# US 11,117,754 B2 · Method and apparatus used to handle non-upright articles of an article stream under prevention of disturbances

> Agents: this data is available as JSON from the patentgrep API and MCP server — see https://patentgrep.com/llms.txt

- Number: US 11,117,754 B2
- Document ID: US11117754B2
- Status: Granted
- Kind: B2
- Application number: 16/620,038
- Filed: 2018-06-12
- Published: 2020-03-26
- Granted: 2021-09-14
- Earliest claimed: 2017-06-13
- Assignees: Krones AG
- Applicants: Krones Aktiengesellschaft
- Inventors: Simon Berger; Richard Eschlbeck; Thomas Hensel; Herbert Spindler; Martin Bauer; Lucas Kiefer; Georg Goetz
- Web page: https://patentgrep.com/patent/US11117754B2

## CPC

- B65G 43/08: Control devices operated by article or material being fed, conveyed or discharged {(and controlling the discharging devices B65G47/42)}
- B65G 47/24: orientating the articles
- B65G 47/244: by turning them about an axis substantially perpendicular to the conveying plane
- B65G 47/256: removing incorrectly orientated articles
- B65G 47/914: {provided with drive systems incorporating rotary and rectilinear movements}
- B65G 47/31: by varying the relative speeds of the conveyors forming the series
- B65G 47/525: {using fluid jets}
- B65G 47/907: {with at least two picking-up heads}
- B65G 47/908: {with inflatable picking-up means (inflatable gripping members on load engaging elements for cranes B66C1/46)}
- B65G 2201/0235: Containers
- B65G 2201/0244: Bottles
- B65G 2203/0225: Orientation of the article
- B65G 2203/025: Speed of the article
- B65G 2203/0291: Speed of the load carrier
- B65G 2811/0626: Orientation of articles
- B65G 2811/0678: Determining the path to be followed
- B65G: TRANSPORT OR STORAGE DEVICES, e.g. CONVEYORS FOR LOADING OR TIPPING, SHOP CONVEYOR SYSTEMS OR PNEUMATIC TUBE CONVEYORS (packaging B65B; handling thin or filamentary materials, e.g. paper sheets or thread, B65H; cranes B66C; portable mobile or lifting or hauling appliances, e.g. hoists, B66D; devices for lifting or lowering goods for loading or unloading purposes, e.g. fork-lift trucks, B66F9/00; emptying bottles, jars, casks, barrels or similar containers, not otherwise provided for, B67C9/00; delivering or transferring liquids B67D; filling or discharging vessels for liquefied, solidified or compressed gases F17C; pipe-line systems for fluids F17D)

## Abstract

The invention includes a method (100) and an apparatus to handle irregularly conveyed and/or irregularly aligned and/or non-upright articles of an article stream under prevention of disturbances. The method (100) comprises the following steps: identifying at least one non-upright article in an article stream as an error; performing a correction step to resolve the error, the correction step comprising removal from the article stream of the at least one irregularly aligned article, or transfer to an upright orientation of the at least one irregularly aligned article, with a defined action being exerted temporally before and/or in temporal overlap with the correction step upon the at least one irregularly aligned article or upon regularly conveyed articles of the article stream.

## Claims

### Claim 1

A method (100) used to handle irregularly aligned beverage container (5) of an article stream (7) comprising:
identifying at least one irregularly aligned beverage container (5) in an article stream (7) as an error;
correcting to resolve the error, the correcting step comprising removing from the article stream (7) the at least one irregularly aligned beverage container (5) previously identified, or transferring to a regular orientation of the particular at least one irregularly aligned beverage container (5) previously identified; and
exerting a defined action temporally before or in temporal overlap with the correcting step upon the at least one irregularly aligned beverage container (5) previously identified or upon regularly conveyed at least one article (3) of the article stream (7),
wherein the exerting step comprises undoing or reducing an abutment or contact between the at least one irregularly aligned beverage container (5) and at least one regularly conveyed article (3) of the article stream (7) by guiding the article stream (7) with the at least one irregularly aligned articles over a plurality of horizontal conveying devices (8), and controlling the plurality of horizontal conveying devices (8) in a coordinated manner to undo or reduce the abutment or contact between the at least one irregularly aligned beverage container (5) and the at least one regularly conveyed article (3) of the article stream (7).

