Abstract
A dedicated borehole for an ESP or artificial lift mechanism communicates with a sump or wellbore to collect liquids and/or condensate from one or more other bores where there can be laterals into a producing formation. If the ESP or artificial lift mechanism needs to be replaced the dedicated bore with the ESP or artificial lift mechanism can be closed off and the ESP or artificial lift mechanism removed without taking out the main bore or bores connected to the sump or wellbore. Those bores can continue to produce gas as liquids and/or condensate accumulate in the sump, sumps or wellbore. When the ESP or artificial lift mechanism is replaced the liquid can be pumped to surface without interruption of the gas production.
Claims18
A well configuration, comprising:
- at least one main borehole comprising multiple discrete laterals that drain into said main bore to conduct produced liquid from the formation into a collection sump where said main bore terminates, said main borehole conducting produced gas from the formation to a first remote location in an uphole direction;
- an auxiliary borehole further comprising an artificial lift device and terminating at said sump for selective removal of only said produced liquid to a second remote location;
- a barrier in said auxiliary bore selectively closed to allow removal of said artificial lift device while continuing to produce gas to the first remote location through said main borehole.
A production method, comprising:
- providing a main borehole comprising multiple laterals that drain back produced fluids to said main borehole with said main borehole terminating at a sump;
- providing an auxiliary borehole terminating into said sump;
- producing only liquids with an artificial lift device in said auxiliary borehole from said sump;
- producing only formation gas from said main borehole regardless of whether said auxiliary borehole is or is not in service.