# US 2011/0209870 A1 · Gas flow system

> Agents: this data is available as JSON from the patentgrep API and MCP server — see https://patentgrep.com/llms.txt

- Number: US 2011/0209870 A1
- Document ID: US20110209870A1
- Status: Published application
- Kind: A1
- Application number: 13/097,685
- Filed: 2011-04-29
- Published: 2011-09-01
- Earliest claimed: 2008-09-03
- Assignees: En Cana Corporation
- Inventors: Kenneth W. Lowe; Javier Alfonso Becaria Valero; Clarence Robert Dyck
- Web page: https://patentgrep.com/patent/US20110209870A1

## CPC

- E21B 43/13: {specially adapted to dewatering of wells of gas producing reservoirs, e.g. methane producing coal beds}
- E21B: EARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS

## Abstract

A gas flow system for removing a liquid from a well bore and allowing for gas production is provided. The gas flow system comprises a casing in the well bore for allowing flow of the liquid and gas; a tubing string in the casing for allowing flow of the liquid and gas; pressure measurement devices for use in determining a rate of liquid influx into the well bore; a casing control valve moveable between various positions ranging from fully open to fully closed for controlling flow through the casing; a tubing control valve moveable between various positions ranging from fully open to fully closed for controlling flow through the tubing; and flow measurement devices for determining the rate of flow through the tubing and the total rate of flow. The system is switchable between a current production phase and an alternate production phase based on the determined rate of liquid influx, a tubing critical velocity and a gas flow rate through the tubing, wherein switching from a current production phase to an alternate production phase results in the either or both of a decrease in liquid build-up in the well bore and an increase in gas production rate and wherein the current production phase differs from the alternate production phase.

## Claims

### Claim at position 1

1-17. (canceled)

### Claim 18

A gas flow system for removing a liquid from a well bore and allowing for gas production, the system comprising:
a casing in the well bore for allowing flow of the liquid and gas;
a tubing string in the casing for allowing flow of the liquid and gas;
pressure measurement devices for use in determining a rate of liquid influx into the well bore;
a casing control valve moveable between various positions ranging from fully open to fully closed for controlling flow through the casing;
a tubing control valve moveable between various positions ranging from fully open to fully closed for controlling flow through the tubing;
flow measurement devices for determining the rate of flow through the tubing and the total rate of flow;
the system switchable between a current production phase and an alternate production phase based on the rate of liquid influx determined by the pressure measurement devices, a tubing critical velocity and a gas flow rate through the tubing by moving the casing control valve and the tubing control valve between the various positions ranging from fully open and fully closed, wherein switching from a current production phase to an alternate production phase results in either or both of a decrease in liquid build-up in the well bore and an increase in gas production rate and wherein the current production phase differs from the alternate production phase,
wherein the current production phase and the alternate production phase are selected from the group consisting of casing flow with auto cleanout, slipstreaming, siphon string/tubing flow and switching valves and wherein the current production phase is different from the alternate production phase.

### Claim 19 (depends on 18)

The gas flow system according to claim 18, wherein the system further comprises a programmable logic controller (PLC) in communication with the pressure measurement devices, the casing control valve, the tubing control valve and the flow measurement devices, the PLC adapted to determine the rate of liquid influx into the well bore, the critical rate, and control the casing control valve and the tubing control valve to alternate the current production phase the alternate production phase.

### Claim 20 (depends on 18)

The gas flow system according to claim 18, wherein the current production phase and the alternate production phase are each selected from a group of possible production phases, the group of possible production phases consisting of any three phases of: casing flow with auto cleanout, slipstreaming, siphon string/tubing flow and switching valves and wherein the current production phase is different from the alternate production phase.

### Claim 21 (depends on 18)

The gas flow system according to claim 18, wherein the current production phase and the alternate production phase are each selected from a group of possible production phases, the group of possible production phases consisting of any two phases of: casing flow with auto cleanout, slipstreaming, siphon string/tubing flow and switching valves and wherein the current production phase is different from the alternate production phase.

### Claim 22 (depends on 19)

The gas flow system according to claim 19, wherein the PLC is programmed to switch the system between the current production phase and the alternate production phase based on a liquid to gas influx rate and/or critical rate, wherein the current production phase and the alternate production phase are selected from a casing flow with auto cleanout production phase and a slipstreaming production phase.

### Claim 23 (depends on 19)

The gas flow system according to claim 19, wherein the PLC is programmed to switch the system between the current production phase and the alternate production phase based on the critical gas flow rate, wherein the current production phase and the alternate production phase are selected from a slipstreaming production phase and a siphon string/tubing flow production phase.

### Claim 24 (depends on 19)

The gas flow system according to claim 19, wherein the PLC is programmed to switch the system between the current production phase and the alternate production phase based on the critical gas flow rate and a liquid to gas influx rate, wherein the current production phase and the alternate production phase are selected from a siphon string production phase and a switching valves production phase.