### Claim 2 (depends on 1)

The method of claim 1, comprising guiding the article stream (7) with the at least one irregularly aligned beverage container (5) over at least one horizontal conveying device (8) that is operated at reduced conveying speed or stopped temporally while performing the exerting step.

### Claim 3 (depends on 1)

The method of claim 1, wherein the exerting step further comprises rotating the at least one irregularly aligned beverage container (5) about an axis that is approximately perpendicular to the ground.

### Claim 4 (depends on 1)

The method of claim 1, wherein the exerting step further comprises inclining at least one regularly conveyed (3) of the article stream (7) in relation to the at least one irregularly aligned beverage container (5).

### Claim 5 (depends on 1)

The method of claim 1, wherein the exerting step further comprises dipping at least one separator element (22) between the at least one irregularly aligned beverage container (5) and at least one regularly conveyed article (3) of the article stream (7), wherein at least one regularly conveyed article (3) is immediately adjacent to the at least one irregularly aligned beverage container (5).

### Claim 6 (depends on 5)

The method of claim 5, wherein the exerting step comprises decelerating or accelerating the at least one regularly conveyed article (3) temporally after the dipping step.

### Claim 7 (depends on 1)

The method of claim 1, wherein the exerting step further comprises applying a vibration to the at least one irregularly aligned beverage container (5).

### Claim 8 (depends on 1)

The method of claim 1, wherein exerting step further comprises pushing the at least one irregularly aligned beverage container (5) in an upward direction by compressed air and thus removes the acted upon at least one irregularly aligned beverage container (5) from the article stream (7).

### Claim 9 (depends on 1)

The method of claim 1, wherein the exerting step further comprises forming at least one opening formed along a transport path for the article stream (7) through which opening the at least one irregularly aligned beverage container (5) falls and thus removes the at least one irregularly aligned beverage container (5) from the article stream (7).

### Claim 10

A method (100) used to handle irregularly aligned beverage container (5) of an article stream (7) comprising:
identifying at least one irregularly aligned beverage container (5) in an article stream (7) as an error;
correcting to resolve the error, the correcting step comprising removing from the article stream (7) the at least one irregularly aligned beverage container (5) previously identified, or transferring to a regular orientation of the particular at least one irregularly aligned beverage container (5) previously identified; and
exerting a defined action temporally before or in temporal overlap with the correcting step upon the at least one irregularly aligned beverage container (5) previously identified or upon regularly conveyed at least one article (3) of the article stream (7),
wherein the exerting step comprises discharging, with at least one seizing unit (25) comprising at least two shanks (28, 28′) located opposite each other, the at least one irregularly aligned beverage container (5) from the article stream (7) by lifting the at least one irregularly aligned beverage container (5),
wherein the discharging step comprises dipping the at least one seizing unit (25) into the article stream (7) to receive the at least one irregularly aligned beverage container (5), and then increasing the distance between the at least two shanks (28, 28′) to move away an adjacent regularly conveyed article (3), and then decreasing the distance between the at least two shanks (28, 28′) to clasp the at least one irregularly aligned beverage container (5).

### Claim 11 (depends on 10)

The method of claim 10, wherein the at least one seizing unit (25), during lifting the at least one irregularly aligned beverage container (5), supports a regularly conveyed article (3) that immediately succeeds or precedes, in the movement direction of the article stream (7), the lifted article.

### Claim 12 (depends on 11)

The method of claim 11, wherein the seizing unit (25) clasps the at least one irregularly aligned beverage container (5).

### Claim 13 (depends on 12)

The method of claim 12, wherein the at least one seizing unit (25) comprises an air cushion (47).

### Claim 14 (depends on 10)

The method of claim 10, wherein the at least one seizing unit (25) is suspended from a gantry system and is moved along the gantry system.

### Claim 15

The method of 10, wherein the at least one seizing unit (25) is moved by a parallel kinematic robot.

### Claim 16 (depends on 10)

The method of claim 10, wherein the at least one seizing unit (25) is moved by a rope system (35).

