# US 2001/0023665 A1 · Steam generator and process for assembling it

> Agents: this data is available as JSON from the patentgrep API and MCP server — see https://patentgrep.com/llms.txt

- Number: US 2001/0023665 A1
- Document ID: US20010023665A1
- Status: Published application
- Kind: A1
- Application number: 09/815,736
- Filed: 2001-03-23
- Published: 2001-09-27
- Earliest claimed: 2000-03-24
- Assignees: Alstom (Switzerland) Ltd
- Inventors: Jurgen Heidrich
- Web page: https://patentgrep.com/patent/US20010023665A1

## CPC

- F22B 37/244: {for water-tube steam generators suspended from the top}
- Y10T 29/4935: Heat exchanger or boiler making
- Y10T 29/49387: Boiler making
- F22B: METHODS OF STEAM GENERATION; STEAM BOILERS
- Y10T: TECHNICAL SUBJECTS COVERED BY FORMER US CLASSIFICATION

## Abstract

During the assembly of a steam generator, the boiler columns are assembled, and, in parallel, headers and other wall boxes are assembled on booms of the boiler columns, so that when the boiler columns are completed, the headers and wall boxes are also finally assembled. Next, the peripheral roof section is assembled onto the boiler columns, and the vertical steam generator-containing walls are suspended from the peripheral roof section. Parallel to this, the inner roof section is constructed and the convection heating surfaces are successively mounted to the inner roof section and lifted upward from the base. The assembled inner roof section and convection heating surfaces are then lifted to the height of the peripheral roof section, and the two parts of the roof are connected. Finally, the furnace walls having a vertical or inclined tube arrangement, including the furnace hopper, are assembled.

## Claims

### Claim 1

Process for assembling steam generators having a vertically extending boiler structural steelwork, a roof having an inner roof section and an outer roof section, boiler walls, and interior components, the process comprising the steps of:
constructing portions of the boiler wall at a first area of the installation site and constructing the interior components at a second area of the installation site that is different from the first area:
positioning the interior components between the portions of the boiler wall; and
fastening the interior components in position between the boiler walls.

### Claim 2 (depends on 1)

Process according to claim 1, wherein the portions of the boiler wall and the interior components are constructed simultaneously and the portions of the boiler wall and the interior components are constructed while they are suspended.

### Claim 3 (depends on 1)

Process according to claim 1, wherein the portions of the boiler wall are installed into an upper part of the boiler structural steelwork and the interior components are constructed in a lower part of the boiler structural steelwork.

### Claim 4 (depends on 3)

Process according to claim 3, wherein the steam generator also has a temporary cable hoisting system and the final assembly of the interior components includes raising the interior components between the boiler walls into an assembly position and fastening the interior components in the assembly position.

### Claim 5 (depends on 1)

Process according to claim 1, further comprising the steps of:
erecting the boiler structural steelwork and at least one outer section of the roof of the boiler structural steelwork; and
arranging a cable hoisting system on the outer section of the roof;
before the portions of the boiler wall and the interior components are assembled.

### Claim 6 (depends on 5)

Process according to claim 5, further comprising the step of erecting buckstays and wall boxes for the boiler walls as the boiler structural steelwork is erected or immediately after the boiler structural steel work is erected.

### Claim 7 (depends on 6)

Process according to claim 6, further comprising the steps of:
preassembling the buckstays and wall boxes; and
transporting the preassembled buckstays and wall boxes to their place of installation or to a temporary installation place on the boiler structural steelwork.

### Claim 8 (depends on 1)

Process according to claim 1, further comprising the steps of:
assembling the interior components under the inner section of the roof of the boiler structural steelwork;
suspending the interior components from the inner section of the roof; and
raising the inner section of the roof and the suspended interior components stepwise according to the building progress.

### Claim 9 (depends on 8)

Process according to claim 8 further comprising the step of connecting the inner and outer sections of the roof of the boiler structural steelwork after the interior components are raised into the assembly position.

### Claim 10 (depends on 1)

Process according to claim 1, wherein the step of constructing portions of the boiler wall includes the sub-steps of:
assembling the portions by registers,
inserting the portions from above,
suspending the portions into the boiler structural steelwork,
aligning the portions, and
welding the portions.

### Claim 11

A steam generator comprising:
a boiler structural steelwork;
a plurality of boiler walls mounted on the boiler structural steelwork, the boiler walls being furnace walls and defining a flue gas pass;
a roof supported on the boiler structural steelwork, the roof being divided into an outer roof section and an inner roof section, the inner roof section being longitudinally moveable through the flue gas pass during assembly and being connected in an assembled state with the outer roof section; and
a plurality of interior components disposed in the flue gas pass and suspended from the boiler structural steelwork roof.

### Claim 12 (depends on 11)

Steam generator according to claim 11, wherein the boiler walls are suspended from the outer roof section of the boiler structural steelwork roof.

### Claim 13 (depends on 11)

Steam generator according to claim 11, wherein the interior components are suspended from the inner roof section.

### Claim 14 (depends on 11)

Steam generator according to claim 11, wherein the interior components include heat recovery sections.

### Claim 15 (depends on 11)

Steam generator according to claim 11, further including a boiler top casing mounted to the inner roof section and a plurality of sling tubes, the interior components being suspended from the inner roof section by the sling tubes.

### Claim 16 (depends on 11)

Steam generator according to claim 11, further including a hoisting system mounted to the boiler structural steelwork, the hoisting system being adapted for raising the inner roof section in a stepwise manner during assembly.

### Claim 17 (depends on 16)

Steam generator according to claim 16, wherein the hoisting system is adapted for raising the inner roof section through the flue gas pass up to a height at which the inner roof section can be fastened to the outer roof section.