- Number: US 11,115,844 B2
- Document ID: US11115844B2
- Status: Granted
- Kind: B2
- Application number: 15/574,704
- Filed: 2015-05-20
- Published: 2018-05-31
- Granted: 2021-09-07
- Earliest claimed: 2015-05-20
- Assignees: Telefonaktiebolaget LM Ericsson (publ)
- Applicants: Telefonaktiebolaget Lm Ericsson (Publ)
- Inventors: Anders Johansson
- Web page: https://patentgrep.com/patent/US11115844B2

## CPC

- H04W 24/08: Testing, {supervising or monitoring} using real traffic
- H04L 5/0053: {Allocation of signalling, i.e. of overhead other than pilot signals}
- H04L 5/0064: {Rate requirement of the data, e.g. scalable bandwidth, data priority}
- H04W 52/0203: {in the radio access network or backbone network of wireless communication networks}
- H04W 72/044: based on the type of the allocated resource
- H04W 72/1263: Mapping of traffic onto schedule, e.g. scheduled allocation or multiplexing of flows
- H04W 72/23: in the downlink direction of a wireless link, i.e. towards a terminal
- H04L 5/0007: {the frequencies being orthogonal, e.g. OFDM(A) or DMT}
- Y02D 30/70: in wireless communication networks
- H04W: WIRELESS COMMUNICATION NETWORKS (broadcast communication H04H; communication systems using wireless links for non-selective communication, e.g. wireless extensions H04M1/72)
- H04L: TRANSMISSION OF DIGITAL INFORMATION, e.g. TELEGRAPHIC COMMUNICATION (arrangements common to telegraphic and telephonic communication H04M)
- Y02D: CLIMATE CHANGE MITIGATION TECHNOLOGIES IN INFORMATION AND COMMUNICATION TECHNOLOGIES [ICT], I.E. INFORMATION AND COMMUNICATION TECHNOLOGIES AIMING AT THE REDUCTION OF THEIR OWN ENERGY USE

## Abstract

The application relates to a method (60) for managing enhanced physical downlink control channel, EPDCCH, resources used in a wireless communications network (1) for transmitting scheduling assignments. The method (60) comprises establishing (61) a measure on load in the wireless communications network (1), and controlling (62) assigning one or more user terminals (3) to use EPDCCH resources based on the established measure on load. A corresponding wireless communications network (1) is provided, as well as computer programs and computer program products.

## Claims

### Claim 1

A method for managing enhanced physical downlink control channel, EPDCCH, resources used in a wireless communications network for transmitting scheduling assignments, the method comprising:
establishing a measure on load in a cell of the wireless communications network;
controlling a use of EPDCCH resources based on the established measure on load, wherein the controlling the use of EPDCCH resources comprises not using any EPDCCH resource to transmit control information to an EPDCCH capable user terminal while the measure on load is below a first threshold;
detecting that no EPDCCH resources or other resources are assigned in a set of one or more orthogonal frequency division multiplexing (OFDM) symbols; and
in response to detecting that no EPDCCH resources or other resources are assigned in the set of one or more OFDM symbols, causing one or more power amplifiers of a base station to enter a low power or no power mode during the set of one or more OFDM symbols.

### Claim 2 (depends on 1)

The method as claimed in claim 1, further comprising:
determining that the measure on load is above the first threshold, wherein
the controlling further comprises assigning EPDCCH resources in the cell as a result of determining that the established measure on load is above the first threshold.

### Claim 3 (depends on 1)

The method as claimed in claim 1, further comprising:
determining that the measure on load is above the first threshold, wherein
the controlling further comprises ceasing to assign EPDCCH resources in the cell as a result of determining that the established measure on load is below the first threshold.

### Claim 4 (depends on 1)

The method as claimed in claim 1, further comprising:
assigning EPDCCH resources to a user equipment (UE);
after assigning the EPDCH resources to the UE, determining that the measure on load is below the first threshold; and
in response to determining that the measure on load is below the first threshold, removing from the UE said EPDCCH resources that were assigned to the UE.

