# US 2001/0032454 A1 · Combined cycle power generation plant

> Agents: this data is available as JSON from the patentgrep API and MCP server — see https://patentgrep.com/llms.txt

- Number: US 2001/0032454 A1
- Document ID: US20010032454A1
- Status: Published application
- Kind: A1
- Application number: 09/381,952
- Filed: 1999-09-28
- Published: 2001-10-25
- Earliest claimed: 1996-07-30
- Assignees: Mitsubishi Heavy Industries, Ltd.
- Inventors: JUN YASURAOKA; KOUZO TOYAMA
- Web page: https://patentgrep.com/patent/US20010032454A1

## CPC

- F02C 6/18: using the waste heat of gas-turbine plants outside the plants themselves, e.g. gas-turbine power heat plants (using waste heat as source of energy for refrigeration plants F25B27/02; using the waste heat of a gasturbine for steam generation or in a steam cycle see F01K23/10)
- F02C: GAS-TURBINE PLANTS; AIR INTAKES FOR JET-PROPULSION PLANTS; CONTROLLING FUEL SUPPLY IN AIR-BREATHING JET-PROPULSION PLANTS (construction of turbines F01D; jet-propulsion plants F02K; construction of compressors or fans F04; generating combustion products of high pressure or high velocity F23R; using gas turbines in compression refrigeration plants F25B11/00)

## Abstract

A means detecting the flow of the steam at the gateway of the steam cooling system is provided, and the timing of the finish of the warm-up process of the steam cooling system at start-up is decided by the difference of the flow of the steam at the gateway. In case of the difference between the flow of the steam at the inlet and the flow of the steam at the outlet, of the steam cooling system, is below a permitted value, it is considered that residual air and drainage are not remained between the inlet and the outlet and the warming-up is finished, and running to the step for starting the gas turbine can be performed.

## Claims

### Claim 1

A combined cycle power plant composed of a gas turbine plant and a steam turbine plant, comprising;
an exhaust heat recovery boiler for generating steam driving said steam turbine by using the exhaust heat from said gas turbine, and a steam cooling system for cooling high temperature cooled parts of said gas turbine by steam;
wherein super heated steam from said steam cooling system is returned to said steam turbine, and
a means detecting the flow of the steam at the gateway of said steam cooling system is provided, and the timing of the finish of the warm-up process of said steam cooling system at start-up is detected by the difference of the flow of said steam at said gateway.

### Claim 2

A combined cycle power plant composed of a gas turbine plant and a steam turbine plant, comprising;
an exhaust heat recovery boiler for generating steam driving said steam turbine by using the exhaust heat from said gas turbine, and
a steam cooling system for cooling high temperature cooled parts of said gas turbine by steam;
wherein super heated steam from said steam cooling system is returned to said steam turbine, and
a means detecting the temperature of the steam at the outlet of said steam cooling system is provided, and the timing of the finish of the warm-up process of said steam cooling system at start-up is decided by the detected temperature of said steam at said outlet.