# US 2009/0276375 A1 · Analysis of powder metal production of a component

> Agents: this data is available as JSON from the patentgrep API and MCP server — see https://patentgrep.com/llms.txt

- Number: US 2009/0276375 A1
- Document ID: US20090276375A1
- Status: Published application
- Kind: A1
- Application number: 12/151,112
- Filed: 2008-05-05
- Published: 2009-11-05
- Earliest claimed: 2008-05-05
- Assignees: Burgess-Norton Mfg. Co., Inc.
- Inventors: Brett Vasseur; Kevin Skibinski; Vince Perez
- Web page: https://patentgrep.com/patent/US20090276375A1

## CPC

- G06Q 10/00: Administration; Management
- G06Q 10/063: Operations research, analysis or management
- G06Q 30/0283: Price estimation or determination
- G06Q 99/00: Subject matter not provided for in other groups of this subclass
- G06Q: INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR

## Abstract

A method of calculating the cost saving for producing a metallic component by the use of a powder metal process is provided. The method includes the steps of analyzing the current production method of the component, usually machining, to determine the current unit cost. The customer would agree to purchase an agreed supply of components for an agreed period of time for the components that could be supplied with an agreed cost savings. The production of the component utilizing powder metal process is then analyzed to determine the powder metal unit cost. The savings for production of the component utilizing the powder metal process is then presented to the customer. The customer could agree to purchase the agreed supply of components for an agreed period of time. If agreed, the test production of the component utilizing a powder metal process is then performed. If successful, a final tooling and production quotation for the production of the component is then provided to the customer.

## Claims

### Claim 1

A method for calculating the cost savings for producing a component utilizing a powder metallurgy process, the method comprising the steps of:
analyzing current production methods for the component to determine a unit cost for such current production method and to determine whether the component can be produced utilizing a powder metallurgy process,
obtaining agreement to supply the requirements of any such components if a minimum cost savings can be achieved,
analyzing production of the component utilizing a powder metallurgy process to determine a unit cost for such component utilizing a powder metallurgy process,
and quoting such unit cost for the production of such component utilizing a powder metallurgy process and the associated cost savings for producing the component utilizing a powder metallurgy process compared to the current production method,
and agreeing to supply the requirements of any component for which the minimum cost savings can be achieved for an agreed period of time.

### Claim 2 (depends on 1)

The method of claim 1
wherein current methods for producing the component include machining the component from a cut to size stock metal piece.

### Claim 3 (depends on 1)

The method of claim 1
wherein the analyzing of current production methods includes an analysis of optimizing the design of the component.

### Claim 4 (depends on 1)

The method of claim 1
further comparing providing a cost savings of at least 20%.

### Claim 5 (depends on 1)

The method of claim 1
further comprising the steps of providing a test tooling and production purchase order, and conducting test production of the component utilizing a powder metallurgy process.

### Claim 6 (depends on 5)

The method of claim 5
further comprising the steps of analyzing the test production of the component utilizing a powder metallurgy process and providing a final tooling and production quotation.

### Claim 7 (depends on 6)

The method of claim 6
further comprising the steps of calculating the cost of final tooling and factoring a portion of such cost into the final tooling and production quotation.

### Claim 8 (depends on 7)

The method of claim 7
further comprising the steps of entering into a guaranteed cost savings supply contract to supply the requirements of any such component for an agreed period of time.

### Claim 9

A method of contracting for the production of a part using a powder metal process, the method comprising the steps of:
assessing a part and its current production process,
obtaining a unit cost for producing the part using the current production process,
analyzing production of the part using a powder metal process to determine a unit cost for producing the part using a powder metal process,
agreeing to supply certain of the parts for which at least an agreed percent cost savings for production costs can be achieved,
comparing the unit cost for producing the part using the current production process and the unit cost for producing the part using a powder metal process and quoting the cost savings for producing the part using a powder metal process,
and agreeing to supply the agreed parts for which at least the agreed percent cost savings can be achieved.

### Claim 10 (depends on 9)

The method of claim 9
wherein current methods for producing the part include machining the part from a metal blank.

### Claim 11 (depends on 9)

The method of claim 9
wherein the analysis of current production of the part includes an analysis of improving the design of the part.

### Claim 12 (depends on 9)

The method of claim 9
further comprising the steps of conducting test production of the part using a powder metal process.

### Claim 13 (depends on 9)

The method of claim 9
Further comprising the step of providing a production price analysis for each component with a guaranteed cost savings.

### Claim 14 (depends on 12)

The method of claim 12
further comprising the steps of analyzing the test production of the part utilizing a powder metal process and providing a final tooling and production quotation.

### Claim 15 (depends on 14)

The method of claim 14
further comprising the steps of determining the cost of final tooling and factoring a portion of such cost into the final tooling and production quotation.

### Claim 16 (depends on 15)

The method of claim 15
further comprising the step of entering into a guaranteed cost savings contract.