# US 2004/0083480 A1 · System and method for creating a pert chart

> Agents: this data is available as JSON from the patentgrep API and MCP server — see https://patentgrep.com/llms.txt

- Number: US 2004/0083480 A1
- Document ID: US20040083480A1
- Status: Published application
- Kind: A1
- Application number: 10/690,392
- Filed: 2003-10-20
- Published: 2004-04-29
- Earliest claimed: 2002-10-21
- Assignees: The Boeing Company
- Inventors: William C. Dodge
- Web page: https://patentgrep.com/patent/US20040083480A1

## CPC

- G06Q 10/06: Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
- G06Q: INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR

## Abstract

A method of creating a program management chart comprising the steps of displaying a plurality of tasks within a selected set of data as a first part of the program management chart; and displaying a task that is outside of the selected set of data but that is associated with at least one of the plurality of tasks within the selected set of data as a second part of the program management chart. A method of creating a program management chart comprising the steps of displaying a work breakdown structure tree associated with a project without accessing project data; selecting a subfolder within the work breakdown structure tree; and accessing task data associated with the selected subfolder within the work breakdown structure tree without accessing all of the project data.

## Claims

### Claim 1

A method of creating a program management chart comprising the steps of:
displaying a plurality of tasks within a selected set of data as a first part of the program management chart; and
displaying a task that is outside of the selected set of data but that is associated with at least one of the plurality of tasks within the selected set of data as a second part of the program management chart.

### Claim 2 (depends on 1)

The method of claim 1 further comprising the step of differentiating between the plurality of tasks within the selected set of data and the task that is outside of the selected set of data.

### Claim 3 (depends on 1)

The method of claim 1 wherein the task that is outside of the selected set of data is outside of a project that contains the selected set of data.

### Claim 4

A method of creating a program management chart comprising the steps of:
displaying a work breakdown structure tree associated with a project without accessing project data;
selecting a subfolder within the work breakdown structure tree; and
accessing task data associated with the selected subfolder within the work breakdown structure tree without accessing all of the project data.

### Claim 5 (depends on 4)

The method of claim 4 further comprising the step of displaying the program management chart associated with the subfolder within the work breakdown structure tree.

### Claim 6

A method of creating a program management chart comprising the steps of:
selecting one of a plurality of tasks within a program management chart;
determining which of the plurality of tasks within the program management chart are predecessor tasks of the selected one of the plurality of tasks;
determining which of the plurality of tasks within the program management chart are successor tasks of the selected one of the plurality of tasks; and
displaying the program management chart with only the selected one of the plurality of tasks and the predecessor tasks or the successor tasks of the selected one of the plurality of tasks.

### Claim 7 (depends on 6)

The method of claim 6 further comprising displaying only the predecessor tasks and the selected one of the plurality of tasks.

### Claim 8 (depends on 6)

The method of claim 6 further comprising displaying only the successor tasks and the selected one of the plurality of tasks.

### Claim 9

A method of creating a program management chart comprising the steps of:
selecting a task within a project, the task including a display data associated with the task;
accessing a database comprising task data associated with the selected task, the task data including the display data and non-display data; and
displaying the task data associated with the selected task.

### Claim 10 (depends on 9)

The method of claim 9 wherein the task data is displayed in a separate window from the task within the project.

### Claim 11

A method of creating a program management chart comprising the steps of:
displaying a plurality of tasks forming the program management chart;
displaying an interface for filtering the plurality of tasks;
selecting a parameter value using the interface for filtering the plurality of tasks;
displaying the program management chart with only those tasks having the parameter value.

### Claim 12

A method of creating a program management chart comprising the steps of:
accessing a subset of data within a project;
displaying a plurality of tasks associated with the subset of data; and
displaying a task that is outside of the subset of data.

### Claim 13 (depends on 12)

The method of claim 12 wherein the task that is outside of the subset of data is a task within the project.

### Claim 14 (depends on 12)

The method of claim 12 wherein the task that is outside of the subset of data is a task outside of the project.

### Claim 15 (depends on 12)

The method of claim 12 further comprising the step of accessing a header relating to the task that is outside of the subset of data.