### Claim 5 (depends on 1)

The method as claimed in claim 1, further comprising setting a state in a cell of the wireless communications network to EPDCCH disabled based on the established measure on load, wherein
the step of controlling the use of EPDCCH resources based on the established measure on load comprises determining that the state in the cell is set to EPDCCH disabled and not assigning EPDCCH resources as a result of determining that the state in the cell is set to EPDCCH disabled.

### Claim 6 (depends on 1)

The method as claimed in claim 1, wherein the establishing the measure on the load comprises establishing, for the cell of the wireless communications network, utilization of downlink physical resource blocks, average number of scheduling entities per transmission time interval, utilization of control channel elements of a physical downlink control channel, or peak number of uplink grants per frame.

### Claim 7 (depends on 1)

The method as claimed in claim 1, wherein the method is performed in a network node.

### Claim 8 (depends on 1)

A computer program product comprising a non-transitory computer readable medium storing a computer program for a network node for management of an enhanced physical downlink control channel, EPDCCH, resources used in a wireless communications network, the computer program comprising computer program code, which, when executed on at least one processor in the network node causes the network node to perform the method according to claim 1.

### Claim 9

A wireless communications network node for managing enhanced physical downlink control channel (EPDCCH) resources used in a wireless communications network for transmitting scheduling assignments, the wireless communications network node comprising:
a memory; and
processing circuitry coupled to the memory, wherein the wireless communications network node is configured to:
establish a measure on load in a cell of the wireless communications network,
control a use of EPDCCH resources based on the established measure on load, wherein the wireless communications network is configured to control the use of EPDCCH resources by performing a process that includes not using any EPDCCH resource to transmit control information to an EPDCCH capable user terminal while the measure on load is below the first threshold;
detect whether there are no EPDCCH resources or other resources are assigned in certain orthogonal frequency division multiplexing (OFDM) symbols; and
cause one or more power amplifiers of a base station to enter a low power or no power mode during the certain OFDM symbols as a result of detecting that no EPDCCH resources or other resources are assigned in the certain OFDM symbols.

### Claim 10 (depends on 9)

The wireless communications network node as claimed in claim 9, wherein the process further includes assigning EPDCCH resources in the cell as a result of determining that the established measure on load is above the first threshold.

### Claim 11 (depends on 9)

The wireless communications network node as claimed in claim 9, wherein the process further includes ceasing to assign EPDCCH resources in the cell as a result of determining that the established measure on load is below the first threshold.

### Claim 12 (depends on 9)

The wireless communications network node as claimed in claim 9, wherein the process further includes:
assigning EPDCCH resources to a user equipment (UE);
after assigning EPDCCH resources to the UE, determining that the measure on load is below the first threshold; and
in response to determining that the measure on load is below the first threshold, removing from the UE said EPDCCH resources that were assigned to the UE.

### Claim 13 (depends on 9)

The wireless communications network node as claimed in claim 9, wherein the process further includes:
setting a state in a cell of the wireless communications network to EPDCCH disabled based on the established measure on load;
determining that the state in the cell is set to EPDCCH disabled; and
not assigning EPDCCH resources as a result of determining that the state in the cell is set to EPDCCH disabled.

### Claim 14 (depends on 9)

The wireless communications network node as claimed in claim 9, configured to establish the measure on the load by establishing, for the cell of the wireless communications network, utilization of downlink physical resource blocks, average number of scheduling entities per transmission time interval, utilization of control channel elements of a physical downlink control channel or peak number of uplink grants per frame.

### Claim 15 (depends on 9)

The wireless communications network as claimed in claim 9, wherein the process further includes not assigning any new user equipments (UEs) entering the cell to monitor any EPDCCH resources while the measure on load is below the first threshold.

### Claim 16 (depends on 1)

The method of claim 1, wherein the controlling the use of EPDCCH resources further comprises:
determining that the measure on load is below the first threshold; and
in response to determining that the measure on load is below the first threshold, not assigning any new user equipments (UEs) entering the cell to monitor any EPDCCH resources while the measure on load is below the first threshold.