# US 10,768,262 B2 · Managing the determination of a transfer function of a measurement sensor

> Agents: this data is available as JSON from the patentgrep API and MCP server — see https://patentgrep.com/llms.txt

- Number: US 10,768,262 B2
- Document ID: US10768262B2
- Status: Granted
- Kind: B2
- Application number: 15/691,414
- Filed: 2017-08-30
- Published: 2019-02-28
- Granted: 2020-09-08
- Earliest claimed: 2017-08-30
- Assignees: Analog Devices Global Unlimited Campany
- Applicants: Analog Devices Global Unlimited Company
- Inventors: Seyed Amir Ali Danesh; John Stuart
- Web page: https://patentgrep.com/patent/US10768262B2

## CPC

- G01R 35/00: Testing or calibrating of apparatus covered by the other groups of this subclass
- G01R 11/25: Arrangements for indicating or signalling faults
- G01R 11/56: Special tariff meters
- G01R 15/04: Voltage dividers
- G01R 21/007: {Adapted for special tariff measuring (G01R21/01, G01R21/02, G01R21/08, G01R21/10, G01R21/1278 and G01R21/1333 take precedence)}
- G01R 21/133: by using digital technique
- G01R 21/1333: {adapted for special tariff measuring}
- G01R 27/28: Measuring attenuation, gain, phase shift or derived characteristics of electric four pole networks, i.e. two-port networks; Measuring transient response (in line transmission systems H04B3/46)
- G01R 35/04: of instruments for measuring time integral of power or current
- G01R: MEASURING ELECTRIC VARIABLES; MEASURING MAGNETIC VARIABLES (indicating correct tuning of resonant circuits H03J3/12)

## Abstract

The present disclosure relates to the control of an operation of a monitor module of an electrical measurement system, where the monitor module has a plurality of operating states, including a) monitor at least a first measurement sensor of the utility meter to determine a first monitor result comprising an estimate of a transfer function of the first measurement sensor and a corresponding certainty value indicative of the accuracy of the estimate of the transfer function of the first measurement sensor, wherein the first measurement sensor is for measuring a first electrical property, and b) do not monitor any measurement sensor of the electrical measurement system.

## Claims

### Claim 1

An apparatus for controlling an operation of an electrical measurement system, the apparatus being configured to:
include a plurality of operating states comprising at least:
a) a first operating state to monitor at least a first measurement sensor for measuring a first electrical property of a utility meter to determine a first monitor result comprising:
1) an estimate of a transfer function of the first measurement sensor, and
2) a corresponding certainty value of the estimate of the transfer function of the first measurement sensor,
b) a second operating state which does not monitor the first measurement sensor of the electrical measurement system; and, wherein the apparatus is also configured for:
using the first operating state to determine the first monitor result of the utility meter;
selecting one of the plurality of operating states, wherein the selecting is based at least in part on at least one of the first monitor result or the corresponding certainty value; and
performing a control action for controlling the operation to implement the selected operating state.

### Claim 2 (depends on 1)

The apparatus of claim 1, wherein in response to selecting the first operating state, the control action comprises communicating a first control instruction to monitor the first measurement sensor for a first individual run length of time to determine the first monitor result.

### Claim 3 (depends on 2)

The apparatus of claim 2, wherein the first individual run length of time is a specified length of time that is a portion of the first monitoring time window.

### Claim 4 (depends on 3)

The apparatus of claim 3, further configured to determine the first individual run length of time in order to achieve a desired level of accuracy for the estimate of the transfer function of the first measurement sensor by comparing one or more previously determined certainty values against a target certainty value.

### Claim 5 (depends on 2)

The apparatus of claim 2, wherein the first individual run length of time is a variable length of time and the apparatus is further configured to determine the first individual run length of time.

### Claim 6 (depends on 5)

The apparatus of claim 5, further configured to:
determine the first individual run length of time based at least in part on one or more previously determined certainty values corresponding to a respective one or more previously determined estimates of the transfer function of the first sensor.

