# US 10,871,146 B2 · Methods and systems for generating wind turbine control schedules

> Agents: this data is available as JSON from the patentgrep API and MCP server — see https://patentgrep.com/llms.txt

- Number: US 10,871,146 B2
- Document ID: US10871146B2
- Status: Granted
- Kind: B2
- Application number: 15/738,183
- Filed: 2016-06-29
- Published: 2018-06-28
- Granted: 2020-12-22
- Earliest claimed: 2015-06-30
- Assignees: Vestas Wind Systems A/S
- Applicants: Vestas Wind Systems A/S
- Inventors: Chris Spruce; Kelvin Hales; Judith Turner
- Web page: https://patentgrep.com/patent/US10871146B2

## CPC

- F03D 7/0292: {to reduce fatigue}
- F03D 7/046: {with learning or adaptive control, e.g. self-tuning, fuzzy logic or neural network}
- F03D 7/048: {controlling wind farms}
- F03D 17/00: Monitoring or testing of wind motors, e.g. diagnostics (testing during commissioning of wind motors F03D13/30)
- F03D 80/50: Maintenance or repair
- G05B 13/024: {in which a parameter or coefficient is automatically adjusted to optimise the performance}
- F05B 2270/20: to optimise the performance of a machine
- F05B 2270/332: Maximum loads or fatigue criteria
- F05B 2270/335: Output power or torque
- Y02E 10/72: Wind turbines with rotation axis in wind direction
- F03D: WIND MOTORS
- G05B: CONTROL OR REGULATING SYSTEMS IN GENERAL; FUNCTIONAL ELEMENTS OF SUCH SYSTEMS; MONITORING OR TESTING ARRANGEMENTS FOR SUCH SYSTEMS OR ELEMENTS (systems for controlling or regulating non-electric variables G05D; systems for regulating electric or magnetic variables G05F; control devices or systems insofar as characterised by mechanical features only G05G)
- F05B: INDEXING SCHEME RELATING TO WIND, SPRING, WEIGHT, INERTIA OR LIKE MOTORS, TO MACHINES OR ENGINES FOR LIQUIDS COVERED BY SUBCLASSES F03B, F03D AND F03G
- Y02E: REDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION

## Abstract

A method of generating a control schedule for a wind turbine is provided, the control schedule indicating how the turbine maximum power level varies over time, the method comprising: receiving input indicative of the maximum number of times that each of one or more turbine components are to be replaced over the remaining lifetime of the turbine; determining a value indicative of the current remaining fatigue lifetime of the turbine, or one or more of the turbine components, based on measured wind turbine site and/or operating data; and varying a parameter of an initial predefined control schedule that specifies how the turbine maximum power level varies over time. The varying is performed by: (i) adjusting the parameter of the initial predefined control schedule; (ii) estimating the future fatigue lifetime consumed by the wind turbine, or one or more turbine components, over the duration of the varied control schedule, based upon the varied control schedule and accounting for the replacements of the one or more turbine components; and (iii) repeating steps (i) and (ii) until the estimated future fatigue lifetime consumed by the wind turbine or each of the one or more turbine components is sufficient to allow a target minimum wind turbine life to be reached.

## Claims

### Claim 1

A method of generating a control schedule for a wind turbine, the method comprising:
receiving an input indicative of a maximum number of times that each of one or more components of the wind turbine are to be replaced over a remaining lifetime of the wind turbine;
determining, based on one or both of site data and operating data of the wind turbine, a value indicative of a current remaining fatigue lifetime of the wind turbine or of one or more of the components; and
generating a control schedule for the wind turbine that specifies how a maximum power level of the wind turbine varies over time, wherein generating the control schedule comprises:
i) adjusting a parameter of a current iteration of the control schedule to generate a varied control schedule;
ii) estimating a future fatigue lifetime consumed by the wind turbine, or of the one or more components, over a duration of the varied control schedule, based upon the varied control schedule and accounting for replacements of the one or more components; and
iii) repeating (i) and (ii) until the estimated future fatigue lifetime is sufficient to reach a target minimum wind turbine life of the wind turbine.

### Claim 2 (depends on 1)

The method according to claim 1, wherein (iii) further comprises maximizing energy capture over a lifetime of the wind turbine.

### Claim 3 (depends on 1)

The method according to claim 1, wherein the control schedule indicates an amount of power by which the wind turbine may be over-rated above a rated power.

### Claim 4 (depends on 1)

The method according to claim 1, wherein (i) further comprises adjusting, for each component of one or more of the components, a number of times that the component may be replaced over the remaining lifetime of the wind turbine.

### Claim 5 (depends on 4)

The method according to claim 4, wherein (i) further comprises adjusting, for each component of one or more of the components, when the component may be replaced during the remaining lifetime of the wind turbine.

### Claim 6 (depends on 1)

The method according to claim 1, wherein the target minimum wind turbine life is a predetermined target value corresponding to a design lifetime of the wind turbine.

### Claim 7 (depends on 1)

The method according to claim 1, further comprising receiving an input indicative of a user-defined value of the target minimum wind turbine life.

### Claim 8 (depends on 1)

The method according to claim 1, wherein an initial iteration of the control schedule specifies a relative variation of the maximum power level over time.

