# US 2010/0169029 A1 · Diagnosis and position identification for remote capacitor banks

> Agents: this data is available as JSON from the patentgrep API and MCP server — see https://patentgrep.com/llms.txt

- Number: US 2010/0169029 A1
- Document ID: US20100169029A1
- Status: Published application
- Kind: A1
- Application number: 12/347,105
- Filed: 2008-12-31
- Published: 2010-07-01
- Earliest claimed: 2008-12-31
- Inventors: Carl L. Benner; Karthick Muthu-Manivannan; Alexandre Perera-Lluna; Peng Xu; Billy Don Russell
- Web page: https://patentgrep.com/patent/US20100169029A1

## CPC

- G01R 31/64: Testing of capacitors
- G01R 19/2513: {Arrangements for monitoring electric power systems, e.g. power lines or loads; Logging}
- G01R 31/40: Testing power supplies (testing photovoltaic devices H02S50/10)
- G01R: MEASURING ELECTRIC VARIABLES; MEASURING MAGNETIC VARIABLES (indicating correct tuning of resonant circuits H03J3/12)

## Abstract

A method of evaluating one or more capacitor banks in an electrical power system includes: (a) acquiring data representing a signal of interest of the power system, where the data describes a plurality of power system events; and (b) based on one or more patterns contained in the data, identifying at least one of the power system events as being associated with capacitor operation.

## Claims

### Claim 1

A method of evaluating one or more capacitor banks in an electrical power system, comprising:
(a) acquiring data representing a signal of interest of the power system, where the data describes a plurality of power system events; and
(b) based on one or more patterns contained in the data, identifying at least one of the power system events as being associated with a capacitor operation.

### Claim 2 (depends on 1)

The method of claim 1 further comprising classifying the capacitor operation as normal or abnormal.

### Claim 3 (depends on 1)

The method of claim 1 further comprising:
(a) extracting at least one feature characteristic of a capacitor operation from the data; and
(b) identifying one or more capacitor banks as potentially being involved in the at least one capacitor operation, based at least in part on the at least one extracted feature.

### Claim 4 (depends on 3)

The method of claim 3 wherein the at least one extracted feature is a voltage transient consistent with capacitor bank switch contacts alternately making and breaking connection several times per second.

### Claim 5 (depends on 3)

The method of claim 3 wherein the one or more capacitor banks includes at least one capacitor for each of a plurality of phases, and the at least one extracted feature is a volt-ampere reactive power step size for each phase that occurs during a capacitor operation.

### Claim 6 (depends on 3)

The method of claim 3 wherein the capacitor bank includes at least one capacitor for each of a plurality of phases, and the at least one extracted feature is a sequence in which the phases switch on or off.

### Claim 7 (depends on 3)

The method of claim 3 wherein the capacitor bank includes at least one capacitor for each of a plurality of phases, and the at least one extracted feature is a time interval between the phases when the phases switch on or off.

### Claim 8 (depends on 3)

The method of claim 3 wherein step (a) comprises extracting a plurality of features from the data, and step (b) comprises grouping the extracted features into one or more clusters, wherein each cluster represents a repeated event occurring at a specific capacitor bank.

### Claim 9 (depends on 1)

The method of claim 1 wherein the data is taken from multiple geographic monitoring points in the electrical power system.

### Claim 10 (depends on 9)

The method of claim 9 wherein the data includes information as to whether the power system events have occurred upstream or downstream relative to each of the monitoring points.

### Claim 11 (depends on 2)

The method of claim 2 further comprising:
(a) counting the number of capacitor operations over a defined period of time;
(b) comparing the number of operations to a predetermined limit; and
(c) classifying the operations as abnormal if the predetermined limit is exceeded.

### Claim 12 (depends on 2)

The method of claim 2 further comprising:
(a) measuring the frequency of capacitor operations over a defined period of time;
(b) comparing the frequency of operations to a predetermined limit; and
(c) classifying the operations as abnormal if the predetermined limit is exceeded.

### Claim 13

A computer program product comprising one or more computer readable media having stored thereon a plurality of instructions that, when executed by one or more processors of a system, causes the one or more processors to carry out a method comprising:
(a) acquiring data representing a signal of interest of the power system, where the data describes a plurality of power system events; and
(b) based on one or more patterns contained in the data, identifying at least one of the power system events as being associated with a capacitor operation.

### Claim 14 (depends on 13)

The computer program product of claim 13 wherein the instructions further cause the one or more processors to classify the capacitor operation as normal or abnormal.

### Claim 15 (depends on 13)

The computer program product of claim 13 wherein the instructions further cause the one or more processors to:
(a) extract at least one feature characteristic of a capacitor operation from the data; and
(b) identify one or more capacitor banks as potentially being involved in the at least one capacitor operation, based at least in part on the at least one extracted feature.

### Claim 16 (depends on 15)

The computer program product of claim 15 wherein the at least one extracted feature is a voltage transient consistent with capacitor bank switch contacts alternately making and breaking connection several times per second.

### Claim 17 (depends on 15)

The computer program product of claim 15 wherein the one or more capacitor banks includes at least one capacitor for each of a plurality of phases, and the at least one extracted feature is a volt-ampere reactive power step size for each phase that occurs during a capacitor operation.

### Claim 18 (depends on 15)

The computer program product of claim 15 wherein the capacitor bank includes at least one capacitor for each of a plurality of phases, and the at least one extracted feature is a sequence in which the phases switch on or off.

### Claim 19 (depends on 15)

The computer program product of claim 15 wherein the capacitor bank includes at least one capacitor for each of a plurality of phases, and the at least one extracted feature is a time interval between the phases when the phases switch on or off.

### Claim 20 (depends on 15)

The computer program product of claim 15 wherein step (a) comprises extracting a plurality of features from the data, and step (b) comprises grouping the extracted features into one or more clusters, wherein each cluster represents a repeated event occurring at a specific capacitor bank.

### Claim 21 (depends on 13)

The computer program product of claim 13 wherein the data is taken from multiple geographic monitoring points in the electrical power system.

### Claim 22 (depends on 21)

The computer program product of claim 21 wherein the data includes information as to whether the power system events have occurred upstream or downstream relative to each of the monitoring points.

### Claim 23 (depends on 14)

The computer program product of claim 14 wherein the instructions further cause the one or more processors to:
(a) count the number of capacitor operations over a defined period of time;
(b) compare the number of operations to a predetermined limit; and
(c) classify the operations as abnormal if the predetermined limit is exceeded.

### Claim 24 (depends on 14)

The computer program product of claim 14 wherein the instructions further cause the one or more processors to:
(a) measure the frequency of capacitor operations over a defined period of time;
(b) compare the frequency of operations to a predetermined limit; and
(c) classify the operations as abnormal if the predetermined limit is exceeded.