The present invention relates to a method for manufacturing and assembling a plurality of towers (1) on a wind farm (2), wherein said towers (1) comprise a plurality of precast concrete segments (3) superimposed in height, wherein the method comprises: a) establishing a centralised manufacturing point (6) on the wind farm (2); and b) establishing a plurality of land routes (8) to the definitive location (5) of the towers (1). Advantageously, the method further comprises: c) prefabricating at least one segment (3) of a tower (1); d) positioning the prefabricated segment (2) in a vertical position on a land transport system (9); e) transporting the segment (3) in a vertical position to the definitive location (5) of one of the towers (1), following one of the land routes (8); and f) assembling the segment (3), forming at least one portion of a shaft (4) of a tower (1).
A method for manufacturing and assembling a plurality of towers on a wind farm, wherein each of said towers comprises a plurality of precast concrete segments superimposed in height, forming a shaft of a tower, and wherein each tower occupies, after its assembly, a definitive location on the wind farm;
Dependencies are inferred from the claim text.