels or galleries, with or without linings; Methods or apparatus for making thereof (E02D29/045, E02D29/063 take precedence; linings per se E21D11/00); Layout of tunnels or galleries
- E21D 9/12: Devices for removing or hauling away excavated material or spoil; Working or loading platforms (underground transport E21F13/00)
- E21D: SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS (soil-conditioning or soil-stabilising materials C09K17/00; drilling or cutting machines for mining or quarrying E21C; safety devices, transport, rescue, ventilation or drainage E21F)

## Abstract

In developing an underground mine a mine shaft 80 is formed by excavating earth and removing excavated material from the shaft 80 by a material transport system comprising skips 36 movable up and down on skip guides within the shaft. Tunnels 82 are launched from a bottom part of shaft 80 by excavating a cavern 81 in which a tunnel boring machine is assembled and operated to bore the tunnels 82. Material from the tunnel excavation is transported from the tunnels via conveyor 87 to the material transport system established within the shaft during formation of the shaft which is operated to transport that material to an earth surface region.

## Claims

### Claim at position 1

1-20. (canceled)

### Claim 21

A method of developing an underground mine, comprising:
forming a mine shaft by excavating earth to form a hole extending downwardly from an earth surface region;
removing excavated material from the hole during the formation of the shaft by a material transport system operable to transport the excavated material upwardly through the hole to the earth surface region for discharge at the surface region;
launching one or more tunnels from a bottom part of the shaft when formed by excavating outwardly from the shaft; and
removing material excavated in the tunnel excavation by transporting that material from the tunnel to the material transport system established during formation of the shaft and operating that system to transport the material to the surface region.

### Claim 22 (depends on 21)

The method as claimed in claim 21, wherein the tunnel launching is carried out by firstly excavating a cavern at the bottom part of the shaft and then excavating a tunnel or tunnels from the cavern.

### Claim 23 (depends on 22)

The method as claimed in claim 22, wherein the cavern is excavated to extend to opposite sides of the shaft.

### Claim 24 (depends on 22)

The method as claimed in claim 22, wherein the cavern is excavated by drilling and blasting and removing excavated material.

### Claim 25 (depends on 22)

The method as claimed in claim 22, wherein tunnel boring machine components are lowered down the shaft and assembled within the cavern into a tunnel boring machine operable to bore outwardly from the cavern to form the tunnel or tunnels.

### Claim 26 (depends on 21)

The method as claimed in claim 21, wherein the excavation of earth to form the shaft is carried out by an excavator disposed below the material transport system for transporting excavated material to the surface region.

### Claim 27 (depends on 26)

The method as claimed in claim 26, wherein the excavator is an earth boring machine comprising a rotary cutting head.

### Claim 28 (depends on 26)

The method as claimed in claim 26, wherein, on completion of the shaft formation and prior to the tunnel launch, the excavator is wholly or partly salvaged by removing parts and hoisting the removed parts up the shaft to the earth surface region.

### Claim 29 (depends on 26)

The method as claimed in claim 26, wherein the excavator or part of the excavator is buried at the bottom of the shaft prior to the tunnel launch.

### Claim 30 (depends on 21)

The method as claimed in claim 21, wherein the material transport system comprises one or more skips moveable up and down on skip guides within the hole.

### Claim 31 (depends on 30)

The method as claimed in claim 30, wherein the hole is progressively lined and provided with skip guide extensions as formation of the shaft proceeds.

### Claim 32 (depends on 30)

The method as claimed in claim 30, wherein the material transport system comprises a transfer station at which material excavated in the formation of the shaft is transferred into the skip or skips for transport to the surface region and the transfer station is moved downwardly as excavation progresses.

### Claim 33 (depends on 32)

The method as claimed in claim 32, wherein on completion of the shaft formation, the transfer station is at or near the bottom of the shaft and the tunnel excavation material is fed to the transfer station for transfer into the skip or skips.

### Claim 34 (depends on 32)

The method as claimed in claim 32, wherein there is a pair of said skips movable up and down within the shaft along adjacent pathways to, in turn, receive excavated material and transport that material to the surface region for discharge at the surface region and to then return downwardly to the transfer station.

### Claim 35 (depends on 34)

The method as claimed in claim 34, wherein there is a pair of bins at the transfer station to receive excavated material and to discharge discrete loads of that material intermittently into the skips.

### Claim 36 (depends on 22)

The method as claimed in claim 22, wherein the excavation of earth to form the shaft is carried out by an earth boring machine comprising a rotary cutting head disposed below the material transport system for transporting excavated material to the surface region, the earth boring machine is fitted above the cutting head with rock drills operable to drill outwardly extending rock holes about the periphery of the shaft hole and excavation of the cavern is initiated by operating the rock drills to form outwardly extending blast holes about the periphery of the shaft hole at the bottom part of the shaft hole, setting and detonating explosive charges within the blast holes to excavate an initial station from which the cavern and tunnel or tunnels are developed.

### Claim 37 (depends on 36)

The method as claimed in claim 36, wherein the blast holes are blasted in stages and the earth boring machine is raised above the blast zone for the blast of each stage.

### Claim 38 (depends on 36)

The method as claimed in claim 36, wherein the material excavated by the blasting is allowed or caused to fall to the bottom of the shaft hole and the shaft boring machine is operated to pick up that material and feed it to the material transport system for transport to the surface region.

### Claim 39 (depends on 38)

The method as claimed in claim 38, wherein the material transport system comprises one or more skips moveable up and down within the hole and a transfer station at which material excavated in the formation of the shaft is transferred into the skip or skips for transport to the surface region, the transfer station is moved downwardly as excavation progresses and after drilling and blasting to form the enlarged station the earth boring machine is operated to extend the shaft downwardly until the transfer station reaches the launching station and can receive excavated material directly from the launching station and the tunnel or tunnels extended from it.

### Claim 40 (depends on 39)

The method as claimed in claim 39, comprising a pair of said skips moveable up and down within the shaft on skip guides and a pair of excavated material storage bins at the transfer station to receive excavated material and to discharge discrete loads of that material intermittently into the skips.