### Claim 17 (depends on 10)

The method of claim 10, in which the at least one seizing unit (25) is moved by at least one unmanned aircraft (33).

### Claim 18 (depends on 10)

The method of claim 10, wherein at least one seizing unit (25) is swivelably movable by a ball joint (26).

### Claim 19 (depends on 10)

The method of claim 10, wherein the exerting step further comprises:
rotating the at least one irregularly aligned beverage container (5) about an axis that is approximately perpendicular to the ground,
inclining at least one regularly conveyed (3) of the article stream (7) in relation to the at least one irregularly aligned beverage container (5),
dipping at least one separator element (22) between the at least one irregularly aligned beverage container (5) and at least one regularly conveyed article (3) of the article stream (7), wherein at least one regularly conveyed article (3) is immediately adjacent to the at least one irregularly aligned beverage container (5),
applying a vibration to the at least one irregularly aligned beverage container (5),
pushing the at least one irregularly aligned beverage container (5) in an upward direction by compressed air and thus removes the acted upon at least one irregularly aligned beverage container (5) from the article stream (7), or
at least one opening formed along a transport path for the article stream (7) through which opening the at least one irregularly aligned beverage container (5) falls and thus removes the at least one irregularly aligned beverage container (5) from the article stream (7).

### Claim 20

A method (100) used to handle irregularly aligned beverage container (5) of an article stream (7) comprising:
identifying at least one irregularly aligned beverage container (5) in an article stream (7) as an error;
correcting to resolve the error, the correcting step comprising removing from the article stream (7) the at least one irregularly aligned beverage container (5) previously identified, or transferring to a regular orientation of the particular at least one irregularly aligned beverage container (5) previously identified; and
exerting a defined action temporally before or in temporal overlap with the correcting step upon the at least one irregularly aligned beverage container (5) previously identified or upon regularly conveyed at least one article (3) of the article stream (7),
wherein the exerting step comprises discharging, with at least one seizing unit (25) comprising at least two shanks (28, 28′) located opposite each other, the at least one irregularly aligned beverage container (5) from the article stream (7) by lifting the at least one irregularly aligned beverage container (5),
wherein the at least one seizing unit (25) penetrates into the at least one irregularly aligned beverage container (5).

### Claim 21 (depends on 20)

The method of claim 20, wherein the at least one seizing unit (25), during lifting the at least one irregularly aligned beverage container (5), supports a regularly conveyed article (3) that immediately succeeds or precedes, in the movement direction of the article stream (7), the lifted article.

### Claim 22 (depends on 21)

The method of claim 21, wherein the seizing unit (25) clasps the at least one irregularly aligned beverage container (5).

### Claim 23 (depends on 22)

The method of claim 22, wherein the at least one seizing unit (25) comprises an air cushion (47).

### Claim 24 (depends on 20)

The method of claim 20, wherein the exerting step further comprises:
rotating the at least one irregularly aligned beverage container (5) about an axis that is approximately perpendicular to the ground,
inclining at least one regularly conveyed (3) of the article stream (7) in relation to the at least one irregularly aligned beverage container (5),
dipping at least one separator element (22) between the at least one irregularly aligned beverage container (5) and at least one regularly conveyed article (3) of the article stream (7), wherein at least one regularly conveyed article (3) is immediately adjacent to the at least one irregularly aligned beverage container (5), or
applying a vibration to the at least one irregularly aligned beverage container (5),
pushing the at least one irregularly aligned beverage container (5) in an upward direction by compressed air and thus removes the acted upon at least one irregularly aligned beverage container (5) from the article stream (7), or
at least one opening formed along a transport path for the article stream (7) through which opening the at least one irregularly aligned beverage container (5) falls and thus removes the at least one irregularly aligned beverage container (5) from the article stream (7).

### Claim 25 (depends on 20)

The method of claim 20, wherein the at least one seizing unit (25) is suspended from a gantry system and is moved along the gantry system, is moved by a parallel kinematic robot, is moved by a rope system (35, is moved by at least one unmanned aircraft (33), or is swivelably movable by a ball joint (26).