# US 2008/0306805 A1 · Method and Apparatus for Queue-Based Automated Staff Scheduling

> Agents: this data is available as JSON from the patentgrep API and MCP server — see https://patentgrep.com/llms.txt

- Number: US 2008/0306805 A1
- Document ID: US20080306805A1
- Status: Published application
- Kind: A1
- Application number: 11/814,802
- Filed: 2005-12-09
- Published: 2008-12-11
- Earliest claimed: 2004-12-09
- Inventors: Suvas Vajracharya; David Setiawan; Robby Tjahjono
- Web page: https://patentgrep.com/patent/US20080306805A1

## CPC

- G06Q 10/109: Time management, e.g. calendars, reminders, meetings or time accounting
- G06Q 10/00: Administration; Management
- G06Q 10/063112: {Skill-based matching of a person or a group to a task}
- G06Q 10/063116: {Schedule adjustment for a person or group}
- G06Q 10/0635: Risk analysis of enterprise or organisation activities
- G06Q 10/1097: {using calendar-based scheduling for task assignment}
- G06Q: INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR

## Abstract

The invention disclosed herein provides a queue-based scheduling system, which comprises an automated staff scheduling computer program that is highly flexible in enforcing scheduling rules. This flexibility comes from the ability to: (1) Define conditional and unconditional rules; (2) Rank the rules/requests in varying priority as represented by a numeric value assigned to each rule/request; and (3) Specify rules both per individual and per group. These three abilities synergistically produce an automatic scheduling system that can enforce a wide variety of scheduling rules and requirements seen in actual staff scheduling situations. Furthermore, all these abilities rely on using a queue per scheduled assignment to hold requests and rules.

## Claims

### Claim 1

A queue-based scheduling apparatus for automated staff scheduling and for enforcing scheduling rules and requirements, comprising:
means for defining conditional and unconditional rules;
means for ranking rules and requests in varying priority as represented by a numeric value assigned to each rule and request; and
means for specifying rules both per individual and per group.

### Claim 2 (depends on 1)

The apparatus of claim 1, further comprising:
at least one queue per each scheduled assignment for holding requests and rules.

### Claim 3

A scheduling process, comprising the steps of:
collecting requests and rules using a graphical user-interface;
determining a scheduling period that has a user-defined start date and stop date;
creating a request queue for each day of a period;
for each request or rule, determining which days said request or rule is applicable;
for each applicable day, inserting a request into its queue;
sorting said days from most constrained to least constrained;
beginning scheduling from a most constrained day;
for each assignment in a day, creating a list of candidates for that assignment for that day;
for each candidate, associating a highest priority request in said request queue that applies to said candidate, wherein said highest priority value for a candidate is a candidate bid for a chosen assignment;
sorting said candidates according to a bid calculated in the immediately preceding step;
scheduling a candidate having a highest number;
determining a schedule for any remaining days.

### Claim 4 (depends on 3)

The method of claim 3, wherein said constraints on scheduling choices comprise either of conditional and unconditional constraints, wherein conditional constraints are only in effect if a certain scheduling condition applies.

### Claim 5 (depends on 3)

The method of claim 3, wherein a rule applies to either of a specific individual or a group of individuals.

### Claim 6 (depends on 3)

The method of claim 3, further comprising the step of:
associating rules with a number which describes a rank or a priority of that rule relative to other rules;
wherein a large positive number indicates that any individual under that rule is highly favored to be scheduled for the given shift on a given day;
wherein a large negative number indicates that any individual under that rule is not favored to be scheduled for the given shift on a given day; and
wherein an individual who is not subject to any rules has a priority point zero by default, indicating neutrality.

### Claim 7 (depends on 3)

The method of claim 3, further comprising the step of:
choosing a rule having a highest absolute value of priority points for an individual to compete with other individuals when more than one rule is to be applied.

### Claim 8 (depends on 3)

The method of claim 3, further comprising the steps of:
entering static or unconditional rules in the request queue prior to running the automated scheduler; and
entering conditional rules and requests during execution of the steps of said method, depending on the scheduling conditions;
wherein a highly adaptive scheduler is provided that changes its scheduling behavior during execution of the method, based on scheduling decisions made during execution of the method.

