# US 11,118,453 B2 · System and method of layering material

> Agents: this data is available as JSON from the patentgrep API and MCP server — see https://patentgrep.com/llms.txt

- Number: US 11,118,453 B2
- Document ID: US11118453B2
- Status: Granted
- Kind: B2
- Application number: 15/980,831
- Filed: 2018-05-16
- Published: 2019-11-21
- Granted: 2021-09-14
- Earliest claimed: 2018-05-16
- Assignees: Caterpillar Inc.
- Applicants: Caterpillar Inc.
- Inventors: Mo Wei
- Web page: https://patentgrep.com/patent/US11118453B2

## CPC

- E21C 41/26: Methods of surface mining (machines for obtaining, or the removal of, materials in open-pit mines E21C47/00); Layouts therefor
- E02F 3/841: {Devices for controlling and guiding the whole machine, e.g. by feeler elements and reference lines placed exteriorly of the machine (construction of roads E01C19/008)}
- E02F 9/205: {Remotely operated machines, e.g. unmanned vehicles (E02F3/8866 takes precedence)}
- E02F 9/262: {with follow-up actions to control the work tool, e.g. controller}
- G05D 1/00: Control of position, course, altitude or attitude of land, water, air or space vehicles, e.g. using automatic pilots (drive control systems specially adapted for autonomous road vehicles B60W60/00)
- G05D 1/0278: {using satellite positioning signals, e.g. GPS}
- E21C: MINING OR QUARRYING
- E02F: DREDGING; SOIL-SHIFTING (winning peat E21C49/00)
- G05D: SYSTEMS FOR CONTROLLING OR REGULATING NON-ELECTRIC VARIABLES

## Abstract

A system for moving material from a first work area to a second work includes a material moving machine, a machine position sensor and a controller system. The controller system performs first material moving operations including determining a premature termination of a material stacking operation. The controller system performs additional material moving operations including instructing a material moving machine in response to the premature termination of a material stacking operation.

## Claims

### Claim 1

A computer-implemented method of responding to a premature direction reversal of a material moving machine, the computer-implemented method comprising:
monitoring, by a control system, a location of the material moving machine while the material moving machine is moving a material to form a fill layer of the material within a fill layer zone;
calculating a target reverse point indicative of a target material pile location as adjacent to a location of a previously placed material pile within the fill layer zone using a previous reverse point of the material moving machine for the previously placed material pile within the fill layer zone and a size of an average material pile;
determining, by the control system, a premature direction reversal of the material moving machine at a premature direction reversal location based at least partially on a deviation distance between the location of the material moving machine and the target material pile location, wherein the premature direction reversal is indicative of leaving a pile of material as an improperly placed material pile;
identifying a position of the improperly placed material pile based on the premature direction reversal location;
storing, by the control system, the position of the improperly placed material pile;
controlling, by the control system, the material moving machine to align the material moving machine with the improperly placed material pile; and
controlling, by the control system, the material moving machine to re-engage and move, using an implement of the material moving machine, the improperly placed material pile to the target material pile location within the fill layer zone.

### Claim 2 (depends on 1)

The computer-implemented method of claim 1, wherein the deviation distance between the location of the material moving machine and the target material pile location is compared by the control system to a predefined distance threshold to determine the premature direction reversal location of the material moving machine.

### Claim 3 (depends on 1)

The computer-implemented method of claim 1, wherein the material moving machine is a dozer and the control system provides instructions to the dozer to lower a blade at the position of the improperly placed material pile to re-engage the improperly placed material pile.

### Claim 4 (depends on 1)

The computer-implemented method of claim 1, further comprising:
calculating, by the control system, a pile detection zone within the fill layer zone having a leading-edge location and a farthest most reverse location;
monitoring outputs of material moving machine sensors with the control system when the material moving machine is located within the pile detection zone; and
controlling, by the control system, the material moving machine to reverse its direction when the control system calculates that a predetermined threshold load level on the implement of the material moving machine has been exceeded based on the outputs of the material moving machine sensors.

### Claim 5 (depends on 4)

The computer-implemented method of claim 4, wherein determining the premature direction reversal location of the material moving machine is based at least partially on the deviation distance being greater than zero between the location of the material moving machine and the leading-edge location of the pile detection zone.

### Claim 6 (depends on 1)

The computer-implemented method of claim 1, further comprising setting, by the control system, an immature pile location data flag indicating that the premature direction reversal location of the material moving machine was determined by the control system.

### Claim 7 (depends on 1)

The computer-implemented method of claim 1, wherein controlling the material moving machine, by the control system, to align the material moving machine with the improperly placed material pile comprises:
instructing the material moving machine to move to a first location apart from the position of the improperly placed material pile; and
instructing the material moving machine to move from the first location to the position of the improperly placed material pile
instructing the material moving machine to activate the implement of the material moving machine to re-engage the improperly placed material pile.

