# US 2002/0059477 A1 · Configuration of a control system for an electrical switchgear assembly

> Agents: this data is available as JSON from the patentgrep API and MCP server — see https://patentgrep.com/llms.txt

- Number: US 2002/0059477 A1
- Document ID: US20020059477A1
- Status: Published application
- Kind: A1
- Application number: 09/948,062
- Filed: 2001-09-07
- Published: 2002-05-16
- Earliest claimed: 2000-09-21
- Assignees: ABB Schweiz AG
- Inventors: Wolfgang Wimmer; Xiaobing Qiu
- Web page: https://patentgrep.com/patent/US20020059477A1

## CPC

- H02J 3/00: Circuit arrangements for AC mains or AC distribution networks
- H02J 13/181: the equipment comprising generators
- H02J 2103/30: Simulating, planning, modelling, reliability check or computer assisted design [CAD] of electric power networks
- Y02E 60/00: Enabling technologies; Technologies with a potential or indirect contribution to GHG emissions mitigation
- Y04S 10/16: Electric power substations
- Y04S 40/20: Information technology specific aspects, e.g. CAD, simulation, modelling, system security
- H02J: ELECTRIC POWER NETWORKS; CIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
- Y02E: REDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
- Y04S: SYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS

## Abstract

A method for configuration of a control system for an electrical switchgear assembly uses a primary device model for representation of primary devices, and a topology model of the switchgear assembly. In order to configure a first control system function, the first control system function is allocated to a primary device and to a field device, after which the primary device model and the topology model are used to automatically determine second control system functions which the first control system function requires during operation.

## Claims

### Claim 1

A method for configuration of a control system for an electrical switchgear assembly, which uses a field device model for representation of field devices, and a control function model for representation of control system functions of the switchgear assembly, characterized in that the method uses a primary device model for representation of primary devices in the switchgear assembly, and a topology model of the switchgear assembly, and comprises the following steps:
a) association of a first control system function with a primary device by means of the primary device model,
b) association of the first control system function with a field device by means of the field device model,
c) automatic determination of second control system functions, which the first control system function requires during operation of the assembly, on the basis of the topology model.

### Claim 2 (depends on 1)

The method as claimed in claim 1, characterized in that the method uses a communication model for representation of communication means, and, as a further step comprises:
d) automatic determination of communication links between the first control system function and the second control system functions on the basis of the communication model.

### Claim 3 (depends on 1)

The method as claimed in claim 1, characterized in that a control system function is allocated a software agent for configuration of the control system function, which determines a representation of information, which information the control system function requires, and which carries out the automatic determination of the second control system functions.

### Claim 4 (depends on 1)

The method as claimed in claim 1, characterized in that the method is carried out when the switchgear assembly is in an off-line engineering phase, and, when the method is being carried out, configuration parameters are determined for control system functions and communication units and can be loaded into the corresponding control system functions or communication units, respectively.

### Claim 5 (depends on 1)

The method as claimed in claim 1, characterized in that the method is carried out when the switchgear assembly is in an on-line configuration phase, and, when the method is being carried out, configuration parameters of control system functions and communication units are determined and are loaded into the corresponding control system functions or communication units, respectively.

### Claim 6 (depends on 1)

The method as claimed in claim 1, characterized in that configuration parameters for a control system function are determined on the basis of data from the primary device model and/or from the topology model.

### Claim 7

A computer program product having a stored program code which, during operation on a data processing unit, carries out a method for configuration of a control system for an electrical switchgear assembly, which method uses a field device model for representation of field devices, and a control function model for representation of control system functions of the switchgear assembly, characterized in that the method uses a primary device model for representation of primary devices in the switchgear assembly, and a topology model of the switchgear assembly, and comprises the following steps:
a) association of a first control system function with a primary device by means of the primary device model,
b) association of the first control system function with a field device by means of the field device model,
c) automatic determination of second control system functions, which the first control system function requires during operation of the assembly, on the basis of the topology model.

### Claim 8 (depends on 7)

The computer program product as claimed in claim 7, characterized in that the method which is carried out uses a communication model for representation of communication means and, as a further step, comprises:
d) automatic determination of communication links between the first control system function and the second control system functions on the basis of the communication model.