### Claim 9 (depends on 3)

The method of claim 3, further comprising the step of:
providing conditional rules, wherein each conditional rule has a set of conditions and a set of actions, wherein when all conditions are met, said set of actions is converted into a request.

### Claim 10 (depends on 3)

The method of claim 3, further comprising the step of:
providing an alternates list that exposes information in a form a user can use to override the choice that said automatic scheduler has made;
wherein said alternates list displays all constraints and requests that are currently imposed on alternate individuals.

### Claim 11 (depends on 3)

The method of claim 3, further comprising the steps of:
said auto scheduler generating schedules in multiple phases;
wherein during each phase, said automatic scheduler entirely schedules every assignment on every day in a scheduling period;
wherein on second and later phases, said auto scheduler learns from any hazards detected in earlier phases to generate a better overall schedule;
wherein said hazards are detected whenever said automatic scheduler cannot find an individual that would not violate some rule or request;
said automatic scheduler determining if any conditional rule has forced this situation and, if it did, finding a source or a condition of the rule that generated a violating request;
said automatic scheduler generating and submitting an internal request; and
in subsequent phases, said automatic scheduler avoiding said hazard by using said submitted request from previous phases.

### Claim 12 (depends on 3)

The method of claim 3, further comprising the steps of:
said auto scheduler randomly choosing different assignments on different days, rescheduling individuals until a global schedule improves or converges to an acceptable one; and
said auto scheduler summarizing a number of requests or rules in each queue that are in violation across all assignments in an entire schedule to determine whether a global schedule has improved after a scheduling adjustment;
wherein if a total number of violations decreases, said schedule has been improved and therefore is chosen over prior schedules.

### Claim 13

An auction method for resolving conflicting scheduling requests, comprising the steps of:
giving each scheduled individual a fixed number of points or currency to spend;
each individual then deciding how to distribute or spend said points to various requests, based on individual needs and preferences;
wherein an individual that spends the most points wins a request for an assignment for a specific day.

### Claim 14 (depends on 13)

The method of claim 13, wherein seniority or preferential treatment is provided to individuals by giving each individual a different number of points to spend based upon said seniority or preference.

### Claim 15 (depends on 13)

The method of claim 13, further comprising the steps of:
a scheduling administrator defining scheduling rules and policies and entering said scheduling rule and practices in the form of conditional or unconditional rules, wherein each rule is given a number that represents the priority of that rule;
users entering their request for a scheduling period, wherein said users, can assign a priority point to each of these requests, indicating a relative importance of said request;
once all rules and requests have been entered, said scheduling administrator initiating scheduling for a user-specified period defined by a begin date and an end date;
sorting said rules and requests for a given assignment for a day based on the value of said priorities;
matching candidates with requests to arrive at a candidate with a highest request priority, which is a scheduling choice for an assignment for that day;
once a schedule has been generated, said scheduling administrator optionally inspecting each scheduling choice and reviewing alternates for any particular assignment; and
when said schedule is complete, making said schedule available.

### Claim 16

An automated staff scheduling method, comprising the steps of:
allowing a large number of conflicting requests and rules to be entered;
said requests and rules competing in a scheduling decision based on numerical priority associated with said requests and rules.

### Claim 17 (depends on 16)

The method of claim 16, further comprising the step of:
resolving conflicts that arise in said scheduling decision.

### Claim 18 (depends on 16)

The method of claim 16, further comprising the step of:
implementing rules and exceptions to rules.

### Claim 19 (depends on 16)

The method of claim 16, further comprising the step of:
implementing auction-based bidding for contentious assignments and days based on which request has the highest priority.

### Claim 20 (depends on 16)

The method of claim 16, further comprising the step of:
exposing a rationale for a scheduling decision to a user by showing who is scheduled, their constraints, and a cause for said constraints.

### Claim 21 (depends on 16)

The method of claim 16, further comprising the step of:
manipulating a local queue of requests for each assignment.