A smart load control system for use in a power distribution system including an electric grid, an aggregator, an electric vehicle (EV) coupled to a bidirectional EV charger and a smart inverter structured to convert direct current output of the EV into bidirectional alternating current, and a plurality of loads, the electric grid structured to supply power to the loads during a grid-connected mode, the EV structured to supply power to the loads during an islanded mode, the smart load control system comprising:
- a plurality of smart circuit breakers (SCBs) including an islanding and grid-connecting device (IGD) coupled to the electric grid, an EV SCB coupled to the bidirectional EV charger, and load SCBs coupled to respective loads, each SCB having a sensor and a controller, the IGD being structured to sense grid voltage and switch ON and OFF the electric grid, the EV smart circuit breaker being structured to sense EV voltage and switch ON and OFF the bidirectional EV charger;
- and
- a building energy system manager communicatively coupled to the plurality of SCBs and the aggregator, the building energy system manager being structured to collect data from each SCB, the data including at least the grid voltage and the EV voltage, select one of the grid-connected mode or the islanded mode based on the grid voltage and the EV voltage, perform a safe transition to the selected mode, and monitor the grid voltage and the EV voltage,
- wherein the building energy system manager is structured to select the grid-connected mode based on a determination that the grid voltage has remained a predetermined voltage for a predefined period, and wherein for performing a safe transition to the selected mode, the building energy system manager is further structured to:
- transmit a first signal to the bidirectional EV charger, the first signal indicating that the electric grid is available for reconnection;
- open all of the SCBs;
- close the EV SCB and transmit a second signal to the bidirectional EV charger, the second signal informing that the electric grid is ready for reconnection and commanding the EV to stop providing power to the loads;
- open the EV SCB and verify that the EV voltage has remained zero for the predefined period;
- close the IGD and reconnect the smart load control system to the electric grid;
- and
- provide power to the loads from the electric grid.