# US 10,641,414 B2 · Method of filling and sealing a microtrench

> Agents: this data is available as JSON from the patentgrep API and MCP server — see https://patentgrep.com/llms.txt

- Number: US 10,641,414 B2
- Document ID: US10641414B2
- Status: Granted
- Kind: B2
- Application number: 16/000,628
- Filed: 2018-06-05
- Published: 2018-10-11
- Granted: 2020-05-05
- Earliest claimed: 2016-10-18
- Assignees: Cciip LLC
- Applicants: Corbel Communications Industries, LLC
- Inventors: Angelo J. Pino, Jr.; Daniel Urban
- Web page: https://patentgrep.com/patent/US10641414B2

## CPC

- F16L 1/11: for the detection or protection of pipes in the ground
- E02F 5/08: with digging wheels turning round an axis {(E02F5/109 takes precedence; with digging wheels per se E02F3/18)}
- E02F 5/10: with arrangements for reinforcing trenches or ditches; with arrangements for making or assembling conduits or for laying conduits or cables (laying pipes per se F16L1/00, making pipes in situ F16L1/038; laying electric cables per se H02G1/06; {drainage device- laying apparatus E02B11/02})
- E02F 5/101: {forming during digging, e.g. underground canalisations or conduits, by bending or twisting a strip of pliable material; by extrusion}
- E02F 5/12: with equipment for back-filling trenches or ditches
- E02F 5/226: {with means for processing the soil, e.g. screening belts, separators; Padding machines}
- E02F 9/245: {for preventing damage to underground objects during excavation, e.g. indicating buried pipes or the like (detection of pipes in the ground F16L1/11)}
- F16L 1/028: in the ground (F16L1/026 takes precedence)
- H02G 1/06: for laying cables, e.g. laying apparatus on vehicle
- H02G 9/02: laid directly in or on the ground, river-bed or sea-bottom; Coverings therefor, e.g. tile
- H02G 9/025: {Coverings therefor, e.g. tile}
- H02G 9/06: in underground tubes or conduits; Tubes or conduits therefor
- F16L: PIPES; JOINTS OR FITTINGS FOR PIPES; SUPPORTS FOR PIPES, CABLES OR PROTECTIVE TUBING; MEANS FOR THERMAL INSULATION IN GENERAL
- E02F: DREDGING; SOIL-SHIFTING (winning peat E21C49/00)
- H02G: INSTALLATION OF ELECTRIC CABLES OR LINES, OR OF COMBINED OPTICAL AND ELECTRIC CABLES OR LINES

## Abstract

Provided is a microtrench fill comprising concrete, a polymer, and a colorant. Also provided is a method of using the microtrench fill to fill a microtrench in a street or walkway.

## Claims

### Claim 1

A method of simultaneously filling and sealing a microtrench containing an optical fiber and/or innerduct/microduct on a roadway to return the roadway to substantially an original state with a color-matched, filled and sealed microtrench comprising:
forming a flowable concrete-based fill comprising cement, a polymer bonding agent, a colorant, an aggregate, and water, wherein the colorant provides the fill with a color substantially matching the color of the roadway, the polymer bonding agent provides adhesion to the existing roadway, and the flowable concrete-based fill is configured to flow into the microtrench from a fill device; and
filling the microtrench with the flowable concrete-based fill material from the fill device to cover the optical fiber and/or innerduct/microduct, fill and seal the microtrench and return the roadway back to an original state with the color-matched, filled and sealed microtrench in one step.

### Claim 2 (depends on 1)

The method according to claim 1, wherein the aggregate comprises sand.

### Claim 3 (depends on 1)

The method according to claim 1, wherein the aggregate comprises spoil formed by ground up roadway from cutting the mictrotrench in the roadway.

### Claim 4 (depends on 1)

The method according to claim 1, wherein the bonding agent bonds to the microtrench and provides a seal to the roadway.

### Claim 5 (depends on 1)

The method according to claim 1, further comprising altering a slump or viscosity of the flowable concrete-based fill by altering a water content to control a flow rate and application of the flowable concrete-based fill into the mictrotrench.

### Claim 6 (depends on 1)

The method according to claim 1, further comprising forming the flowable concrete-based fill so that the flowable concreted-based fill flows from the fill device into the microtrench having a width of less than 2 inches and a depth of 2 inches to 20 inches.

### Claim 7 (depends on 1)

The method according to claim 1, further comprising cutting the microtrench using a microtrencher, and laying the optical fiber cable or innerduct/microduct within the microtrench.

### Claim 8 (depends on 7)

The method according to claim 7, further comprising forming the flowable concrete-based fill so that the flowable concreted-based fill flows from the fill device into the microtrench having a width of less than 2 inches and a depth of 2 inches to 20 inches.

### Claim 9 (depends on 1)

The method according to claim 1, wherein the roadway comprises asphalt or cement.