### Claim 7 (depends on 1)

The apparatus of claim 1, further configured to select one of the plurality of operating states based at least in part on one or more previously determined certainty values.

### Claim 8 (depends on 7)

The apparatus of claim 7, configured to select one of the plurality of operating states by:
determining a first utilization target based on the one or more previously determined certainty values, wherein the first utilization target is indicative of a target total portion of the first monitoring time window to be spent determining monitor results relating to the first measurement sensor; and
selecting one of the plurality of operating states based at least in part on the first utilization target.

### Claim 9 (depends on 8)

The apparatus of claim 8, wherein determining the first utilization target comprises:
comparing the one or more previously determined certainty values against a target minimum level of accuracy to be achieved for the estimate of the transfer function of the first measurement sensor, and
in response to the one or more previously determined certainty values failing to achieve the target minimum level of accuracy, setting the first utilization target to be greater than a previous first utilization target that was in place during determination of one or more previously determined estimates of the transfer function of the first sensor.

### Claim 10 (depends on 8)

The apparatus of claim 8, wherein determining the first utilization target comprises:
comparing the one or more previously determined certainty values against a target maximum level of accuracy, and
in response to the one or more previously determined certainty values are indicative of the target maximum level of accuracy, setting the first utilization target to be less than a previous first utilization target that was in place during determination of one or more previously determined estimates of the transfer function of the first measurement sensor.

### Claim 11 (depends on 8)

The apparatus of claim 8, wherein selecting one of the plurality of operating states comprises comparing the first utilization target against an updated first utilization,
wherein the updated first utilization is indicative of a portion of the first monitoring time window that has already been spent determining monitor results relating to the first measurement sensor.

### Claim 12 (depends on 1)

The apparatus of claim 1, further configured to select one of the plurality of operating states such that time spent to determine the monitor results relating to the first measurement sensor during a monitoring time window is sufficient for estimates of the transfer function of the first measurement sensor determined during the monitoring time window to achieve a desired level of accuracy for a given measurement of a first electrical property.

### Claim 13 (depends on 1)

The apparatus of claim 1, wherein the plurality of operating states further comprises:
c) a third operating state to monitor at least a second measurement sensor of the electrical measurement system to determine a second monitor result comprising an estimate of the transfer function of the second measurement sensor and a corresponding certainty value of the estimate of the transfer function of the second measurement sensor, and wherein
the second measurement sensor is for measuring a second electrical property.

### Claim 14 (depends on 13)

The apparatus of claim 13 wherein in response to selecting the third operating state, the control action comprises communicating a second control instruction to monitor the second measurement sensor for a second individual run specified length of time to determine the second monitor result.

### Claim 15 (depends on 14)

The apparatus of claim 14, wherein the second individual run length of time is a fixed length of time.

### Claim 16 (depends on 14)

The apparatus of claim 14, wherein the second individual run length of time is a variable length of time, and the apparatus is further configured to determine the second individual run length of time.

### Claim 17 (depends on 16)

The apparatus of claim 16, further configured to:
determine the second individual run length of time based at least in part on the one or more previously determined certainty values corresponding to a respective one or more previously determined estimates of the transfer function of the second measurement sensor.

### Claim 18 (depends on 13)

The apparatus of claim 13, further configured to select one of the plurality of dule operating states based at least in part on one or more previously determined certainty values corresponding to a respective one or more previously determined estimates of the transfer function of the second measurement sensor.

### Claim 19 (depends on 13)

The apparatus of claim 13, further configured to select one of the plurality of operating states based at least in part on at least one of a first target level of accuracy for one or more estimates relating to the first measurement sensor or a second target level of accuracy for estimates relating to the second measurement sensor.

