# US 10,953,961 B2 · Techniques in the upstream oil and gas industry

> Agents: this data is available as JSON from the patentgrep API and MCP server — see https://patentgrep.com/llms.txt

- Number: US 10,953,961 B2
- Document ID: US10953961B2
- Status: Granted
- Kind: B2
- Application number: 15/476,593
- Filed: 2017-03-31
- Published: 2017-10-05
- Granted: 2021-03-23
- Earliest claimed: 2016-04-01
- Assignees: Mirade Consultants Ltd.
- Applicants: Mirade Consultants Ltd.
- Inventors: Timothy Robert Baker
- Web page: https://patentgrep.com/patent/US10953961B2

## CPC

- B63B 35/44: Floating buildings, stores, drilling platforms, or workshops, e.g. carrying water-oil separating devices {(construction methods for floating offshore platforms B63B75/00)}
- B63B 25/12: closed
- B63B 27/25: for fluidised bulk material
- B63B 27/34: using pipe-lines {(anchoring arrangements for special vessels with mooring turrets B63B21/507; buoys specially adapted for mooring a vessel and for transferring fluids, e.g. liquids B63B22/021)}
- E02B 17/00: Artificial islands mounted on piles or like supports, e.g. platforms on raisable legs {or offshore constructions}; Construction methods therefor ({construction methods for floating platforms B63B75/00}; anchoring floating platforms B63B21/00; floating platforms, e.g. anchored, B63B35/44; {underwater reservoirs B65D88/78})
- E21B 41/0064: {Carbon dioxide sequestration (storing fluids in porous layers B65G5/005)}
- E21B 43/01: specially adapted for obtaining from underwater installations
- E21B 43/164: {Injecting CO2 or carbonated water (in combination with organic material C09K8/594)}
- E21B 43/40: Separation associated with re-injection of separated materials {(E21B43/385 takes precedence)}
- B63B 2035/4473: {Floating structures supporting industrial plants, such as factories, refineries, or the like}
- B63B 2035/4486: {Floating storage vessels, other than vessels for hydrocarbon production and storage, e.g. for liquid cargo}
- E02B 2017/0056: {Platforms with supporting legs}
- Y02C 20/40: of CO2
- Y02P 90/70: Combining sequestration of CO2 and exploitation of hydrocarbons by injecting CO2 or carbonated water in oil wells
- B63B: SHIPS OR OTHER WATERBORNE VESSELS; EQUIPMENT FOR SHIPPING (arrangements of vessel ventilation, heating, cooling, or air-conditioning B63J2/00; floating substructures as supports of dredgers or soil-shifting machines E02F9/06)
- E02B: HYDRAULIC ENGINEERING (ship-lifting E02C; dredging E02F)
- E21B: EARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
- Y02C: CAPTURE, STORAGE, SEQUESTRATION OR DISPOSAL OF GREENHOUSE GASES [GHG]
- Y02P: CLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS

## Abstract

CO2 in the liquid or super-critical state is delivered by at least one carrier vessel from at least one CO2 storage site, which may be an onshore site, to an integrated offshore facility. The integrated offshore facility is provided with at least one on-site storage tank or vessel adapted to store CO2 in the liquid or super-critical state and with equipment for marine transfer of CO2 in the liquid or super-critical state. CO2 is utilised as required from said at least one on-site storage tank or vessel for EOR at said offshore site or for EGR at said offshore site by injection into a sub-sea oil or natural gas bearing reservoir and recovery of oil and/or natural gas from a resulting production stream.

## Claims

### Claim 1

A method for enhancing offshore oil recovery using carbon dioxide (CO2) or for enhancing offshore gas recovery using CO2 comprising the steps of:
delivering CO2 in a liquid state or a super-critical state by at least one carrier vessel from at least one CO2 storage site to an offshore facility provided with at least one on-site storage unit, selected from subsea tanks or internal tanks within a hull or other floating structure of the offshore facility, and with marine transfer equipment configured to transfer CO2 in said state from the carrier vessel to the on-site storage unit;
storing the CO2 in said state in the on-site storage unit; and
utilizing the CO2 from said at least one on-site storage unit for enhanced oil recovery at said offshore site or for enhanced gas recovery at said offshore site both at times when a said carrier vessel is present at said offshore facility and at times when no carrier vessel is present at said offshore facility by injecting the CO2 into a sub-sea oil or natural gas bearing reservoir and recovering oil and/or natural gas from a resulting production stream;
wherein at least a portion of the CO2 delivered to said facility by said at least one carrier vessel comprises CO2 from a production stream at a second offshore facility wherein said CO2 is stored at the second offshore facility in the liquid or super-critical state and transferred at the second offshore facility to said at least one carrier vessel.

### Claim 2 (depends on 1)

A method according to claim 1, wherein said at least one on-site storage unit comprises a separate floating storage and offloading hulled vessel without oil or natural gas production facilities that comprises said internal storage tanks.

### Claim 3 (depends on 1)

A method according to claim 1, wherein said at least one on-site storage unit comprises a separate hulled vessel that is provided with:
said internal storage tanks;
first plant and equipment configured to process CO2-laden hydrocarbon production streams, separate CO2 from production fluids, and process and apply the necessary pressure and temperature regulation to CO2 so that it reaches the said state; and
second plant and equipment to achieve the requisite CO2 pressure and temperature for injection into the a sub-sea oil field or a sub-sea natural gas field;
whereby the said separate hulled vessel is configured to be supplied for enhanced recovery of oil using CO2 or for enhanced recovery of gas using CO2 at an offshore facility not otherwise equipped for enhanced recovery of oil or gas using CO2, and is adapted to be towed away from said facility when no longer required thereat for use at a different offshore facility.

### Claim 4 (depends on 1)

A method according to claim 1, wherein the offshore facility further comprises separation equipment configured for separating CO2 from the production stream for direct re-injection or for storage in the at least one on-site storage unit.

### Claim 5 (depends on 1)

A method according to claim 1, wherein the at least one CO2 storage site comprises at least one onshore site to which CO2 is delivered by at least one of pipeline, road and rail from at least one facility in which CO2 is produced as a waste product; and wherein the CO2 is liquefied or rendered supercritical at one of the said facility and the onshore site.

### Claim 6

A method for producing oil and or gas at an offshore facility, comprising the steps of:
separating CO2 at said offshore facility from a production stream at said offshore facility,
storing said CO2 in a liquid or supercritical state in at least one on-site storage unit, selected from subsea tanks or internal tanks within a hull or other floating structure of the offshore facility,
transferring CO2 in said liquid or supercritical state from the at least one on-site storage unit to a carrier vessel using marine transfer equipment provided at the offshore facility, and
delivering the transferred CO2 to a second facility using the carrier vessel for use in enhancing offshore oil recovery using CO2 or for enhancing offshore gas recovery using CO2 at the second facility.

### Claim 7

An offshore oil or natural gas facility provided with:
at least one on-site storage unit, selected from subsea tanks or internal tanks within a hull or other floating structure of the offshore oil or natural gas facility, adapted to store CO2 in a liquid or a super-critical state;
marine transfer equipment configured to transfer CO2 in said state from said at least one on-site storage unit to a carrier vessel;
recovery equipment configured to recover oil and/or natural gas from a hydrocarbon production stream;
first plant and equipment which has the capability to process CO2-laden hydrocarbon production streams, separate CO2 from production fluids, and to process and apply the necessary pressure and temperature regulation to the separated CO2 so that it reaches said state; and
second plant and equipment coupled to the first plant and equipment and to the at least one on-site storage unit, to store the separated CO2 in said at least one on-site storage unit.