### Claim 10 (depends on 1)

The method according to claim 1, further comprising transporting at least a portion of a spoil from the micro-trencher to a first container constructed to contain the spoil using at least one spoil transporting device; and laying the cable and/or innerduct/microduct in the micro-trench from a reel device.

### Claim 11 (depends on 10)

The method according to claim 10, wherein the steps of transporting the spoil from the micro-trencher to the first container constructed to contain spoil using a first spoil transporting device and laying at least one of the cable and innerduct/microduct in the micro-trench from a reel device are conducted using the micro-trencher using a multifunctional reel carrier, spoil material handling container device comprising:
a first truck or first trailer;
the first container constructed to contain the spoil being on the first truck or first trailer; and
the at least one spoil transporting device constructed to transfer the spoil from the micro trencher and deposit the spoil in the first container.

### Claim 12 (depends on 11)

The method according to claim 11, further comprising using the at least one spoil transporting device to transport the at least a portion of the spoil from the first container to the fill device, wherein the fill comprises at least a portion of the spoil.

### Claim 13 (depends on 11)

The method according to claim 11, wherein the at least one spoil transporting device comprises at least one vacuum device and using the first vacuum device to vacuum spoil from the micro trencher and deposit the spoil into the first container.

### Claim 14 (depends on 11)

The method according to claim 11, wherein the at least one spoil transporting device comprises a second spoil transporting device comprising at least one second vacuum device, and using the at least one second vacuum device to transfer at least a portion of the spoil from the first container to the fill device.

### Claim 15

A method of simultaneously filling and sealing a microtrench containing an optical fiber and/or innerduct/microduct on a roadway to return the roadway to substantially an original state with a filled and sealed microtrench comprising:
forming a flowable concrete-based fill comprising cement, a polymer bonding agent, an aggregate, and water, wherein the polymer bonding agent provides adhesion to the existing roadway, and the flowable concrete-based fill is configured to flow into the microtrench from a fill device; and
filling the microtrench with the flowable concrete-based fill material from the fill device to simultaneously cover the optical fiber and/or innerduct/microduct, fill and seal the microtrench and return the roadway back to an original state with the filled and sealed microtrench in one step.

### Claim 16 (depends on 15)

The method according to claim 15, wherein the aggregate comprises sand.

### Claim 17 (depends on 15)

The method according to claim 15, wherein the aggregate comprises spoil formed by ground up roadway from cutting the mictrotrench in the roadway.

### Claim 18 (depends on 15)

The method according to claim 15, wherein the bonding agent bonds to the microtrench and provides a seal to the roadway.

### Claim 19 (depends on 15)

The method according to claim 15, further comprising altering a slump or viscosity of the flowable concrete-based fill by altering a water content to control a flow rate and application of the flowable concrete-based fill into the mictrotrench.

### Claim 20 (depends on 15)

The method according to claim 15, further comprising forming the flowable concrete-based fill so that the flowable concreted-based fill flows from the fill device into the microtrench having a width of less than 2 inches and a depth of 2 inches to 20 inches.

### Claim 21 (depends on 15)

The method according to claim 15, further comprising cutting the microtrench using a microtrencher, and laying the optical fiber cable or innerduct/microduct within the microtrench.

### Claim 22 (depends on 21)

The method according to claim 21, further comprising forming the flowable concrete-based fill so that the flowable concreted-based fill flows from the fill device into the microtrench having a width of less than 2 inches and a depth of 2 inches to 20 inches.

### Claim 23 (depends on 15)

The method according to claim 15, wherein the roadway comprises asphalt or cement.

### Claim 24 (depends on 15)

The method according to claim 15, further comprising transporting at least a portion of a spoil from the micro-trencher to a first container constructed to contain the spoil using at least one spoil transporting device; and laying the cable and/or innerduct/microduct in the micro-trench from a reel device.

### Claim 25 (depends on 24)

The method according to claim 24, wherein the steps of transporting the spoil from the micro-trencher to the first container constructed to contain the spoil using a first spoil transporting device and laying at least one of the cable and innerduct/microduct in the micro-trench from a reel device are conducted using the micro-trencher using a multifunctional reel carrier, spoil material handling container device comprising:
a first truck or first trailer;
the first container constructed to contain the spoil being on the first truck or first trailer; and
the at least one spoil transporting device constructed to transfer the spoil from the micro trencher and deposit the spoil in the first container.

### Claim 26 (depends on 24)

The method according to claim 24, further comprising using the at least one spoil transporting device to transport at least a portion of the spoil from the first container to the fill device, wherein the fill comprises at least a portion of the spoil.

### Claim 27 (depends on 24)

The method according to claim 24, wherein the at least one spoil transporting device comprises the at least one vacuum device and using the first vacuum device to vacuum spoil from the micro trencher and deposit the spoil into the first container.

### Claim 28 (depends on 24)

The method according to claim 24, wherein the at least one spoil transporting device comprises a second spoil transporting device comprising at least one second vacuum device, and using the at least one second vacuum device to transfer at least a portion of the spoil from the first container to the fill device.