### Claim 8 (depends on 1)

The computer-implemented method of claim 1, wherein the control system comprises a first controller located with the material moving machine and a second controller located remote from the material moving machine.

### Claim 9

A control system for responding to an incomplete material pile during a material layering operation by a material moving machine, the control system comprising:
a memory configured to retrievably store one or more algorithms; and
a controller in communication with the memory, the controller, based on the one or more algorithms, configured to:
calculate a target reverse point indicative of a target material pile location as adjacent to a location of a previously placed material pile within a fill layer zone using a previous reverse point of the material moving machine for the previously placed material pile within the fill layer zone and a size of an average material pile, the material moving machine moving material to form a fill layer within the fill layer zone;
identify a premature direction reversal of the material moving machine at a premature direction reversal location leaving a pile of the material as the incomplete material pile, the premature direction reversal identified based at least partially on a material moving machine position and the target material pile location;
instruct the material moving machine to align with the premature direction reversal location, and
instruct the material moving machine to engage an implement to restart a material movement procedure at the premature direction reversal location to move material of the incomplete material pile to the target material pile location within the fill layer zone.

### Claim 10 (depends on 9)

The control system of claim 9, wherein the controller is configured to calculate a deviation distance between the material moving machine position and the target material pile location relative to a predefined distance threshold stored in the memory in identifying the premature direction reversal.

### Claim 11 (depends on 9)

The control system of claim 9, wherein the controller is configured to set a data flag in response to detecting the premature direction reversal and to store the premature direction reversal location.

### Claim 12 (depends on 9)

The control system of claim 9, wherein the controller is configured to define a farthest location and a nearest location with respect to the target reverse point for the target material pile location based at least partially on the location of the previously placed material pile.

### Claim 13 (depends on 9)

The control system of claim 9, wherein the controller comprises a first controller located with the material moving machine and a second controller located remote from the material moving machine.

### Claim 14

An autonomous method of mining using a dozer comprising a drive mechanism to move the dozer in forward and reverse directions, an adjustable blade for pushing material when the dozer moves in the forward direction, and a location position sensor to determine a position of the dozer, the method comprising:
monitoring the location of the dozer while the dozer is moving material using the adjustable blade to form a fill layer within a fill layer zone;
calculating a target reverse point for the dozer using a previous reverse point of the dozer for a previously placed material pile within the fill layer zone and a size of an average material pile;
calculating a target material pile location zone that includes the target reverse point within the fill layer zone for the dozer to push the material, the target material pile location zone adjacent a location of the previously placed material pile within the fill layer zone and the target material pile location zone including a beginning location and farthest location with respect to the target reverse point for the dozer;
providing instructions to the drive mechanism and the adjustable blade of the dozer to move the dozer toward the target material pile location zone while pushing the material;
comparing the location of the dozer to the target material pile location zone;
storing the location of the dozer when it reverses direction from the forward direction to the reverse direction when the dozer reverses direction before the dozer entered the target material pile location zone while pushing the material, thereby forming an improperly placed material pile; and
providing instructions to the drive mechanism and the adjustable blade of the dozer to move the dozer to the improperly placed material pile and adjust the blade to push the improperly placed material pile into the target material pile location zone within the fill layer zone.

### Claim 15 (depends on 14)

The method of claim 14, wherein calculating the target material pile location zone comprises:
retrieving from a memory the location of the previously placed material pile in the fill layer zone;
calculating the farthest location based upon the retrieved location; and
calculating the beginning location based upon a predetermined distance from the farthest location.

### Claim 16 (depends on 14)

The method of claim 14, further comprising:
monitoring outputs of sensors of the dozer while the dozer is located within the target material pile location zone;
calculating a load on the dozer based upon the sensor outputs; and
providing instructions to the dozer to reverse direction from the forward direction to the reverse direction when the calculated load exceeds a predetermined threshold level.

### Claim 17 (depends on 16)

The method of claim 16, further comprising providing instructions to the dozer to reverse direction from the forward direction to the reverse direction when the dozer reaches the farthest location before the calculated load exceeds the predetermined threshold level.

### Claim 18 (depends on 14)

The method of claim 14, further comprising setting a machine-readable data flag when the dozer forms the improperly placed material pile.

### Claim 19 (depends on 14)

The method of claim 14, wherein providing the instructions to the drive mechanism and the adjustable blade of the dozer to move the dozer to the improperly placed material pile comprises:
providing first instructions to the dozer to move the dozer to a first location a predetermined distance from the location of the improperly placed material pile;
providing second instructions to the dozer to move the dozer from the first location to the location of the improperly placed material pile; and
providing third instructions to the dozer to lower the adjustable blade prior to the dozer reaching the location of the improperly placed material pile.

### Claim 20 (depends on 14)