# US 2004/0210470 A1 · System and method for project management

> Agents: this data is available as JSON from the patentgrep API and MCP server — see https://patentgrep.com/llms.txt

- Number: US 2004/0210470 A1
- Document ID: US20040210470A1
- Status: Published application
- Kind: A1
- Application number: 10/414,941
- Filed: 2003-04-16
- Published: 2004-10-21
- Earliest claimed: 2003-04-16
- Inventors: John Rusk
- Web page: https://patentgrep.com/patent/US20040210470A1

## CPC

- G06Q 10/10: Office automation; Time management
- G06Q 10/063114: {Status monitoring or status determination for a person or group}
- G06Q: INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR

## Abstract

Systems and methods applicable, for example, in project management. Provided operations include, for instance, operations regarding projects, tasks, subtasks, questions, attachments, users, and/or the like.

## Claims

### Claim 1

A method for project management, comprising:
receiving from a first user an indication that a task has been completed, wherein said task has been assigned to said first user;
informing a second user of the indication that said task has been completed; and
receiving from said second user an indication regarding whether said task was satisfactorily completed.

### Claim 2 (depends on 1)

The method of claim 1, wherein said second user provides an indication regarding actions performed incorrectly by said first user with regard to said task.

### Claim 3 (depends on 1)

The method of claim 1, wherein said second user indicates a camera link.

### Claim 4 (depends on 3)

The method of claim 3, wherein said second user employs said camera link in providing feedback to said first user regarding actions performed incorrectly by said first user with regard to said task.

### Claim 5 (depends on 1)

The method of claim 1, wherein said second user indicates a question for association with said task.

### Claim 6 (depends on 1)

The method of claim 1, further comprising informing said first user that said task needs to be reconsidered.

### Claim 7 (depends on 1)

The method of claim 1, further comprising informing said second user that said task is considered to be pending complete.

### Claim 8 (depends on 1)

The method of claim 1, further comprising receiving from said second user an indication to designate said task as complete.

### Claim 9 (depends on 8)

The method of claim 8, further comprising terminating a display of said task to said first user.

### Claim 10

A method for project management, comprising:
assigning a task to a user;
receiving from said user an indication of one or more subtasks corresponding to said task;
receiving from said user an indication of one or more assignees for one or more of said subtasks; and
assigning one or more of said subtasks in accordance with said indication of one or more assignees.

### Claim 11 (depends on 10)

The method of claim 10, further comprising querying said user for data corresponding to one or more of said subtasks.

### Claim 12 (depends on 10)

The method of claim 10, wherein said user indicates one or more categories corresponding to one or more of said subtasks.

### Claim 13 (depends on 10)

The method of claim 10, wherein said user indicates privacy information corresponding to one or more of said subtasks.

### Claim 14 (depends on 10)

The method of claim 10, wherein said user indicates billing information corresponding to one or more of said subtasks.

### Claim 15 (depends on 10)

The method of claim 10, wherein said user indicates time estimate information corresponding to one or more of said subtasks.

### Claim 16 (depends on 10)

The method of claim 10, wherein said user indicates due date information corresponding to one or more of said subtasks.

### Claim 17 (depends on 10)

The method of claim 10, wherein said user indicates comments corresponding to one or more of said subtasks.

### Claim 18 (depends on 10)

The method of claim 10, wherein said user indicates one or more questions for association with one or more of said subtasks.

### Claim 19 (depends on 10)

The method of claim 10, wherein said user indicates one or more attachments for association with one or more of said subtasks.

### Claim 20 (depends on 10)

The method of claim 10, further comprising notifying one or more of said assignees of one or more of said subtasks.

### Claim 21 (depends on 11)

The method of claim 11, wherein said data is subject to one or more constraints.

### Claim 22 (depends on 21)

The method of claim 21, wherein said one or more constraints relate to said task.

### Claim 23

A system for project management, comprising:
a memory having program code stored therein; and
a processor disposed in communication with said memory for carrying out instructions in accordance with the stored program code;
wherein said program code, when executed by said processor, causes said processor to perform:
receiving from a first user an indication that a task has been completed, wherein said task has been assigned to said first user;
informing a second user of the indication that said task has been completed; and
receiving from said second user an indication regarding whether said task was satisfactorily completed.

### Claim 24 (depends on 23)

The system of claim 23, wherein said second user provides an indication regarding actions performed incorrectly by said first user with regard to said task.

### Claim 25 (depends on 23)

The system of claim 23, wherein said second user indicates a camera link.

### Claim 26 (depends on 25)

The system of claim 25, wherein said second user employs said camera link in providing feedback to said first user regarding actions performed incorrectly by said first user with regard to said task.

### Claim 27 (depends on 23)

The system of claim 23, wherein said second user indicates a question for association with said task.

### Claim 28 (depends on 23)

The system of claim 23, wherein said processor further performs informing said first user that said task needs to be reconsidered.

### Claim 29 (depends on 23)

The system of claim 23, wherein said processor further performs informing said second user that said task is considered to be pending complete.

### Claim 30 (depends on 23)

The system of claim 23, wherein said processor further performs receiving from said second user an indication to designate said task as complete.

### Claim 31 (depends on 30)

The system of claim 30, wherein said processor further performs terminating a display of said task to said first user.

### Claim 32

A system for project management, comprising:
a memory having program code stored therein; and
a processor disposed in communication with said memory for carrying out instructions in accordance with the stored program code;
wherein said program code, when executed by said processor, causes said processor to perform:
assigning a task to a user;
receiving from said user an indication of one or more subtasks corresponding to said task;
receiving from said user an indication of one or more assignees for one or more of said subtasks; and
assigning one or more of said subtasks in accordance with said indication of one or more assignees.

### Claim 33 (depends on 32)

The system of claim 32, wherein said processor further performs querying said user for data corresponding to one or more of said subtasks.

### Claim 34 (depends on 32)

The system of claim 32, wherein said user indicates one or more categories corresponding to one or more of said subtasks.

### Claim 35 (depends on 32)

The system of claim 32, wherein said user indicates privacy information corresponding to one or more of said subtasks.

### Claim 36 (depends on 32)

The system of claim 32, wherein said user indicates billing information corresponding to one or more of said subtasks.

### Claim 37 (depends on 32)

The system of claim 32, wherein said user indicates time estimate information corresponding to one or more of said subtasks.

### Claim 38 (depends on 32)

The system of claim 32, wherein said user indicates due date information corresponding to one or more of said subtasks.

### Claim 39 (depends on 32)

The system of claim 32, wherein said user indicates comments corresponding to one or more of said subtasks.

### Claim 40 (depends on 32)

The system of claim 32, wherein said user indicates one or more questions for association with one or more of said subtasks.

### Claim 41 (depends on 32)

The system of claim 32, wherein said user indicates one or more attachments for association with one or more of said subtasks.

### Claim 42 (depends on 32)

The system of claim 32, wherein said processor further performs notifying one or more of said assignees of one or more of said subtasks.

### Claim 43 (depends on 33)

The system of claim 33, wherein said data is subject to one or more constraints.

### Claim 44 (depends on 43)

The system of claim 43, wherein said one or more constraints relate to said task.