# US 2003/0208580 A1 · Process duration control

> Agents: this data is available as JSON from the patentgrep API and MCP server — see https://patentgrep.com/llms.txt

- Number: US 2003/0208580 A1
- Document ID: US20030208580A1
- Status: Published application
- Kind: A1
- Application number: 10/136,483
- Filed: 2002-05-02
- Published: 2003-11-06
- Earliest claimed: 2002-05-02
- Assignees: Hewlett-Packard Development Company, L.P.
- Inventors: Joe K. Presley
- Web page: https://patentgrep.com/patent/US20030208580A1

## CPC

- G06F 9/4887: {involving deadlines, e.g. rate based, periodic}
- G06F 11/3409: {for performance assessment}
- G06F 2209/508: Monitor
- G06F: ELECTRIC DIGITAL DATA PROCESSING (computer systems based on specific computational models G06N)

## Abstract

A computer system incorporates means, and corresponding methods, for controlling access and usage of one or more processors in the computer system. The means may include hardware and software features. The means may operate according to specified steps according to a specific algorithm. In an embodiment, the system may include a discovery executable that discovers a target process for duration management. The system may further include a duration monitor that determines a percent completion of a target process. The percent completion information may be provided to a process duration controller that uses process information and the percent completion information to calculate a run-time metric. The run-time metric may then be provided to a process resource manager that controls resources consumed by the target process.

## Claims

### Claim 1

An apparatus that controls the duration of one or more processes executing in a computer system, comprising:
a discovery executable that discovers a target process to be managed, wherein process information is discovered;
a duration detector that receives data from the target process and determines percent complete information for the target process;
a process duration control module coupled to the discovery executable and the duration detector that receives the process information and the percent complete information and computes a run-time metric; and
a process resource manager that receives the run-time metric and adjusts computer resources available to the target process consistent with the run-time metric.

### Claim 2 (depends on 1)

The apparatus of claim 1, wherein the run-time metric comprises a ratio of a required run-time parameter to an actual run-time parameter.

### Claim 3 (depends on 2)

The apparatus of claim 2, wherein the required run-time parameter and the actual run-time parameter relate to a number of ticks per second of processor operation.

### Claim 4 (depends on 1)

The apparatus of claim 1, wherein the process information comprises process identification, process profile value, and process elapsed time.

### Claim 5 (depends on 4)

The apparatus of claim 4, wherein the process elapsed time is based on historical data related to execution of the target process.

### Claim 6 (depends on 5)

The apparatus of claim 5, wherein the historical data are updated following an execution of the target process.

### Claim 7 (depends on 1)

The apparatus of claim 1, wherein the process duration control module comprises a metrics calculator that receives the percent complete information from the target process, and wherein the metrics calculator updates the run-time metric.

### Claim 8 (depends on 1)

The apparatus of claim 1, wherein the process duration control module comprises a profile calculator that determines a profile value of the target process upon execution of the target process.

### Claim 9

An apparatus for controlling resources in a computer system, comprising:
means for identifying target processes for duration management;
means, coupled to the identifying means, for receiving process information for the identified target processes;
means, coupled to the receiving means, for monitoring process information from the target processes;
means, coupled to the monitoring means, for computing process run-time metrics; and
means, coupled to the computing means, for receiving the run-time metrics and for adjusting the resources based on the received run-time metrics.

### Claim 10 (depends on 9)

The apparatus of claim 9, wherein the run-time metrics comprise a ratio of a required process run-time and an actual process run-time.

### Claim 11 (depends on 10)

The apparatus of claim 10, wherein the required process run-time and the actual process run-time relate to processor ticks per second, and wherein the resources controlled in the computer system comprise central processor units.

### Claim 12

A method for controlling resources in a computer system, comprises:
discovering a target process executing on the computer system, including determining target process information;
monitoring completion of the target process, wherein percent completion information for the target process is determined;
providing the percent completion information and the target process information to a process duration controller;
computing a run-time metric based on the received information;
providing the run-time metric to a resource manager; and
adjusting allocation of the resources in the computer system consistent with the run-time metric.

### Claim 13 (depends on 12)

The method of claim 12, wherein computing the run-time metric comprises:
measuring an actual run time parameter; and
determining a ratio of a required run-time parameter to the actual run-time parameter.

### Claim 14 (depends on 13)

The method of claim 13, wherein the required run-time parameter and the actual run-time parameter relate to a number of ticks per second of processor operation.

### Claim 15 (depends on 12)

The method of claim 12, wherein the process information comprises process identification, process profile value, and process elapsed time.

### Claim 16 (depends on 15)

The method of claim 15, further comprising:
measuring actual elapsed time for one or more executions of the target processes in the computer system; and
storing the measured actual process elapsed time as historical data, wherein the process elapsed time is based on historical data related to execution of the target process.

### Claim 17 (depends on 16)

The method of claim 16, further comprising updating the historical data updated following an execution of the target process.

### Claim 18 (depends on 12)

The method of claim 12, further comprising determining a profile value of the target process upon execution of the target process.

### Claim 19 (depends on 18)

The method of claim 18, further comprising storing the profile value of the target process.

### Claim 20

A method for allocating resources in a computer system, comprising:
discovering one or more target processes executing on the computer system;
determining a run-time metric for each of the discovered target processes; and
adjusting allocation of the resources based on the run time metric determined for each of the discovered target processes.