### Claim 9 (depends on 1)

The method according to claim 1, wherein determining the value indicative of the current remaining fatigue lifetime comprises applying sensor data from one or more sensors of the wind turbine to one or more lifetime usage estimation algorithms.

### Claim 10 (depends on 1)

The method according to claim 1, wherein determining the value indicative of the current remaining fatigue lifetime comprises using data from a condition monitoring system.

### Claim 11 (depends on 1)

The method according to claim 1, wherein determining the value indicative of the current remaining fatigue lifetime comprises using sensor data obtained from sensors of a wind power plant in combination with a site check program that determines loads acting on the one or more components based upon the sensor data sensors and parameters relating to the wind power plant and to the design of the wind turbine.

### Claim 12 (depends on 11)

The method according to claim 11, wherein the sensor data includes sensor data collected prior to one or both of commissioning and construction of the wind turbine or the wind power plant.

### Claim 13 (depends on 1)

The method according to claim 1, wherein adjusting the parameter comprises applying an offset to the control schedule.

### Claim 14 (depends on 1)

The method according to claim 1, wherein adjusting the parameter comprises applying an amplification, a de-amplification, or a gain factor to the current iteration of the control schedule.

### Claim 15 (depends on 1)

The method according to claim 1, wherein the parameter is adjusted until all, or substantially all, of a fatigue life of a most-heavily loaded component is consumed over the duration of the schedule.

### Claim 16 (depends on 15)

The method according to claim 15, wherein the parameter is adjusted by equalizing areas of a curve above and below a line showing fatigue damage incurred for the wind turbine operating with a maximum power level set at a site-specific capability for a desired lifetime.

### Claim 17 (depends on 1)

The method according to claim 1, wherein an initial iteration of the control schedule specifies a gradient of a variation of the maximum power level over time.

### Claim 18 (depends on 17)

The method according to claim 17, wherein adjusting the parameter comprises adjusting the gradient.

### Claim 19 (depends on 1)

The method according to claim 1, wherein the control schedule is indicative of an amount of fatigue damage that should be incurred over time, the method further comprising operating the wind turbine, based on one or more lifetime usage estimation algorithms, to incur fatigue damage at a rate indicated by the control schedule.

### Claim 20 (depends on 1)

The method according to claim 1, further comprising providing the control schedule to a wind turbine controller to control the power output of the wind turbine.

### Claim 21 (depends on 1)

The method according to claim 1, wherein the one or more components include one or more of: blades, pitch bearing, pitch actuation system, hub, main shaft, main bearing, gearbox, generator, converter, yaw drive, yaw bearing, or transformer.

### Claim 22

A controller comprising:
a memory;
a processor communicatively coupled to the memory and configured to perform an operation, comprising:
receiving an input indicative of a maximum number of times that each of one or more components of a wind turbine are to be replaced over a remaining lifetime of the wind turbine;
determining, based on one or more both of site data and operating data of the wind turbine, a value indicative of a current remaining fatigue lifetime of the wind turbine or of one or more of the components; and
generating a control schedule for the wind turbine that specifies how a maximum power level of the wind turbine varies over time, wherein generating the control schedule comprises:
i) adjusting a parameter of a current iteration of the control schedule to generate a varied control schedule;
ii) estimating a future fatigue lifetime consumed by the wind turbine, or of the one or more components, over a duration of the varied control schedule, based upon the varied control schedule and accounting for replacements of the one or more components; and
iii) repeating (i) and (ii) until the estimated future fatigue lifetime is sufficient to reach a target minimum wind turbine life of the wind turbine.

### Claim 23

A method of generating a control schedule for a wind power plant comprising two or more wind turbines, the method comprising:
receiving an input indicative of a maximum number of times that each of one or more components, for each wind turbine of the two or more wind turbines, are to be replaced over a remaining lifetime of the wind turbine;
determining, based on one or both of site data and operating data of each wind turbine of the two or more wind turbines, a value indicative of a current remaining fatigue lifetime of the wind turbine or of one or more components of the wind turbine; and
generating a control schedule for the two or more wind turbines that specifies how a maximum power level of each wind turbine of the two or more wind turbines varies over time, wherein generating the control schedule comprises:
i) adjusting a parameter of a current iteration of the control schedule to generate a varied control schedule;
ii) estimating a future fatigue lifetime consumed by the two or more wind turbines, or of the one or more components, over a duration of the varied control schedule, based upon the varied control schedule and accounting for replacement of the one or more components using a site check program that determines loads acting on the one or more components based upon sensor data obtained from sensors of the wind power plant and parameters relating to the wind power plant and to the design of the wind turbine, and includes interactions between the two or more wind turbine; and
iii) repeating (i) and (ii) until the estimated future fatigue lifetime is sufficient to reach a target minimum wind turbine life of the two or more wind turbines.

### Claim 24 (depends on 23)

The method according to claim 23, wherein the sensor data includes sensor data collected prior to one or both of commissioning and construction of the wind turbine or of the wind power plant.

### Claim 25 (depends on 23)

The method according to claim 23, wherein (iii) is further constrained such that for any given time period within the control schedule, a sum of a power of the two or more wind turbines does not exceed an amount of power that can be carried in a connection from the wind power plant to a grid.