### Claim 20 (depends on 13)

The apparatus of claim 13, further configured to select one of the plurality of operating states by:
determining a first utilization target based on one or more previously determined certainty values corresponding to the respective one or more previously determined estimates of the transfer function of the first sensor, wherein the first utilization target is indicative of a target total portion of the monitoring time window to be spent determining the monitor results relating to the first measurement sensor of the electrical measurement system;
determining a second utilization target based on the one or more previously determined certainty values corresponding to the respective one or more previously determined estimates of the transfer function of the second sensor, wherein the second utilization target is indicative of a target total portion of the monitoring time window to be spent determining the monitor results relating to the second measurement sensor of the electrical measurement system; and
selecting one of the plurality of operating states based at least in part on the first utilization target and the second utilization target.

### Claim 21 (depends on 20)

The apparatus of claim 20, wherein selecting one of the plurality of operating states comprises comparing the first utilization target against an updated first utilization target and comparing the second utilization target against an updated second utilization target, wherein
the updated first utilization target is indicative of a proportion portion of the first monitoring time window that has already been spent to determine the monitor results relating to the first measurement sensor, and wherein the updated second utilization target is indicative of a proportion portion of the second monitoring time window having a specified total run time that has already been spent to determinr the monitor results relating to the second measurement sensor.

### Claim 22 (depends on 13)

The apparatus of claim 13, wherein in response to selecting the third operating state, the apparatus determines a schedule of priority for operating states based on at least one of target level of accuracy of the first measurement sensor, the second measurement sensor, or the first utilization target and second utilization target.

### Claim 23 (depends on 13)

The apparatus of claim 13, wherein the the previously determined certainty value includes an aggregation of all previous corresponding certainty values for at least one of the first or second monitor result, and
based on the aggregation the priority for which measurement sensor to monitor and the operating state is selected.

### Claim 24 (depends on 1)

The apparatus of claim 1, wherein the previously determined certainty value includes an aggregation of two or more previous corresponding certainty values of the first monitor result, and
the operating state is selected based on the aggregation.

### Claim 25

An electrical measurement system for measuring at least one electrical property, the electrical measurement system comprising:
a first measurement sensor for measuring a first electrical property;
a first module configured to operate in one of a plurality of operating states comprising:
a) a first operating state to monitor at least the first measurement sensor to determine a first monitor result comprising:
1) an estimate of a transfer function of the first measurement sensor, and
2) a corresponding certainty value indicative of the accuracy of the estimate of the transfer function of the first measurement sensor,
b) a second operating state in which no measurement sensor of the electrical measurement system is monitored, and
a a second module configured to:
using the first operating state, measure the first electrical property of a utility meter to determine the first monitor result;
select one of the plurality of operating states wherein the selection is from a group consisting of the first monitor result an utilization target based on the one or more previously determined certainty values, wherein the first utilization target is indicative of a target total proportion portion of the first monitoring time window to be spent by the monitor module determining monitor results relating to the first measurement sensor; and
perform a control action for controlling the operation to implement the selected operating state.

### Claim 26

A method of controlling an electrical measurement system, the method comprising:
including a plurality of operating states comprising:
a) a first operating state to monitor at least a first measurement sensor for measuring a first electrical property of the electrical measurement system to determine a first monitor result comprising:
1) an estimate of a transfer function of the first measurement sensor, and
2) a corresponding certainty value indicative of the accuracy of the estimate of the transfer function of the first measurement sensor,
b) a second operating state in which no measurement sensor of the electrical measurement system is monitored;
using the first operating state, measure the first electrical property of a utility meter to determine the first monitor result;
selecting one of the plurality of operating states, wherein the selection is based at least in part on at least one of the first monitor result or the corresponding certainty value or a utilization target based on the one or more previously determined certainty values, wherein the first utilization target is indicative of a target total proportion portion of the first monitoring time window to be spent by the monitor module determining. monitor results relating to the first measurement sensor; and
performing a control action for controlling the operation to implement the selected operating state.

### Claim 27 (depends on 26)

A non-transitory computer readable medium storing computer readable instructions that, in response to being executed by at least one processor, cause the at least one processor to perform the method of claim 26.