Method for charging raw materials into blast furnace
AssigneeJfe Steel Corporation
InventorsKazuhira Ichikawa, Yasushi Ogasawara, Takeshi Sato
Life of this patent
Estimating the term…
Loading patent…
AssigneeJfe Steel Corporation
InventorsKazuhira Ichikawa, Yasushi Ogasawara, Takeshi Sato
Estimating the term…
A method for charging raw materials into a blast furnace is provided. The blast furnace includes a bell-less charging device that includes a plurality of main hoppers and an auxiliary hopper. The auxiliary hopper has a smaller capacity than the main hoppers. The method includes discharging ore charged in at least one of the plurality of main hoppers and then sequentially charging the ore from a furnace center side toward a furnace wall side by using a rotating chute. After charging of the ore is started, only the ore is charged from the rotating chute at least until charging of 15 mass % of the ore is completed based on a total amount of the ore to be charged per batch; then discharging of small-size coke charged in the auxiliary hopper is started; and then, the small-size coke is charged together with the ore from the rotating chute.
A method for charging raw materials into a blast furnace, the blast furnace including a bell-less charging device that includes a plurality of main hoppers and an auxiliary hopper at a furnace top portion, the auxiliary hopper having a smaller capacity than the main hoppers,
A method for charging raw materials into a blast furnace, the blast furnace including a bell-less charging device that includes a plurality of main hoppers and an auxiliary hopper at a furnace top portion, the auxiliary hopper having a smaller capacity than the main hoppers,