# US 2002/0159844 A1 · Corner connection for temporary shoring

> Agents: this data is available as JSON from the patentgrep API and MCP server — see https://patentgrep.com/llms.txt

- Number: US 2002/0159844 A1
- Document ID: US20020159844A1
- Status: Published application
- Kind: A1
- Application number: 10/166,635
- Filed: 2002-06-12
- Published: 2002-10-31
- Earliest claimed: 2000-05-11
- Inventors: John H. Meyer
- Web page: https://patentgrep.com/patent/US20020159844A1

## CPC

- E02D 17/083: {Shoring struts}
- E02D 17/04: Bordering {surfacing} or stiffening the sides of foundation pits
- E02D: FOUNDATIONS; EXCAVATIONS; EMBANKMENTS (specially adapted for hydraulic engineering E02B); UNDERGROUND OR UNDERWATER STRUCTURES {(tunnels, tunnelling, mining E21)}

## Abstract

A connection arrangement for temporary shoring in an excavation site is used to secure I-beams together at corners within the excavation site. Typically, four I-beams are connected together to form a rectangular frame that is suspended within the excavation for bracing the shoring walls thereof. However, any polygonal shape may be used. The connection arrangement includes mating socket or connecting members which are placed over the ends of I-beams to be fastened together. One of the connecting members includes an outwardly extended tab while the other includes a pair of outwardly extended tabs. The first outwardly extending tab fits between the two extending tabs of the corresponding connecting member. All of the tabs are provided with apertures which are placed in alignment when the connection is made so that a bolt or pin can be passed through the apertures to secure adjacent connecting members together. Each connecting member also includes a large eyelet for receiving a chain or other elongated supporting member which is typically used to suspend the resulting I-beam frame at a desired height within the shoring wall. Alternative embodiments provide for a secondary bar attached to the connectors to provide additional support. Also numerous beam/connector arrangements may be provided at different heights within a single excavation site. Such an arrangements provide much greater support for the side walls of the excavation site.

## Claims

### Claim 1

In a temporary shoring arrangement including upstanding wall portions positioned within an excavation site and braced by a plurality of shoring beams, a corner connection comprising:
a first shoring beam connector including a hollow main body portion formed along a first longitudinal axis and an opening situated at one longitudinal end of said main body portion, wherein said main body portion is adapted to slidably receive, through said opening, a respective end portion one of said plurality of shoring beams;
an abutment for limiting sliding movement of said respective one of said plurality of shoring beams; and
a tab extending laterally from said main body portion, said tab having an aperture located therein adapted to receive a connecting pin.

### Claim 2 (depends on 1)

The corner connection according to claim 1 wherein said abutment constitutes an end wall of said main body portion, with said end wall being longitudinally spaced from said opening.

### Claim 3 (depends on 1)

The corner connection according to claim 1 further comprising:
a second shoring beam connector including a hollow main body portion formed along a second longitudinal axis and an opening situated at one longitudinal end of said main body portion, wherein said main body portion is adapted to slidably receives through said opening, a respective end portion of one of said plurality of shoring beams;
an abutment for limiting sliding movement of said respective beam within said main body portion; and;
a first tab extending laterally from said main body portion, said tab having an aperture located therein adapted to be aligned with the aperture in the tab of the first corner to receive the connecting pin.

### Claim 4 (depends on 1)

The corner connection according to claim 1 wherein said main body portion has opposed top and bottom rectangular panels and opposed rectangular side panels which are attached together to form said main body.

### Claim 5 (depends on 1)

The corner connection according to claim 1 further comprising: an eyelet provided on said main body portion.

### Claim 6 (depends on 1)

The corner connection according to claim 1 further comprising: a gusset provided between said main body portion and said tab.

### Claim 7 (depends on 3)

The corner connection according to claim 3, wherein said second connector further comprises a second tab extending laterally from said main body portion, said second tab having an aperture located therein adapted to receive the connecting pin.

### Claim 8 (depends on 3)

The corner connection according to claim 3 further comprising a connecting pin extending through both the aperture in the tab of the first connector and the aperture in the first tab of the second connector.

### Claim 9 (depends on 7)

The corner connection according to claim 7 further comprising a connecting pin extending through the aperture of the tab of the first connector, the aperture of the first tab of the second connector and the aperture of the second tab of the second connector.

### Claim 10

A corner connection for connecting shoring beams of a temporary shoring arrangement, said corner connection comprising:
a first shoring beam connector including a hollow main body portion formed along a first longitudinal axis at one longitudinal end of said main body portion, wherein said main body portion is adapted to slidably receive, through said end portion of said shoring beams;
an abutment for limiting sliding movement of said respective beams within said main body, and
and a tab extending laterally from said main body portion, said tab having an aperture located therein adapted to receive a connecting pin.

### Claim 11 (depends on 10)

The corner connection according to claim 10 wherein said abutment constitutes an end wall of said main body portion, with said end wall being longitudinally spaced from said opening.

### Claim 12 (depends on 10)

The corner connection according to claim 10 further comprising:
a second shoring beam connector including a hollow main body port on formed along a second longitudinal axis and an opening situated at one longitudinal end of said main body portion, wherein said main body portion is adapted to slidably receive, through said opening, an end portion of a respective one of said shoring beams,
an abutment for limiting sliding movement of said respective beam within said main body; and
a first tab extending laterally from said main body portion, said tab having an aperture located therein adapted to receive the connecting pin.

### Claim 13 (depends on 10)

The corner connection according to claim 10, wherein said main body portion has opposed top and bottom rectangular panels and opposed rectangular side panels which are attached together to form said main body.

### Claim 14 (depends on 10)

The corner connection according to claim 10 further comprising an eyelet providing on said main body portion.

### Claim 15 (depends on 10)

The corner connection according to claim 10 further comprising: a gusset provided between said main body portion and said tab.

### Claim 16 (depends on 12)

The corner connection according to claim 12 wherein said second connector further comprises a second tab extending laterally from said main body portion, said second tab having an aperture located therein adapted to receive the connecting pin.

### Claim 17 (depends on 12)

The corner connection according to claim 12 further comprising a connecting pin extending through both the aperture in the tab of the first connector and the aperture in the first tab of the second connector.

### Claim 18 (depends on 17)

The corner connection according to claim 17 further comprising a connecting pin extending through both the aperture of the tab of the first connector, the aperture of the first tab of the second connector and the aperture of the second tab of the second connector.

### Claim 19

A method of providing temporary shoring at an excavation site having upstanding wall portions comprising the steps of:
A) assembling a plurality of shoring beams with a series of corner connectors by slidably positioning an end portion of a respective shoring beam within a hollow main body portion of corresponding corner connector;
B) limiting relative sliding between the shoring beam and the main body portion through an abutment;
C) interconnecting adjacent corner connectors to arrange the plurality of shoring beams in a polygonal pattern, with the plurality of shoring beams and corner connectors being positioned against the upstanding wall portions so as to brace the upstanding wall portions so as to define the overall temporary shoring support assembly.

### Claim 20 (depends on 19)

The method according to claim 19, wherein adjacent corner connectors are interconnected by inserting a pin through aligned apertures formed in mating tabs.