Method and system for analyzing the risk of a project
AssigneeRaytheon Company (copy)
InventorThomas Angermeier
Life of this patent
Estimating the term…
Abstract
Analyzing risk includes receiving input parameters describing a project. Schedule values for a schedule variable are established. The following are repeated for each schedule value to calculate cost-probability relationships relating a cost value of a cost variable with a probability value of a probability variable: a schedule value is selected, and a cost-probability relationship at the selected schedule value is calculated. A cost-probability-schedule relationship relating a cost value, a probability value, and a schedule value is determined from the calculated cost-probability relationships.
Claims20
A method for analyzing risk, comprising:
- receiving input comprising a plurality of parameters, the plurality of parameters describing a project associated with a duration and a budget;
- establishing a plurality of schedule values for a schedule variable, the schedule variable representing the duration of the project;
- repeating the following for each schedule value of the plurality of schedule values to calculate a plurality of cost-probability relationships, the cost-probability relationship relating a cost value of a cost variable with a probability value of a probability variable, the cost variable representing the budget of the project, the probability variable representing the probability of meeting a given cost value at a given schedule value:
- selecting a schedule value of the plurality of schedule values;
- and
- calculating a cost-probability relationship at the selected schedule value;
- and
- determining a cost-probability-schedule relationship from the calculated cost-probability relationships, the cost-probability-schedule relationship relating a cost value, a probability value, and a schedule value.
A system for analyzing risk, comprising:
- a database operable to store input comprising a plurality of parameters, the plurality of parameters describing a project associated with a duration and a budget;
- and
- a server system coupled to the database, the server system comprising one or more modules operable to:
- establish a plurality of schedule values for a schedule variable, the schedule variable representing the duration of the project;
- repeat the following for each schedule value of the plurality of schedule values to calculate a plurality of cost-probability relationships, the cost-probability relationship relating a cost value of a cost variable with a probability value of a probability variable, the cost variable representing the budget of the project, the probability variable representing the probability of meeting a given cost value at a given schedule value:
- select a schedule value of the plurality of schedule values;
- and
- calculate a cost-probability relationship at the selected schedule value;
- and
- determine a cost-probability-schedule relationship from the calculated cost-probability relationships, the cost-probability-schedule relationship relating a cost value, a probability value, and a schedule value.
Logic for analyzing risk, the logic embodied in a medium and operable to:
- receive input comprising a plurality of parameters, the plurality of parameters describing a project associated with a duration and a budget;
- establish a plurality of schedule values for a schedule variable, the schedule variable representing the duration of the project;
- repeat the following for each schedule value of the plurality of schedule values to calculate a plurality of cost-probability relationships, the cost-probability relationship relating a cost value of a cost variable with a probability value of a probability variable, the cost variable representing the budget of the project, the probability variable representing the probability of meeting a given cost value at a given schedule value:
- select a schedule value of the plurality of schedule values;
- and
- calculate a cost-probability relationship at the selected schedule value;
- and
- determine a cost-probability-schedule relationship from the calculated cost-probability relationships, the cost-probability-schedule relationship relating a cost value, a probability value, and a schedule value.
A system for analyzing risk, comprising:
- means for receiving input comprising a plurality of parameters, the plurality of parameters describing a project associated with a duration and a budget;
- means for establishing a plurality of schedule values for a schedule variable, the schedule variable representing the duration of the project;
- means for repeating the following for each schedule value of the plurality of schedule values to calculate a plurality of cost-probability relationships, the cost-probability relationship relating a cost value of a cost variable with a probability value of a probability variable, the cost variable representing the budget of the project, the probability variable representing the probability of meeting a given cost value at a given schedule value:
- selecting a schedule value of the plurality of schedule values;
- and
- calculating a cost-probability relationship at the selected schedule value;
- and
- means for determining a cost-probability-schedule relationship from the calculated cost-probability relationships, the cost-probability-schedule relationship relating a cost value, a probability value, and a schedule value.
A method for analyzing risk, comprising:
- receiving input comprising a plurality of parameters, the plurality of parameters describing a project associated with a duration, a budget, and historical data;
- establishing a plurality of schedule values for a schedule variable, the schedule variable representing the duration of the project, the plurality of schedule values established by performing at least one of the following:
- a first procedure comprising:
- receiving a maximum cost value and a minimum cost value;
- estimating a maximum schedule value and a minimum schedule value from the maximum cost value and the minimum cost value;
- segmenting the difference between the maximum schedule value and the minimum schedule value into a plurality of increments;
- and
- establishing the schedule values in accordance with the increments;
- and
- a second procedure comprising:
- receiving a maximum schedule value and a minimum schedule value;
- segmenting the difference between the maximum schedule value and the minimum schedule value into a plurality of increments;
- and
- establishing the schedule values in accordance with the increments;
- repeating the following for each schedule value of the plurality of schedule values to calculate a plurality of cost-probability relationships, the cost-probability relationship relating a cost value of a cost variable with a probability value of a probability variable, the cost variable representing the budget of the project, the probability variable representing the probability of meeting a given cost value at a given schedule value:
- selecting a schedule value of the plurality of schedule values;
- and
- calculating a cost-probability relationship at the selected schedule value by:
- providing information to a cost model operable to estimate a cost value and a probability value at a given schedule value;
- and
- receiving a result comprising the cost-probability relationship at the given schedule value;
- determining a cost-probability-schedule relationship from the calculated cost-probability relationships, the cost-probability-schedule relationship relating a cost value, a probability value, and a schedule value;
- calculating a plurality of graph values representing the cost-probability-schedule relationship;
- generating a graph from the plurality of graph values;
- calculating a probability of overrun from the probability value, the probability of overrun representing the probability that the cost value will be exceeded;
- calculating an amount of overrun from the cost value and a second cost value, the second cost value representing a cost associated with an approximately one hundred percent probability;
- and
- determine a cost risk from the probability of overrun and the amount of overrun.