# US 2008/0189125 A1 · Systems and methods for responding to business disruptions using hierarchically ordered response plans

> Agents: this data is available as JSON from the patentgrep API and MCP server — see https://patentgrep.com/llms.txt

- Number: US 2008/0189125 A1
- Document ID: US20080189125A1
- Status: Published application
- Kind: A1
- Application number: 12/004,055
- Filed: 2007-12-20
- Published: 2008-08-07
- Earliest claimed: 2007-02-02
- Assignees: Ubs AG
- Inventors: Robert Wainwright
- Web page: https://patentgrep.com/patent/US20080189125A1

## CPC

- G06Q 10/06: Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
- G06Q 10/0631: Resource planning, allocation, distributing or scheduling for enterprises or organisations
- G06Q 10/0635: Risk analysis of enterprise or organisation activities
- G06Q 10/0639: Performance analysis of employees; Performance analysis of enterprise or organisation operations
- G06Q: INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR

## Abstract

Systems and methods are disclosed for responding to a business disruption using hierarchically ordered response plans. In one implementation, a method for responding to a business disruption using hierarchically ordered response plans is provided. The method comprises storing the response plans which include at least two of a crisis management plan, a management summary plan, a department resilience plan, and a system resilience plan. The response plans also include escalation points. Further, the method comprises allowing a user to access, through an interface, information on the response plans and the escalation points during normal business operation. The method may also comprise maintaining the response plans using a business impact analysis.

## Claims

### Claim 1

A computer-implemented system for responding to a business disruption using hierarchically ordered response plans, the system comprising:
means for storing the response plans which include at least two of a crisis management plan, a management summary plan, a department resilience plan, and a system resilience plan, wherein the response plans comprise escalation points; and
an interface for allowing a user to access information on the response plans and the escalation points during normal business operation.

### Claim 2 (depends on 1)

The system of claim 1, wherein each plan comprises a plurality of activities for execution during the business disruption.

### Claim 3 (depends on 1)

The system of claim 1, wherein each plan is assigned to at least one member of an organization as a plan owner.

### Claim 4 (depends on 1)

The system of claim 1, further comprising means for maintaining the response plans using a business impact analysis.

### Claim 5 (depends on 4)

The system of claim 4, further comprising:
means for estimating a set of time values for a business unit, the set of time values indicating points of time when a business impact of the business unit will increase;
means for calculating a resilience impact rating of the business unit based on the estimated time values, wherein the resilience impact rating provides a metric for quantifying a time-criticality of the business unit;
means for setting an impact threshold at a specific resilience impact rating value; and
means identifying the business unit as time-critical business unit if the resilience impact rating is greater than or equal to the impact threshold.

### Claim 6 (depends on 1)

The system of claim 1, further comprising means for producing physical printouts containing the response plans for redundancy.

### Claim 7

A computer-readable medium comprising instructions for causing a processor to execute a method for responding to a business disruption using hierarchically ordered response plans, the method comprising:
storing the response plans which include at least two of a crisis management plan, a management summary plan, a department resilience plan, and a system resilience plan, wherein the response plans comprise escalation points; and
allowing a user to access, through an interface, information on the response plans and the escalation points during normal business operation.

### Claim 8 (depends on 7)

The computer-readable medium of claim 7, wherein each plan comprises a plurality of activities for execution during the business disruption.

### Claim 9 (depends on 7)

The computer-readable medium of claim 7, wherein the method further comprises assigning each plan to at least one member of an organization as a plan owner.

### Claim 10 (depends on 7)

The computer-readable medium of claim 7, wherein the method further comprises maintaining the response plans using a business impact analysis.

### Claim 11 (depends on 10)

The computer-readable medium of claim 10, wherein the method further comprises:
estimating a set of time values for a business unit, the set of time values indicating points of time when a business impact of the business unit will increase;
calculating a resilience impact rating of the business unit based on the estimated time values, wherein the resilience impact rating provides a metric for quantifying a time-criticality of the business unit;
setting an impact threshold at a specific resilience impact rating value; and
identifying the business unit as time-critical business unit if the resilience impact rating is greater than or equal to the impact threshold.

### Claim 12 (depends on 7)

The computer-readable medium of claim 7, wherein the method further comprises producing physical printouts containing the response plans for redundancy.

### Claim 13

A method for responding to a business disruption using hierarchically ordered response plans, the method comprising:
storing the response plans which include at least two of a crisis management plan, a management summary plan, a department resilience plan, and a system resilience plan, wherein the response plans comprise escalation points; and
allowing a user to access, through an interface, information on the response plans and the escalation points during normal business operation.

### Claim 14 (depends on 13)

The method of claim 13, wherein each plan comprises a plurality of activities for execution during the business disruption.

### Claim 15 (depends on 13)

The method of claim 13, wherein each plan is assigned to at least one member of an organization as a plan owner.

### Claim 16 (depends on 13)

The method of claim 13, further comprising maintaining the response plans using a business impact analysis.

### Claim 17 (depends on 16)

The method of claim 16, further comprising performing a business impact analysis that includes the following steps:
estimating a set of time values for a business unit, the set of time values indicating points of time when a business impact of the business unit will increase;
calculating a resilience impact rating of the business unit based on the estimated time values, wherein the resilience impact rating provides a metric for quantifying a time-criticality of the business unit;
setting an impact threshold at a specific resilience impact rating value; and
identifying the business unit as time-critical business unit if the resilience impact rating is greater than or equal to the impact threshold.

### Claim 18 (depends on 13)

The method of claim 13, further comprising producing physical printouts containing the response plans for redundancy.